Transcript Slide 1
CALIFORNIA’S COALITION for ADEQUATE SCHOOL HOUSING School Construction 101/201 Tuesday, February 21, 2006 Sacramento Convention Center School Construction 101/201 Welcome and Introductions Don Lussier Corona-Norco Unified School District Selecting Your Construction Project Team Julie Arthur San Jacinto Unified School District Planning a new school construction or modernization project can be a daunting task for all District Administrators The Construction Project Team: Who are the players and what is their role? Legal Counsel • Reviews and recommends approval of contracts for: - Architectural Services - Site Acquisition/School Acquisition Contracts - Construction Consultant Contract (CM, GC, etc.) - Other consultants • In addition: - Review of Bid Documents - Supplies General Conditions Section - Advice on Construction disputes - Recommends procedures to minimize exposure to construction claims School Construction 101/201 Financial Planning Consultants • District to prepare long term financing plan: - Maximize Funding Mechanisms - Financial Hardship vs. 50/50 Districts - GO Bond - Community Finance District (CFD) - Certificates of Participation (COP) - Grant Eligibility - OPSC forms and submittals - Audit Assistance - CDE and OPSC issues School Construction 101/201 Architect School Construction 101/201 • Plans school site lay-out • Develops educational specifications for new school project with District Staff for CDE review • Preliminary Endangerment Assessment (PEA) mitigation team member • Construction drawings • Submit Drawings and Plans to DTSC, CDE, DSA and OPSC • Review District Standards • Prepare Five-Year Facility Plan • Coordinates with local Utility Companies • Coordinates with local City and County staff Architect Continued… School Construction • Oversees the following Consultants on Project: - Civil Engineer - Mechanical Engineer - Structural Engineer - Electrical Engineer - Landscape Architect - Kitchen Design Consultants • Various other duties as assigned…. 101/201 Site Acquisition Consultant School Construction 101/201 • Recommends and assists in a variety of capacities as it relates to school site options: - Site Identification - Site Purchase - Site Viability - Eminent Domain issues - Assists in obtaining Approvals by DTSC, CDE, Local City, Fire and Utility Companies - Works with Developers on master plan projects School Construction 101/201 Appraisers • Self Contained Appraisals for new school sites • GO Bond Appraisals Escrow Companies • Escrow transactions for land purchases agreements • Escrow accounts set up for special projects Geotechnical Consultant • Phase I • Geohazards Study • Soils Testing • Preliminary Endangerment Assessment (PEA) Environmental Consultants • California Environment Quality Act (CEQA) preparation for: - New School Sites - Existing School Site Addition of more than 10 classrooms Construction Manager (CM) • Pre-Construction (Estimates) • Review of Plans • Constructability Review • Value Engineering • Bid Package Assignments and Coverage • Finalize General Conditions and Division 1 with the Architect and District • Scheduling • Supervise Construction Project • Pay Application review and recommendation • Change Order review and recommendation • Close-out Documents/Warranty Calls • Site Safety Compliance General Contractor • • • • Single Prime Contractor Hard Bid Work awarded to lowest bidder Oversees schedule and sub-contractor on project • Handles Pay Application and Close-out documents Multi-Prime Contractor • Individual Trade Contractor working under MultiPrime Construction Management Contract Surveyor • Surveys for new school sites • Handles Parcel splits • Prepare Metes and Bounds for Land Recordation • Set corners, grade stakes, etc. during construction • Contract held by District or Construction Manager Storm Water Prevention Plan (SWPP) • Storm Water Prevention Measures for existing school sites and new construction projects. (Contract held by District or Construction Manager) Division of State Architect Project Inspector (PI) • Formally known as Inspector of Record (IOR) • Handles On-Site Inspection for Construction Projects • Oversees Construction Specialty Testing Inspectors and Services • District holds PI contract but PI acts under the direction of the Architect in general responsible charge and is subject to supervision by DSA (Title 24 Part 1 IR A-8 ) Material & Specialty Construction Testing Services Handles Testing and Review of the following work: – Soils -- Compaction – Concrete -- Welding – Masonry -- Other Specialty Tests – Moisture Tests -- Works under on-site PI Furniture and Equipment Consultant • Handles ordering and purchasing requirements: - Meets with Facility Staff and New School Principal - Helps in procuring furniture, equipment, and supplies to open new schools - Color coordination with Furniture and Classroom interiors - Field measures for office and classroom furniture - Works within State of California purchasing regulations as outlined by Government Codes - Receives furniture delivery, checks in and matches order - Identifies damage or incorrect deliveries - Prepares warranty information book Bank • Set up Escrow or Trusts Accounts for Construction