Transcript No Slide Title
A NOVEL APPROACH TO RESPONSIVE SPACE: LESSONS LEARNED BY THE DoD SPACE TEST PROGRAM (STP)
Sabrina Herrin The Aerospace Corporation Email:[email protected]
Eleni “Sam” Sims The Aerospace Corporation Email: [email protected]
INTRODUCTION
STP serves as the primary provider of spaceflight for the entire DoD space science and technology community Since 1967, STP has flown 168 missions carrying 435 experiments At STP, Responsive Space is seen as › › › Being flexible to changing plans Networking Reusing existing designs April 20 2
OUTLINE
Case Studies
› › › ›
MISSE 5 SPHERES Kodiak Star Nanosat-2
Summary MISSE On-Orbit A Single SPHERE Kodiak Star Spacecraft NanoSat-2 on Vibe Table
3 April 20
Case Study 1: Materials International Space Station Experiment (MISSE) Passive Experiment Container (PEC) 5 (MISSE 5)
Background: MISSE 5
MISSE 1-4 came to STP through the DoD Space Experiments Review Board (SERB), sponsored by the AFRL
›
MISSE 5 is a reimbursable mission Passive Experiment Container (PEC)
›
designed by Langley Research Center, borrowed heavily from the Mir Environment Exposure Payload (MEEP) experiments
›
hosted materials that need to be exposed to the space environment for extended periods of time and then recovered for analysis on the ground MISSE 5 uses almost the same PEC design (MISSE 1-4) to get space/solar exposure data on solar cells MISSE 5 Shuttle mission destined for the ISS in late Spring 2005
April 20
MISSE 1&2
5
Case Description: MISSE 5
Reimbursable customer approached STP about getting space exposure data on some new solar cells STP personnel remembered the MISSE series of experiments, and proposed the MISSE PEC MISSE 5 added a battery, thermal control, and a comm link to the PEC
›
From MISSE PEC design changes to testing completed HW in 15 mos By choosing the MISSE PEC, the team leveraged all of the previous work performed on NASA human space flight safety certification
›
Often, it takes 2-3 years to complete the Space Shuttle or International Space Station safety process
The time to develop Neutral Buoyancy Laboratory training hardware and procedures was also shortened MISSE 5
April 20 6
Lessons Learned: MISSE 5
For human space flight payloads, the impacts of this safety process can be greatly reduced by tapping into existing design solutions, subsystem concepts, etc
Design reuse helps build familiarity and confidence within the human space flight community and ultimately, a more responsive approach to space flight of DoD experiments Before inventing something new, first look to see if there is anything that can be reused
April 20 7
Case Study 2: Synchronized Position Hold Engage Re orient Experimental Satellites (SPHERES)
Background: SPHERES
Joint venture between DARPA, NASA, MIT, Payload Systems Inc, and AFRL
SPHERES tests metrology, formation flight, and autonomy algorithms using from one to three, 25-cm, 3-kg, autonomous micro satellites, a laptop computer, and five infrared/ultrasonic (IR/US) transmitters Commands/telemetry are sent via an RF link between the microsatellites and the laptop control station The microsatellites receive IR/US “pings” from transmitters distributed about the test environment to determine position and attitude and control their relative positions and orientations Conceptual interpretation of SPHERES on-orbit
April 20 9
Case Description: SPHERES
STP manifested them on a Shuttle launch to be taken to the ISS in Sep 03 Feb 03 Columbia tragedy grounded the entire Shuttle fleet
›
STP encouraged SPHERES to complete all Shuttle manifest documentation in order to be ready when the flight schedule resumed During NASA Shuttle grounding, all ISS servicing accomplished by the Russian PROGRESS resupply vehicle
›
STP, working with NASA, found flight opportunities available on PROGRESS STP approached SPHERES team and NASA about putting a subset of the SPHERES HW on the Aug 03 PROGRESS flight (“12P”)
›
A SPHERES IR/US beacon and beacon tester were launched on 12P
Additional SPHERES complement manifested on PROGRESS 14P, scheduled for May 2004
›
While the majority of the SPHERES HW planned to be carried up on the next 2 Shuttle launches, starting with the Shuttle Return-to-Flight in FY05, STP continues looking for space on PROGRESS and Automated Transfer Vehicle (ATV) flights SPHERES Satellite-SPH-1-0000-000
April 20 10
Lessons Learned: SPHERES
Be prepared - completing the NASA manifest documentation allowed SPHERES to easily complete the additional PROGRESS safety documentation and take advantage of that spaceflight opportunity
Modularity adds flexibility – don’t under estimate the power of an experiment subset that can be done earlier as a risk-reduction or proof of-concept to save time or money in the long run In this case, “responsive” means accomplishing some of the objectives soon rather than waiting until all could be executed at once later
April 20 11
Case Study 3: Kodiak Star
Background: Kodiak Star
The mission came about because of an initial discussion over lunch at a conference between individuals from STP and NASA.
