North Hoyle Wind Farm presentation Rhyl town hall

Download Report

Transcript North Hoyle Wind Farm presentation Rhyl town hall

UK’s First
Commercial Scale
Offshore Wind Farm
26th March 2003
NWP Offshore Ltd
Presentation
• Project Overview
• Construction Process
• Progress to Date
• Marking of Wind Farm on Admiralty Charts
• Stakeholder Involvement in Construction
Process
Project Overview
North Hoyle - Main Parameters
• 30 wind turbines, Vestas V-80 2MW
• 4-5 miles off Prestatyn / Rhyl
•Rectangular Turbine Array
• 800m Separation E-W
• 350m Separation N-S
• Cable landfall /grid connection at Rhyl
• Output equivalent to annual demand of
approximately 50,000 homes
Project History
• Summer 1999 - Install Monitoring Mast
• December 2000 - Crown Estate Invitation to Bid
• Spring 2001 - Awarded Licence to Develop
• August 2001 - Launch of “Juice”
• February 2002 - Submit Consents Application
• August 2002 - Obtain Consents
• October 2002 - Commence Onshore Works
• Summer 2003 - Offshore Construction
• Late 2003 - First Generation
Wind Farm Construction
Turnkey Contract
• Turnkey contractor is consortium of Vestas
Celtic Wind Technology and Mayflower Energy
• Includes 5 year Warranty, Operations and
Maintenance provision
Turnkey Contract Major Suppliers
Wind Turbines - Vestas
Wind Turbine Installation - Mayflower
Monopile Supply - Rheden Steel
Monopile Installation - Seacore
Subsea Cables - AEI Cables
Foundations
• 4m diameter, 275t (max), stored at
Mostyn
• Installation by Seacore using Jack-up
Barge “Excalibur”
• Pile towed out from Mostyn, lifted to
vertical
• Hammer installed, drive to rockhead
(10-15m below mudline)
• 3.7m hole drilled through pile, through
overburden to required penetration
• Pile driven to required penetration
Photo of Horns Rev Foundation
Progress Update
Progress to Date
• Construction plans (Environmental Management
System, Oil Spill Contingency Plan etc) in place for
construction phase
• Site establishment at Mostyn
• Onshore Works - Majority Complete
– Sub-station, some cable laying still to be performed
– Directional drill to be performed under sea-wall
Progress to Date
• Offshore Works
– Modifications to Seacore installation vessel (in
Liverpool) almost complete
– Monopile supply on schedule, currently 8 piles
stored at Mostyn
– Piling about to begin
• Project “On Track” for commissioning in late Autumn
Marking of Wind Farm on Admiralty
Charts
Construction Phase
Operations Phase
Stakeholder Involvement
Stakeholder Involvement
• “Safety at Sea” Seminar
– Inform stakeholders of forthcoming
activities
– Methods of communication
– Establish points of contact
– Effect of wind farm on aids to navigation
– Safety
– Invite feedback
Stakeholder Involvement
• Invitees included
– Port Authorities
– Commercial vessel operators
– RYA, RNLI, MCA,
– Local councils
– Sailing clubs
– Fisheries consultees
Stakeholder Involvement
• Fisheries Liaison Officer
• Email
– Notice of forthcoming activities
• Web Site
– Progress Updates
Points of Contact
• [email protected]
• www.northhoyle.co.uk