Projects • Contractor payments dispersed through accounts • Cash Flow Statements Lobbyist • Presents District special requests to State Allocation Board (SAB) Handout • A handout is available in a condensed form to use with Board Members and District Staff. It also identifies whom the consultant reports to and the size of the District that may benefit from these services. Design Process Chris Taylor HMC Architects Primary Considerations School Construction 101/201 • CDE/Code of Regulations- Title 5 • • • • • CEFPI Guide for Educational Facilities Planning DTSC/CEQA Environmental Review DSA Review, Approval and Inspection OPSC/SAB State Funding CHPS Sustainability Criteria Design Process Title 5, Division 1 CDE, Chapter 13 • • • • • • • School Construction 101/201 Site Selection Educational Specifications Circulation Playgrounds Service/Utility Areas Future Expansion Building Arrangement Design Process Title 5, Division 1 CDE, Chapter 13 (Continued) • • • • • • School Construction 101/201 Classrooms/Labs Auxiliary Areas Lighting Acoustics ADA Child Care/Pre-school Design Process Site Acquisition School Construction 101/201 • Civil Engineer/Architect/CM and others to assist with site assessment and purchase - Topography can impact project costs - Proximity of utilities - Site Drainage issues - Soil structural characteristics - Buries conditions (preliminary testing) • Groundwater/rock/organics - Soil contamination/conditions • Phase I report to DTSC • CEQA Design Process Environmental • • • • • School Construction 101/201 Order Geo-hazard Report CEQA- Be aware of necessary approvals and changes to preliminary site design DTSC - Be aware of necessary approvals CDE site approval Proximity to airports, power lines and pipelines Design Process Educational Specifications/Programming School Construction 101/201 • Review educational goals for project • Determine space and adjacencies needs to meet goals • Meet with stakeholders and user groups to determine needs for project • Review District Standards Pre-Design / Design CEFPI Planning Guide School Construction 101/201 • Creating Connections: CEFPI Guide for Educational Facilities Planning • Order online at: www.cefpi.org Pre-Design / Design Once an Architect is Hired Team should review: • Scope of Project • Budget • Schedule School Construction 101/201 Schedule • Ed Spec 1 – 2 months • Schematics 15 – 3 months • Design Development 2 – 4 months • Working Drawings 3 – 6 months • Agency approvals OPSC Health DSA Local City SDE Local Fire School Construction 101/201 • Bid and Award • Construction • Owner Move In 30 – 90 days • Occupancy Date Schematic Design School Construction 101/201 • When the Educational Spec is done and the Project Scope, Budget, and Schedule is agreed, the Architect starts Schematics: Analyze site utilization options Develop site and floor plan options Review Exterior massing and elevation options Check Budget vs. design (coordinate with CM firm) Get Board approval of Schematic Design package Design Development • Work with District to incorporate District Standards • Develop plans in detail and review them with users • Finalize site plans, floor plans, and building exteriors • Research and finalize - Material selection - Equipment selections • District starts to think about F & E requirements • Revisit Budget with District and CM firm - Review soft cost in budget - Testing and Inspection -F&E - Contingencies, etc. School Construction 101/201 Construction Documents School Construction 101/201 • Finalize plans to submit to Agencies • Minimize changes at this phase • CM’s involvement in review of plans, construction methodologies and specifications • Finalize General Conditions and Specifications with the District and CM firm Division of the State Architect School Construction 101/201 • California Building Code - Part 1, Title 24, Administrative Procedures • Access, Fire Life Safety and Structural • Energy and Geologic Review • Encourage preliminary review • Do not submit incomplete plans • Do not start construction w/o approval • Use PCO process for change orders DSA (continued) • Invite DSA to pre-con meeting • Architect approves DSA inspector • Inspector reports to architect • Architect in general responsible charge! School Construction 101/201 Office of Public School Construction School Construction 101/201 • Be aware of budget, schedule and funding availability impact • Get CDE and DSA approval first • Requirements for awarding construction contract and substantial completion • Get local agency/serving utility approval for off-site and utility design Sustainability School Construction 101/201 • CHPS - Collaborative for High Performance Schools is the benchmark • Addresses critical issues like day-lighting, acoustics, air quality, energy efficiency, environmental protection and operational efficiency • More information at: www.chps.net Agency Submittals School Construction 101/201 Make sure the site has been approved to build on. • CEQA • DTSC • City, local Fire, City, and Local Utility companies (usually before others) • CDE - submit at design and the end of Working Drawings • Health submit as early as possible • DSA - make sure package is complete • OPSC - after DSA