High Capacity Underground Coal Mining (L15)
A joint project (Scoping Study) between CSIRO Exploration & Mining and University of Queensland’s Sustainable Minerals Institute (SMI) www.csiro.au
Scoping Study Objectives
Benchmark current practices and determine what is needed to achieve a high capacity underground coal mine (15Mtpa) and optimisation of existing operations Report on strategic research directions needed to support future high capacity mining.
Identify specific, high impact research and development projects to facilitate high capacity mining.
Identify opportunities for operational, technical and postgraduate training in areas relevant to high capacity coal mining
Process
Develop a predictive model (15Mtpa coal mine) on which comprehensive research proposals would be dependent. Incorporates LW productivity, utilisation, seam characteristics, development requirements, sensitivities and cost model.
Considerations included: 1.8 – 4.5m seam thickness; LTCC and multi-seam operation Segregate the overall strategy into 7 sub-categories for further study, under the respective objectives Provide separate reports addressing the requirements of the scoping study
15Mtpa model identified key issues
Criticality of system uptime High shearer speed/power to deliver tonnages Support hydraulics for rapid support cycle times Optimise cutting cycle – uni-di; bi-di; half web Development rate increase Improved coal clearance for minimal bottlenecks
Coal Resources and Deposit Delineation
www.csiro.au
Coal Resources and Deposit Delineation
Update of UNSW thick seam database from public sources (113 mines-330 point source data)
Research Direction
To create confidence that a deposit will be able to host a 15Mtpa operation requires integrated analysis of geologic data across company boundaries at the district scale, similar to that in the ACARP Supermodel 2000 project High tonnage longwall operation will require enhanced interpretation of structure and interburden characteristics Multi-scale modeling of fault geometries and simulation of behaviour under variable rock mass, stress and mining methods
Geological and Geotechnical Assessment and Support www.csiro.au
Current Status
Greater propensity for stability problems in thick seams operations Geotechnical downtime generally occurs comparatively more frequently on the face (a shift from gateroads) Geophysical methods of rock mass characterisation are preferred but there is a lack of experienced people to interpret the information Typically 1-2 normal faults per panel
Research Direction
Implementation of real time face and gate road “Smart” monitoring which includes interpretation and control measures Determination of interaction between cutting height and operational characteristics Interaction of seams in multi-seam operations Enhanced fault detection and definition for mining through in-panel faults – possibly utilising microseismic technology
Roadway Development Systems
www.csiro.au
Current Status
Later generation, best practice mines with good conditions could attain 15Mtpa mines without major developments in mining equipment and systems Infrastructure limitations will constrain older mines from making major improvements in mine capacity, while adverse conditions generally associated with depth pose additional productivity challenges to these mines (and to later generation mines as they mature) Technology developments are currently underway that are likely to address a number of key process constraints in the short to medium term, thus providing the potential to improve system capability across all mines
Specific Research Projects
Extensible (monorail mounted) face services (e.g. ventilation, power, water, compressed air, pump out) Integrated development mining system Extensible, self advancing coal clearance system Alternative skin reinforcement and confinement measures Complementary technology developments including automation and robotics, machine guidance systems, light weight materials, face pumping systems, roadway construction and consolidation
Projected Gains
Gas and Ventilation
www.csiro.au
Longwall Gas Emissions Related to Face Production
21,000 18,000 15,000 12,000 9,000 6,000 3,000 0 0 Vent gas capacity Best practice with goaf drainage SGE 5 m3/t SGE 10 m3/t SGE 20 m3/t SGE 35 m3/t 3 6 9 12
LW Production (MTpa)
15 18
Research Direction Gas Drainage
Extensive pre-drainage of gas including optimisation of MRD gas holes for pre-drainage/deep gas drainage technology and stimulation Coordination and cooperation with petroleum and gas developers to utilise/reduce gas reservoir Optimise goaf inertisation strategies for operational use – including exclusion foams
Research Direction Spontaneous Combustion
Development of low impact inertisation systems
Heat
Development of heat extraction techniques for fixed and possibly mobile plant
Dust
Optimise coal seam water injection techniques prior to mining
Water Management
www.csiro.au
Current Status Water Consumption
Highest users have the highest losses; lowest users have the lowest losses
Water Inflow
Typical inflows range from 3-5 Ml/day; some up to 15Ml/day
Range Average Water use ML/Mtpa 55 – 192 130 Water loss ML/Mtpa 29 – 180 90
Strategic Research Directions
Reduction in water consumption and variability through integration of research into water usage, management and technology Integrated approach to hydro-geology and geotechnical aspects Underground water recycling and reuse technology
Longwall Face Equipment and Coal Transport
www.csiro.au
Current Status
Current equipment is capable of delivering at or about the 15Mt target Average production from the top 5 mines based on the last 3 years was 4,647,660 tonne The average cutting hours per year calculated from the 8 mines studied over the last 3 years was 2745 hours The average output per hour from the longwall faces was 1693 tonne
Current Status
Longwall faces cut for only 31% of the total time in a year Breakdown maintenance outweighs planned maintenance by 4 to 1 The shearer, panel belt and AFC, respectively, are the largest contributors to down time totalling over 50% Planned maintenance effort does not reflect the downtime statistics and is ad-hoc
Downtime Breakdown Longwall Downtime Allocations
30.0
25.0
20.0
15.0
10.0
5.0
0.0
S P he an ar el er C on ve yo r P ow A er FC ed O S th er up po (m rts ee tin E m gs ul e si tc ) on S ys te S ta m ta C on Tr un tro k l C on ve yo r E le ct B SL ric al S up pl y C V ru sh en til er at io n/ G as C om W m at s er S up pl y M on or ai l
Equipment
Research Directions
Further development and implementation of face automation Effective analysis of monitoring data on a real time basis for maintenance purposes Real-time maintenance prioritisation system New sensors and systems for condition monitoring
Licence to Operate
www.csiro.au
Specific Research Projects
Assessment, prediction and validation of the impact of increased mining height and width on local and regional water resources and catchments Development of realistic and achievable engineering controls for dust, noise and heat management Assess and validate current subsidence prediction methodologies for high capacity contexts