No Slide Title

Download Report

Transcript No Slide Title

A NOVEL APPROACH TO RESPONSIVE SPACE: LESSONS LEARNED BY THE DoD SPACE TEST PROGRAM (STP)

Sabrina Herrin The Aerospace Corporation Email:[email protected]

Eleni “Sam” Sims The Aerospace Corporation Email: [email protected]

INTRODUCTION

 STP serves as the primary provider of spaceflight for the entire DoD space science and technology community  Since 1967, STP has flown 168 missions carrying 435 experiments  At STP, Responsive Space is seen as › › › Being flexible to changing plans Networking Reusing existing designs April 20 2

OUTLINE

Case Studies

› › › ›

MISSE 5 SPHERES Kodiak Star Nanosat-2

Summary MISSE On-Orbit A Single SPHERE Kodiak Star Spacecraft NanoSat-2 on Vibe Table

3 April 20

Case Study 1: Materials International Space Station Experiment (MISSE) Passive Experiment Container (PEC) 5 (MISSE 5)

Background: MISSE 5

   

MISSE 1-4 came to STP through the DoD Space Experiments Review Board (SERB), sponsored by the AFRL

MISSE 5 is a reimbursable mission Passive Experiment Container (PEC)

designed by Langley Research Center, borrowed heavily from the Mir Environment Exposure Payload (MEEP) experiments

hosted materials that need to be exposed to the space environment for extended periods of time and then recovered for analysis on the ground MISSE 5 uses almost the same PEC design (MISSE 1-4) to get space/solar exposure data on solar cells MISSE 5 Shuttle mission destined for the ISS in late Spring 2005

April 20

MISSE 1&2

5

Case Description: MISSE 5

   

Reimbursable customer approached STP about getting space exposure data on some new solar cells STP personnel remembered the MISSE series of experiments, and proposed the MISSE PEC MISSE 5 added a battery, thermal control, and a comm link to the PEC

From MISSE PEC design changes to testing completed HW in 15 mos By choosing the MISSE PEC, the team leveraged all of the previous work performed on NASA human space flight safety certification

Often, it takes 2-3 years to complete the Space Shuttle or International Space Station safety process

The time to develop Neutral Buoyancy Laboratory training hardware and procedures was also shortened MISSE 5

April 20 6

Lessons Learned: MISSE 5

For human space flight payloads, the impacts of this safety process can be greatly reduced by tapping into existing design solutions, subsystem concepts, etc

Design reuse helps build familiarity and confidence within the human space flight community and ultimately, a more responsive approach to space flight of DoD experiments Before inventing something new, first look to see if there is anything that can be reused

April 20 7

Case Study 2: Synchronized Position Hold Engage Re orient Experimental Satellites (SPHERES)

Background: SPHERES

Joint venture between DARPA, NASA, MIT, Payload Systems Inc, and AFRL

  

SPHERES tests metrology, formation flight, and autonomy algorithms using from one to three, 25-cm, 3-kg, autonomous micro satellites, a laptop computer, and five infrared/ultrasonic (IR/US) transmitters Commands/telemetry are sent via an RF link between the microsatellites and the laptop control station The microsatellites receive IR/US “pings” from transmitters distributed about the test environment to determine position and attitude and control their relative positions and orientations Conceptual interpretation of SPHERES on-orbit

April 20 9

Case Description: SPHERES

   

STP manifested them on a Shuttle launch to be taken to the ISS in Sep 03 Feb 03 Columbia tragedy grounded the entire Shuttle fleet

STP encouraged SPHERES to complete all Shuttle manifest documentation in order to be ready when the flight schedule resumed During NASA Shuttle grounding, all ISS servicing accomplished by the Russian PROGRESS resupply vehicle

STP, working with NASA, found flight opportunities available on PROGRESS STP approached SPHERES team and NASA about putting a subset of the SPHERES HW on the Aug 03 PROGRESS flight (“12P”)

A SPHERES IR/US beacon and beacon tester were launched on 12P

Additional SPHERES complement manifested on PROGRESS 14P, scheduled for May 2004

While the majority of the SPHERES HW planned to be carried up on the next 2 Shuttle launches, starting with the Shuttle Return-to-Flight in FY05, STP continues looking for space on PROGRESS and Automated Transfer Vehicle (ATV) flights SPHERES Satellite-SPH-1-0000-000