approval Value Engineering/Constructability School Construction • Architect/CM to assist with design options • Utilize CM/third party constructability reviews 101/201 General Condition/Division 1 • Alternates • Bid Packages with CM • Bid dates • Construction facilities • Change order procedures • Submittal requirements • How to pay for utility connection • RFI requirements, etc. School Construction 101/201 Pre-Construction Services Steve Worley Tilden-Coil Constructors, Inc. Construction Consultant Involvement Overview School Construction 101/201 Design Involvement Budgeting Constructability Scheduling Multiple Trade Development Coordination with District’s Department Directors Bidding Design Involvement Construction Material Budgeting Contractor’s Perspective School Construction 101/201 Budgeting Design Development 50% Design Drawings 90% Design Drawings DSA Submittal Final DSA Submittal Alternates & Value Engineering School Construction 101/201 Constructability School Construction 101/201 Electrical/Mechanical/Plumbing Coordination Civil Utilities and Building Utilities Water Intrusion Quality Control Specification Review Scheduling School Construction 101/201 Preconstruction Schedule - Design / Owner / Construction Team Refer to Handout Exhibit B - Schedule Construction Schedule - Elementary School: _________________ - Middle School: _________________ - High School: _________________ Phased Opening Multiple Trade Development School Construction 101/201 Elementary School: ____________________ Middle School: ____________________ High School: ____________________ Refer to Handout Exhibit C - Possible Category Breakdown Coordination with District Personnel School Construction 101/201 Planning Facilities Purchasing Maintenance & Operations Site Administration (Growth Projects) Bidding School Construction 101/201 What: Should I consider? When: Should I bid? Where: Should I bid? How: Long should I bid? Bid Review and preparation for School Board Approval Refer to Handout Exhibit D- Bid Evaluation Form Construction Phase Issues Ron Kuehl Neff Construction Project Startup Activities School Construction 101/201 Permits & Fees Encroachment Permits Utility Connection Fees Temp. Utility Permits NPDES and SWPP issues Resources: EPA at http://cfpub.epa.gov/npdes/stormwater/swppp.cfm California Storm Water Quality Assoc.: http://www.casqa.org Regional Water Boards Storm Water Pollution Prevention Plan Monthly Reporting Best Management Practices Notices of Award & Notices to Proceed What gets initiated on the basis of an NOA When do you issue a NTP Project Startup Activities (Continued) School Construction 101/201 Contracts, Bonds, and Insurance Contracts Should be Prepared by the District or Reviewed for Accuracy Bonds Required by Civil Code section 3247 for contracts greater than $25k Surety Requirements at Code of Civil Procedure 995.61 Insurance Commissioners Contact Info.: www.insurance.ca.gov Preconstruction Conference Topics Contact Info. Official Start Date and Schedule Procedures and Forms As-built Procedures Project Meetings LCP Outside Agency Interactions Public Agency Interactions - Streets and Highways Code sec. 2117 Utility Agency Interactions - Early Contact Critical Construction Administration Project Tracking Resources RFI Logs -- Monitor for Timeliness and Response Times C.O. Logs -- Monitor for Budget Purposes Schedule -- Update/monitor for project progress monthly Superintendent’s Project Logs are a Critical Resource Submittals & Shop Drawings Schedule Critical Submittals/Shop Drawing - steels, doors/windows Prepare and Maintain Submittal Log of Required Submittals As-built Documents Important to Develop a Mechanism to Insure As-builts are Completed Timely Should Require a Line Item on the Schedule of Values Inspector to Verify School Construction 101/201 Construction Administration (Continued) School Construction 101/201 Billings & Payment Include Written Procedure in General Conditions Review Schedule of Values for completeness and accuracy Include line items for as-builts, clean-up and turn-over items Prompt Payment Issues – Public Contract Code 20104.5 and 7107, Civil Code 3260 Communications - Owner, Contractor, CM, Architect, Neighbors, and Staff Establish and Maintain Procedures Include in General Conditions The Appropriate Uses of Weekly Jobsite Meetings Assess Project Progress Review Pending Issues Review Logs for pending items and timely returns Who prepares the minutes? Construction Administration (Continued) Inspections & Testing Inspecting to Plans and Specifications vs. DSA issues Timeliness, Continuous Inspection, Testing Lab Coordinated Through Project Inspector Onsite Safety During Construction What do the Documents Say? Differing Theories of Responsibility Safety Programs, Consultants and OSHA Permits Contractor Bankruptcy and Types of Termination Anticipating a Bankruptcy and Things to Consider Termination for Cause Termination for Convenience Termination/Takeover of a Task School Construction 101/201 Project Completion Punch-list Development and Completion Making a Clear Distinction Between Punch List Items and Incomplete Items Important That There is a Single Punch List Monitor and Certify Completion N.O.C.’s and