The Priority Environmental Investment Programme for South Eastern Europe –
PEIP National Workshop
Developing Environmental Infrastructure Projects in the
WASTE Sector in Serbia
The Regional Solid Waste Management Scheme
Duboko (Uzice/Cacak)
Mr Cok van Schooten, Team Leader MISP
May 9, 2008, Belgrade
Part 1.
MUNICIPAL INFRASTRUCTURE SUPPORT PROGRAM
(MISP)
Part 2.
DUBOKO REGIONAL SOLID WASTE MANAGEMENT
SCHEME
PART 1
MUNICIPAL INFRASTRUCTURE SUPPORT PROGRAM
(MISP)
MAJOR GOAL :
Assistance to Serbian municipalities
in preparing infrastructure projects
for financing (NIP, EU/IPA, EBRD, KFW, ...) and construction.
Serbian communities will benefit by having better quality of
services in:
- Environmental Infrastructure
- Social Infrastructure
- Economic Infrastructure
OBJECTIVES
Strengthening the capacity of municipalities in preparation
and implementation of infrastructure projects.
Enabling municipalities and public utility companies to access
financial funds for infrastructure projects.
THREE COMPONENTS(2/3)
1. Policy dialogue and PUC transformation
Working groups (SCTM, Serbian Ministries) prepare policy recommendations
(‘Green Paper’). Review of inter-municipal co-operation models.
2. Programming and Project Preparation
MISP supports the Serbian Government on the preparation of infrastructure
projects for funding (NIP, IPA, ..) through the SCTM’s SLAP pipeline of projects.
MISP will execute Feasibility studies and recommend on Design and Tender
Documents.
>> WE ARE LOOKING FOR YOUR PROJECTS !
THREE COMPONENTS(3/3)
3. Project implementation
Tendering and supervision in the regional solid waste management projects in
Uzice (Duboko) and Pirot, and monitoring of projects in Subotica (waste water
treatment), Indjija (water supply) and the M25 Regional Road rehabilitation.
Plus: MISP provides training for the municipalities and PUCs in multi annual
planning and FIDIC contracting.
EU/EAR funded program
(history 2003-2007: 46 M€ invested incl. 18 M€ EAR grants)
Current project partners:
National Investment Plan
Environmental Protection Fund
Water Directorate
Directorate of Roads
Plus the municipal line up:
Subotica
Indjija
Uzice
Pirot
Krusevac
Leskovac
Sremska Mitrovica
Vrbas
Sabac
Prokuplje
Time span :
28 January 2008 – 27 January 2010
MISP:
Technical Assistance 3,0 M€
Consortium managed by Eptisa, Spain.
15 experts in Belgrade/10 short term experts
WHICH FIELDS OF MUNICIPAL INFRASTRUCTURE ?
ENVIRONMENT
Water supply, wastewater, solid waste management and district heating
SOCIAL
Sheltered housing, facilities for the disabled and education facilities
ECONOMY
Tourist sites, urban renewal and industrial parks.
Part 2.
DUBOKO REGIONAL SOLID WASTE
MANAGEMENT SCHEME
An excellent project example………
REGIONAL SOLID WASTE MANAGEMENT SCHEME DUBOKO
Including the closure of existing dumpsites.
(1) Present landfills
(Semi) illegal dumpsites
Some sites have lawsuits pending
No alternative
Uncontrolled
Problems with: leachate, fires, smell
Strong need for “Duboko” regional landfill
No closure plans / after care present
(2) Transfer stations
Foreseen in every municipality (ex Uzice)
Not all sites selected yet
(3) Waste separation lines
Uzice (Duboko site)
Cacak (existing)
Proposed set up
A Weighbridge
A ramp towards an unloading platform
A drum screen with an integrated plastic bags opener. The waste is
separated in a fine and coarse fraction
Two sorting lines consisting of a conveyor belt with handpicking
A magnetic separator
Planned recycle rates >>
PET bottles separated on colour
Paper/carton and (when technical
possible) plastic fraction shall be
compacted
The recycle line requires a plot of at
least 2 ha
For internal transport purposes 2
shovels are required.
Duboko
sanitary landfill
Compliance with EU Directive
Bottom liner and top liner
De-gassing (venting) foreseen
Landfill gas utilization foreseen in future
Financing
Estimated investment costs
12,6 M€
Municipalities
Environmental Protection Fund
NIP
Grant by EAR
Loan by EBRD
2,5 M€
1,5 M€
0,6 M€
3,0 M€
5,0 M€
Time lines for construction
Waste separation line Duboko: 2008
Land fill body:
2008/2009
Transfer stations:
2009
Additional activities :
- Setting up the PUC including the PIU
- Setting the Regional Solid Waste Management Policy
- Maintaining the waste separation and waste collection policies
- Master Plan for the Closure of the land fills.
Contact:
Cok van Schooten,
Team Leader MISP
Deli Radivoja 15
11000 Belgrade
+381-64-392 6068
[email protected]
www.misp-serbia.rs
Contact:
Cok van Schooten,
Team Leader MISP
Deli Radivola 15
11000 Belgrade
+381-64-392 6068
[email protected]