April 20 10

Lessons Learned: SPHERES

Be prepared - completing the NASA manifest documentation allowed SPHERES to easily complete the additional PROGRESS safety documentation and take advantage of that spaceflight opportunity

Modularity adds flexibility – don’t under estimate the power of an experiment subset that can be done earlier as a risk-reduction or proof of-concept to save time or money in the long run In this case, “responsive” means accomplishing some of the objectives soon rather than waiting until all could be executed at once later

April 20 11

Case Study 3: Kodiak Star

Background: Kodiak Star

    

The mission came about because of an initial discussion over lunch at a conference between individuals from STP and NASA.

The mission flew three STP SC and one NASA SC PICOSat was an STP built SC and flew the following:

AFRL’s Polymer Battery Experiment (PBEX)

SMC’s Ionospheric Occultation Experiment (IOX)

NRL’s Coherent Eelectromagnetic Radio Tomography (CERTO)

AFRL’s Optical Precision Platform Experiment (OPPEX).

Sapphire and PC Sat were SC that were sponsored by the US Naval Academy STARSHINE 3 was the NASA SC

April 20

Athena launch of Kodiak Star

13

Case Description: Kodiak Star

PICOSat and SAPPHIRE were built and on the shelf

PCSat and STARSHINE 3 were in the design phase

MOA signed and the mission manifested within 2 months of initial conversations

Payload Upper Deck (PUD) adapter was designed, built, and tested by Lockheed Martin in 5 months

Long-lead items and the least mature systems were identified and money and time were spent on those areas to bring them up to speed.

SAPPHIRE PCSat STARSHINE 3 PICOSat

Kodiak Star spacecraft suite

April 20 14

Lessons Learned: Kodiak Star

  

If you are committed to a project, apply the appropriate level of resources and make the project a priority

Networking is invaluable in mission design When all parties stand to benefit, things can be accomplished in a short amount of time In order to meet an aggressive schedule, risks must be identified early and mitigation plans established at the start of the program

April 20

Aggressive risk management is critical in order to keep on schedule, especially if the schedule is accelerated to begin with

15

Case Study 4: University Nanosats-2

Background: Nanosat-2

  

SERB mission sponsored by the Air Force Research Laboratory (AFRL)

Originally a constellation of 3 nanosatellites built by:

› › ›

Arizona State University (Sparkie) University of Colorado at Boulder(Ralphie) New Mexico State University (Petey) Planned for a shuttle launch Nanosat-2 removed from shuttle manifest due to test-related problems verifying safety related satellite function Sparkie Nanosats in current configuration Petey Ralphie Nanosats in 3 SC Configuration

April 20 17

Case Description: Nanosats-2

  

September 2000 – June 2003

STP investigated flying a payload on the Evolved Expendable Launch Vehicle (EELV) Heavy Demo five times

– First four investigations resulted in no manifest attempts due to perceived schedule or technical issues

June 2003

SMC/CC asked STP to find a payload to fly on EELV Heavy Demo

STP forwarded all options they felt were technically feasible, even if they did not meet all the EELV Heavy Demo requirements September 2003

Nanosats-2 is selected to fly on EELV Heavy Demo

SMC, the EELV SPO and Boeing begin negotiation of technical, financial, and contractual issues

 

January 2004

Work toward integrating the payload on the mission begins April 2004

Ready for delivery to CCAFS by May 3 for integration NanoSat-2 in current configuration

April 20 18

Lessons Learned: Nanosats-2

 

Be open to a change in plans Be inventive and identify all options, whether they meet every requirement or not

The community as a whole needs to be more accepting of auxiliary payloads

When a decision is made, press forward and force the work, both technical and programmatic, to begin immediately Establish your processes, agreements, budget, and responsibilities up front

April 20 19

Responsive Space Lessons Learned Summary

      

Be open to a change in plans and to solutions that have never been attempted Networking will help identify more opportunities To accomplish something quickly, commit wholeheartedly and apply enough resources to make the project work Risks and a plans to mitigate them should be identified in the beginning of a program Prior to “starting from scratch,” investigate the utilization of existing resources and designs Be prepared to take advantage of opportunities when they come along Making a project scalable, so that objectives can be accomplished incrementally, will increase the number of manifest options and maximize the early accomplishment of some objectives

April 20 20