Final Payment Best Practices Finalize all Change Orders prior to filing NOC Current Standard is to File N.O.C.’s Pending Completion of Punch List Items Procedures are Defined at Civil Code 3093 Codes Mentioned Under Payment Phased Occupancy & Continuing Construction Activities Segregation of Construction Activities and School Functions Finger Printing Requirements – Ed. Code 45125.1 Other Contractor Turnover Items Attic Stock & Tools & Equip. Guarantees/Warranties + O&M Manuals As-Built Documents School Construction 101/201 Special Considerations – Mods. & Additions School Construction 101/201 Utility Upgrades & Ongoing School Activities Schedule During Breaks and Long Holidays Can Prepare for Certain Disruptions Have a Contingency Plan Scheduling Construction Operations Given Sensitive (Testing, etc.) School Activities These Dates/Times Need to Be Built into the Project Schedule Define Which Activities are Permitted Interim Housing Generally More Cost Effective Than Alternatives Scale and Locate Appropriately Devise Plan for Moving F&E Fingerprinting Requirements See Previous Slide Zero Tolerance on Worker/Student Interaction Overall Project Security Added Security Requirements Due to Site Traffic After School Security Very Often Required Scheduling Disruptive Construction Activities Roofing, Heavy Demo., Painting, Utility Work, Etc. Traffic and Path of Travel Issues Regular Onsite Staff Updates Occupying and Closing Your Project Yvonne Medina Fontana Unified School District Three distinct categories to consider when talking about occupying and closing out a public school facility project District (owner) Contractors, Consultants, Vendors and Agencies Community District (owner) School Construction 101/201 Owner’s representative: Project Manager Maintenance and Operations Technology Food Services Transportation School site staff Programs: Special Education, State Preschool, Childcare, GATE, other Contractors, Consultants, and Vendors School Construction 101/201 General Contractors/Prime Contractors Subcontractors Furniture and equipment vendors Systems vendors (data, fire alarm, energy management) Architect of Record Inspector of Record Construction Management/Specialty Agencies School Construction 101/201 Division of the State Architect Office of Public School Construction Department of Education - County/District/School (CDS) Code City Building / Public Works Department County / Public Works Department City / County Fire Department County Health Department Community School Construction 101/201 Students (mascot, colors, teams) Parents (PTA, Booster Clubs) Neighborhood (school name, signage, suggested routes to school) City / County – joint use Organizations and Associations (CIF) Board of Education (dedication ceremony) City, County, and State Elected Officials Occupancy Schedule: 12 months prior School Construction 101/201 Select a Principal and/or key staff member to facilitate all program related issues with project manager / owner’s representative Identify a process and timeline to determine school attendance boundary configuration and parent/student notification Obtain a County/District/School (CDS) code Generate a list of required furniture and equipment items. Identify long lead time and specialty items. Occupancy Schedule: 9 months prior School Construction 101/201 Confirm project budget/identify any “missing” program-related items Develop a checklist of all agency-related approvals and schedule tentative dates for signoff (fire department, health department, licensing) Initiate community meetings re: new school attendance boundaries, introduce Principal Confirm street address Occupancy Schedule: 6 months prior School Construction 101/201 Complete order of all furniture and equipment Schedule preliminary meetings with Food Services, M & O, Technology, and Transportation staff Confirm room signage and numbering Confirm Critical Construction Schedule Milestones to complete Develop a “back-up” plan (just in case) Occupancy Schedule: 3 months prior School Construction 101/201 Confirm utility service operation Schedule/confirm building systems testing and operation Participate in final punch walk with district departments (technology, M&O, food services) Schedule necessary cleaning Schedule delivery of F & E Occupancy Schedule: 1 month prior School Construction 101/201 School site staff arrives and sets up Test all systems (phone, data, HVAC, etc.) Coordinate completion of remaining project work Develop a process for identifying warranty related matters Coordinate valuation of outstanding work to be completed Closing your Project School Construction 101/201 General Contractors / Prime Contractors - Schedule Board of Education approval of Notice(s) of Completion - Withhold necessary dollar values from each contractor to complete work prior to releasing retention monies - Ensure adequate time and access to complete work Closing your Project School Construction 101/201 Timeframes for expending project funds - Three (3) years from date of apportionment for elementary school projects - Four (4) years from date of apportionment for middle and high school projects - OPSC will audit your project within specified timeframe—not more than two (2) years after final expenditure report Agency Closeout School Construction 101/201 When is the project considered closed? 