The mission flew three STP SC and one NASA SC PICOSat was an STP built SC and flew the following:
›
AFRL’s Polymer Battery Experiment (PBEX)
›
SMC’s Ionospheric Occultation Experiment (IOX)
›
NRL’s Coherent Eelectromagnetic Radio Tomography (CERTO)
›
AFRL’s Optical Precision Platform Experiment (OPPEX).
Sapphire and PC Sat were SC that were sponsored by the US Naval Academy STARSHINE 3 was the NASA SC
April 20
Athena launch of Kodiak Star
13
Case Description: Kodiak Star
PICOSat and SAPPHIRE were built and on the shelf
PCSat and STARSHINE 3 were in the design phase
MOA signed and the mission manifested within 2 months of initial conversations
Payload Upper Deck (PUD) adapter was designed, built, and tested by Lockheed Martin in 5 months
Long-lead items and the least mature systems were identified and money and time were spent on those areas to bring them up to speed.
SAPPHIRE PCSat STARSHINE 3 PICOSat
Kodiak Star spacecraft suite
April 20 14
Lessons Learned: Kodiak Star
If you are committed to a project, apply the appropriate level of resources and make the project a priority
Networking is invaluable in mission design When all parties stand to benefit, things can be accomplished in a short amount of time In order to meet an aggressive schedule, risks must be identified early and mitigation plans established at the start of the program
April 20
Aggressive risk management is critical in order to keep on schedule, especially if the schedule is accelerated to begin with
15
Case Study 4: University Nanosats-2
Background: Nanosat-2
SERB mission sponsored by the Air Force Research Laboratory (AFRL)
Originally a constellation of 3 nanosatellites built by:
› › ›
Arizona State University (Sparkie) University of Colorado at Boulder(Ralphie) New Mexico State University (Petey) Planned for a shuttle launch Nanosat-2 removed from shuttle manifest due to test-related problems verifying safety related satellite function Sparkie Nanosats in current configuration Petey Ralphie Nanosats in 3 SC Configuration
April 20 17
Case Description: Nanosats-2
September 2000 – June 2003
›
STP investigated flying a payload on the Evolved Expendable Launch Vehicle (EELV) Heavy Demo five times
– First four investigations resulted in no manifest attempts due to perceived schedule or technical issues
June 2003
›
SMC/CC asked STP to find a payload to fly on EELV Heavy Demo
›
STP forwarded all options they felt were technically feasible, even if they did not meet all the EELV Heavy Demo requirements September 2003
›
Nanosats-2 is selected to fly on EELV Heavy Demo
›
SMC, the EELV SPO and Boeing begin negotiation of technical, financial, and contractual issues
January 2004
›
Work toward integrating the payload on the mission begins April 2004
›
Ready for delivery to CCAFS by May 3 for integration NanoSat-2 in current configuration
April 20 18
Lessons Learned: Nanosats-2
Be open to a change in plans Be inventive and identify all options, whether they meet every requirement or not
The community as a whole needs to be more accepting of auxiliary payloads
When a decision is made, press forward and force the work, both technical and programmatic, to begin immediately Establish your processes, agreements, budget, and responsibilities up front
April 20 19
Responsive Space Lessons Learned Summary
Be open to a change in plans and to solutions that have never been attempted Networking will help identify more opportunities To accomplish something quickly, commit wholeheartedly and apply enough resources to make the project work Risks and a plans to mitigate them should be identified in the beginning of a program Prior to “starting from scratch,” investigate the utilization of existing resources and designs Be prepared to take advantage of opportunities when they come along Making a project scalable, so that objectives can be accomplished incrementally, will increase the number of manifest options and maximize the early accomplishment of some objectives
April 20 20