1. Notice of Completion(s) approved by the BOE. 2. DSA has closed the file with Certification of a complete and closed project file. All change orders and requested documents must be received and approved by DSA. If not certified—the BOE and Architect and personally held liable pending certification 3. OPSC has issued a closeout letter following project audit 4. All remaining agency approvals have been completed Occupying and Closing Your Project School Construction 101/201 It is a team effort Schedules and checklists will ensure that you and the team stay on track Always have a back-up “housing plan” School Construction 101/201 School Construction 201 Introduction Mark Kelley Miller Brown & Dannis It’s All About the People Building a Successful Program/Project Team Ron Lebs Business Manager Sylvan Union School District Overview • • • • • • • • School Construction 101/201 Know the Culture Establish Expectations Identify Roles and Responsibilities Build the Team Manage the Team - Work the Process Garner Understanding - Make Decisions Communicate & Report Conclusion But First a Little Wisdom… “Whenever you are asked if you can do a job, tell ‘em, 'Certainly I can!' Then get busy and find out how to do it.” Theodore Roosevelt “Things should be made as simple as possible, but not any simpler.” Albert Einstein “With ignorance and arrogance, success is assured.” Mark Twain School Construction 101/201 Know the Culture School Construction 101/201 • Scan the Environment • Identify the Culture – Understand the Decision Making Process – Identify the Decision Makers & Their Roles – Site Specific Personalities • Kindergarten & Coaches – Know Your Board • Committees? • Community Involvement? Know the Culture Cont. • Adapt Process to Fit Culture – One Size Doesn’t Fit All – Don’t Swim Upstream – Work the System, Not Against it! • Listen First and Foremost • Communicate Early and Often School Construction 101/201 Establish Expectations School Construction 101/201 • Clearly… – Define and Communicate Process – Communicate Expectations – Be Consistent With All Parties Throughout • Begin With the End in Mind – Develop Plan - Draw a Map – Know Where You Are Going and… – How to Get There - Beforehand! If you don’t know where you’re going, any road will get you there. Identify Roles & Responsibilities School Construction 101/201 • Your Role as Facility Director – Determine who defines your role. • • • • Superintendent? Board? CBO? You? – Clearly Understand the Issues, Options & Costs • Ask Questions • Have Answers Identify Roles Cont. School Construction • Your Role as Facility Director – Make Sound Recommendations – Insure that Timely Decisions are Made – Manage the Process – Coach - Conductor – Cheerleader – Do the Right Thing • Not Always Popular • Measured Against Expectations – Communicate Once you understand your role, you can help others understand theirs! 101/201 Identify Roles Cont. School Construction 101/201 • Know Everybody Else’s Role – Know Who you Need – Know What They Do • You Define Their Role or They Will 4U! • You Can’t Delegate Leadership! – Take Responsibility • You Define Project Character Those who spend most of their energy trying to stay out of trouble, seem to have it follow them wherever they go. Build Your Team School Construction 101/201 • Selecting the Project Team* – Staff – Committees – Consultants (RFQ&P) – Power Brokers – District Decision Makers • Team(s) should be relevant to district culture and needs. *Selecting the Project Team & Consultants - Construction 101 Build Your Team Cont. • Committees – Define Committee Purpose – Remember Your Role • Leadership - Run or be Run • Communicate Expectations – Cross-Section of Participants • • • • Hand Pick if Possible All Committed to Same Outcome Gather Different View-points Avoid Groupthink School Construction 101/201 Manage Your Team School Construction 101/201 • Your team will be successful only to the extent of your skills as a leader. • “A most important key to successful leadership is your ability to direct and challenge the very best that is in those whom you lead.” Anonymous • Pick the best and Let ‘em run! • “Own” the Project • Be Responsible/Accountable Master Your Team Cont. School Construction • Facilitate Daily Progress • Know Your Role – Clearly Understand the Issues & Options – Make Sound Recommendations – Insure that Timely Decisions are Made – Coach - Conductor – Cheerleader – You don’t have to be “Mr. Know-it-All.” 101/201 Garner Understanding— Make Wise Decisions • Define and establish the decision-making process as part of the expectations. • Seek to Understand. – – – – Know the Issues Know the Options Know the Costs Know the Benefits & Burdens • Sound recommendations can only come from a solid understanding of the issues. Know before you go. If you don’t know, don’t go! School Construction 101/201 Make Wise Decisions Cont. • Don’t make decisions in a vacuum. – Consult with your team (experts). – Consensus is important, but do the right thing. • Decisions Cost Money • Trust but Verify! – Follow the Money – Once contract is awarded the only person motivated to save money is you. – Change Orders! School Construction 101/201 Make Wise Decisions Cont. School Construction • If you don’t know, ask! • Find really smart people and listen to their advice! (Network) • In spite of _______ get it done! • Facilitate the decision-making process. • Remember – You Own the Project • Stop the Buck! 101/201 Communication • A large percentage of issues on a project can be traced to a breakdown in communication which tends to be either, – too much of the wrong kind or – not enough of the good kind. • Know the Communication Culture – Board Room vs. Job Trailer School Construction 101/201 Reporting School Construction 101/201 • Regular Appropriate and Accurate Reporting to… – – – – – Superintendent & Board of Trustees Sites & Departments Teams Committees (Public Relations) Public • Newspaper – Newsletters - Website • Highlight Success! • Don’t Bury Bad News! • Absorb the Blame - Pass the Credit! Roadmap to Project Success Establish Expectations School Construction 101/201 Identify Roles Know Culture Build Team Manage Team Make Decisions Project Success Communicate & Report Final Comments ... • • • • • • • • • Communication is Critical Know Your Role & Everybody Else's Understand the Issues Facilitate Informed Decisions Own the Project Coach Your Team Lead, Follow or Get Out of the Way Facilitate the Process Communicate, Communicate… School Construction 101/201 Client/CM Teamwork V-Anne Chernock Tamalpais Unified School District Karl Shultz Vanir Construction Management Getting Started • Skills sets and preferences • Roles and communication • Operating patters School Construction 101/201 Skill Sets and Preferences • What are we best at? • What do we like to do? • What are we willing to do? School Construction 101/201 Roles and Communication • • • • • Points of contact Planning and design Construction Personnel management Community involvement School Construction 101/201 Operating Patterns • • • • Office locations District culture Open-door policy Brain-storming time School Construction 101/201 How We Work • • • • Together in groups Together in situations Separately In times of conflict School Construction 101/201 Together In Groups School Construction 101/201 • • • • Facilities Cabinet Site and Oversight Committees Board of Trustees Construction meetings Together In Situations School Construction 101/201 • • • • • • Cost control Scheduling Contract administration Standard CM Changes and claims Trouble-shooting Separately School Construction 101/201 • Vanir – Staff assignments – CM contract adherence – Corporate compliance – Other projects • District – Items NIC (e.g., CEQA) – Public relations – District compliance In Times of Conflict • • • • • School Construction 101/201 Talk constantly Listen carefully Settle quickly Stand as a team Remember: the client is always right... School Construction 101/201 . . . even when we’re wrong! Why Didn’t We Do That? Or... David L. Goldin San Francisco Unified School District Why Didn’t We Do That? Or… School Construction 101/201 • Several ways (but not the only ways) to succeed with a school construction program – Know where you are going and how you’re going to get there….. – Get the “A” Team…. – Tell it like it is…… – Manage the design phase….. Know Where You’re Going and How to Get There! School Construction 101/201 Have a current Master Plan • The first step - prior to starting any projects, or making major expenditures! • Develop a Roadmap for a successful Facilities Program – Early & Accurate Project Definition – Adequate Budgets w/contingency & escalation – An appropriate & “Realistic” Master Schedule – School Board-Community buy-in/approval Clearly define projects early in planning (avoid scope leap!) School Construction 101/201 • Develop scope of work for the Program – Perform & Evaluate Facilities Assessments – Determine Educational program priorities – Determine Growth needs for new classrooms – Community Priorities, School Board-political needs • Get as close as possible to fully defined projects and understand the scope! • Assume revisions to project scope will happen! – Scope will/may grow & priorities and School Board Members and Superintendents will change over time Is there enough Money??? School Construction 101/201 • Make sure the available funding matches the Master plan scope – hard and soft program costs – Match project schedule with G.O Bond Sales – Build and update often a “realistic” program and project budget – Remember escalation of costs over time – Budget for “Design” & “Construction” contingency • Make sure that you’ve applied for every state funding program available and continue to monitor eligibility & OPSC/CDE applications • Continuously monitor scope creep and/shifts in District priorities Understand Project Scope Early (or pay the price later!) School Construction 101/201 Example – The community successfully passed a large facilities bond program with a Master Program scope of work. The original bond program called for a replacement gymnasium at the high school for 2.5 million dollars. After political/community pressure and scope creep the Gymnasium became a 2500 seat, 2 story Event Center at a cost of 10 million dollars. Now people are asking why the program is short money to complete the remaining projects. Newark Memorial High School Newark USD Understand Project Scope Early (or pay the price later!) School Construction 101/201 Example – San Francisco USD built a new 36 million dollar urban campus high school 5 years ago. “Probably inspired by a Southern California mall”. Superintendent personally got involved with the programming after “construction documents completed and project awarded”. Construction costs ballooned and 25% of interior build out space remain unfinished five years later**. John O’Connell High School SFUSD **Footnote: Superintendent is now long gone Get the Right Project Team School Construction 101/201 • Architects – Select and retain experienced firm(s)/staff – Build a long term relationship – Develop District design standards-board approve • Project & Construction Managers – Getting the A Team they promised! – Understand the project delivery methods before picking the project and construction managers • Contractors – Getting, keeping a pool of interested GC’s – Prequalification and other myths of General Contractor “selection” and don’t forget………. Get the Right Project Team School Construction 101/201 • Project DSA Inspectors – No one person will assist a successful project more “or” kill a project faster – Standardize procedures & build long term relationships • In house staff – Hire staff that can work well in a team environment and provide leadership – Don’t neglect clerical - Record keeping is critical • Legal Counsel – Retain the best – Division 0 General Conditions, Bid Phase and construction. Think of Counsel as “preventative medicine…not just for claims. Find and build a relationship with the right Architect(s) School Construction 101/201 • Selection Processes that work – No favoritism or wired-in firms • Always pay Adequate fees for services! • Write reasonable, fair contracts • Aggressive Design Phase Management – District engaged in project at all times – Understanding all design decisions – Always pushing the architect on schedule • Build a long term relationship Tactics to survive your Architect School Construction • Select a Pre-Qualified Pool of Architects – Select for individual projects – Don’t contract for all work at once – Allows for changes if performance issues arise • Have a redesign clause in contracts – For budget busters, if bids come in high architect redesigns at own cost • No automatic fee increases tied to cost of construction or bid amounts – Use fixed-fee contracts based on scope – Additional Services for added scope, not cost change 101/201 The PM/CM Team School Construction 101/201 • Always Buy the individual, not the firm!!!!!!!!!! – Demand the personnel you interviewed and were sold • Only Buy the firm – For corporate support—cost estimating, scheduling, claims analysis – For Staff training programs, commitment professional development, back-up personnel • Staffing Plans – Develop an appropriate plan – A good staffing plan is Key to agency CM – Understand roles, durations, responsibilities“Reject overstaff models” or front loaded “Get” Good Contractors (Define “good”?) School Construction 101/201 Attracting good Contractors School Construction 101/201 • The District’s actions are key to attracting & retaining good contractors – Timely payment of Contractors – District response times on starting work, design, change issues, job site issues – Fair negotiation of Change Orders – Quality, clarity of documents for bidding – Quality of overall District team—architect, CM, Project Inspector, District Rep. Contractor Pre-Qualification? School Construction 101/201 • Low Bid reality for most Districts • Contractor Pre-Qualification – Highly defined process – Public Contract Code defines – Screen for special expertise for projects – Preliminary “responsibility” screening – Financial capability, project size & qualifications • Remember the flip-side of Pre-Qualification as a Best Practice - Does it really get you the better contractors and reduce claims? • Districts without Pre-Qualification – Nearly identical Contractor base • Project Labor Agreement- PLAs • LCP- Labor Compliance Programs Tell it Like it is. School Construction 101/201 From no News is good news… School Construction 101/201 • The good old days of operating under the radar are gone • The press is everywhere & someone is always running for election • Districts need positive, aggressive reporting and communications • Be first with the news- not last to hear Good Press is always good for the program Bond Oversight Committee & Board Reporting Basics School Construction 101/201 • Information assists CBOC/Board in meeting obligations of financial oversight • Reporting needs to be understandable by all types of audiences – lay and professional • Agreed upon, appropriate for the group, program and community • Always give a clear picture of the current financial condition of program • Prepare for the CBOC as if they were the auditors as they are the folks who will certify compliance. Manage the Design Phase School Construction 101/201 Why didn’t we manage the Design process! School Construction 101/201 • Most Problems in Construction are born during the design phase • Budget parameters – State and Local funding constraints • Design Phase Management keys – Ongoing, Redundant Cost Estimating – Value Engineering – Document/Constructability Reviews • Aggressive schedule maintenance – Managing Architects and the Responsive District – Agency approvals-Be aggressive with DSA Design Phase Budget Management School Construction 101/201 • Use Design Phase Contingency – Budgets given to Architect at 80%-90% of actual Construction budget – Restrains scope of work from growing – May actually lower scope in project below District’s standards • Architect contracts should always reference budget – Redesign clauses if over budget • Don’t create incentives to increase scope! – Example—architect contracts with adjustments for increased cost of construction Budget Management Keys School Construction 101/201 • Do Redundant Cost Estimating – Contractual obligations for Architect and PM/CM to prepare estimates – Independent cost reviews are the standard • The Reconciliation Drill, or My Apples and Your Oranges – Estimators never agree, never do it the same way, and don’t like to change the way they do it! Continuous Document Quality Reviews School Construction 101/201 • Poor quality, uncoordinated documents at root of most major construction problems – When combined with an aggressive Contractor the worst usually happens • Constructability Reviews at DD/early CD Phase – Coordination of disciplines, completeness of set – Drawing references, Code compliance – After the review—getting the Architect to incorporate comments into sets! – Reviews when plans are at DSA are only coordination efforts…not constructability (too late for that). Maintain the Design Schedule School Construction 101/201 • Managing Architects – Contractual requirement to meet schedule – Architect must help create, buy off on schedule • Focus on DSA review period—the #1 constraint • Maintain Bid timeline – Understand Construction community – Bid late winter, early spring for work in summer – But…Never rush incomplete drawings out to bid!!!! • The Responsive District – Critical in maintaining schedule for design – Single point of contact – Ability to respond quickly with decision So who volunteers to get this project approved at DSA? Using Core Values In Your Construction Program Mark Kelley Miller Brown & Dannis What Are Core Values? School Construction • What does the District value as the result(s) of its construction program? • Develop approaches to the program based on those values • Assess all challenges and results against those Core Values • Reality-based positions/negotiations, not emotion (including fear) based 101/201 Context for Core Values School Construction • Need to comply with laws governing public contracting • Assume that money and time are limited • There is always a tension between cost/time/quality 101/201 Examples of Core Values School Construction 101/201 • “Best quality, least time, under budget” • “The most important factor is our budget - we don’t have any more money” • “If we have another construction claim, the press/public/Board will kill us!” • We absolutely must have the buildings open for the start of the school year” Examples of Non-Core Values School Construction 101/201 • “I want to put that #%?!@ contractor out of business!” • “This architect has always been the District’s architect” • “We need to be on the cutting edge of public contracting” Why Apply Core Values Approach? School Construction 101/201 • Take the emotion out of negotiations, disputes, changes • Reduce risk of bad results • Take care of what is important, and be able to judge what is not Developing the District’s Core Values School Construction • How would you define “success” in your Program? • What are the most important values? • What are the most serious issues facing the Program? • If you could change one thing going into the Program, what would it be? 101/201 Examples Defining Success: School Construction 101/201 • Continued business relations with the contractor? • With the Architect? • Good relations with the Board? – Need their buy-in on Core Values Applying Core Values School Construction 101/201 • Professional contracts (developing approach to negotiations) – Terms applicable to those professionals’ performance – Terms they will help you apply to the contractor(s) • Construction contracts (front-end documents for bid contracts) • There always will be a tension between competing needs Applying Core Values (cont.) School Construction 101/201 • If time is most important: – High liquidated damages (but may reduce bidding pool) – High responsibility on CM to monitor schedule (increased fee) – High responsibility on Architect to verify conditions (increased fee) Applying Core Values (cont.) School Construction 101/201 • If cost is most important: – High responsibility on CM/Architect to estimate (fee) – Keep right to redesign and rebid without additional cost (fee; delay) – Deductive alternates in bids (may reduce bidding pool; bidding problems) Conclusion School Construction 101/201 • Define your and the Board’s Core Values early • Your documents need to reflect those values • Negotiations, even claim negotiations, should be based on those values