Transcript Document

KNPP
New Projects Related to
Decommissioning.
29th May 2008
Richard Benbow – Head of Kozloduy PMU
Group
Contents
 Background for PMU Establishment
 New Projects
 Summary
Group
Background for PMU
Establishment

Phare project (BG.98-02-03) established basis for Decommissioning strategy and
identified relevant supporting projects (final report December 2001)

Initial Projects for PMU scope were obtained from the Phare recommendations

IFT for PMU issued June 2002, Contract placed January 2003 between KNPP and a
Consortium of British Nuclear Group, Electricité de France, supported by ENPRO
Consult
Phase I completed April 2006, contract extension granted for additional Phase II work
till March 2007 with the Consortium.


Phase III extension granted in April 2007, till March 2008, with Project Services
supported by ENPRO Consult.

Phase IV extension granted in April 2008 for work till March 2011with VT Nuclear
Services supported by ENPRO Consult
Group
Project 11 (a, b & c)
Evaluation of the Radiological
Inventory for Units 1 to 4
•The project has now been split into 3 parts
•P11a - Initially equipment will be provided for KNPP to gather all
data necessary to establish an inventory.
•P11b - A feasibility study will be carried out to ensure an optimal
packing regime for all of the wastes is developed
•P11c - A specialist consultant will be engaged to calculate the
activation of components in the reactor pressure vessel
Group
Project 12 Supply of Size Reduction
and Decontamination Workshops
•Project 12 is to provide a range of facilities and equipment for
size reducing and decontaminating dismantled materials from the
Turbine Halls and Auxiliary Buildings at Kozloduy NPP Units 1-4.
•The proposed facilities are envisaged to be used also for size
reduction and decontamination of the dismantled materials from
the other plant areas, including the Reactor Buildings.
•Tenders are currently being invited for this project
Group
13. Dismantling Tools and Equipment
Background
The Decommissioning and Dismantling of the reactors and
ancillary plant will require tools and equipment that are
not normally used at a reactor site.
This project is to procure a range of tools and equipment
for KNPP to use in the dismantling of Units 1-4.
Tenders will be issued over the next 3 months
Group
15. Heat Generation Plant
Background
An additional source of steam for district heating for the
town of Kozloduy will be required after the physical
separation of the infrastructures of Units 1-4, to cover
those situations when Units 5 and 6 are not in
operation.
This steam is also necessary for the processing of liquid
radioactive waste and can be used to accelerate the
restart of Units 5 or 6. Smaller quantities of steam are
also necessary for processes like demineralised water
production and local area heating.
Group
Project 15 Heat Generation Plant
Current proposal is for the supply of a steam and hot water
generation plant fuelled by gas on the Kozloduy site.
•Site location is being finalised prior to Tendering.
Group
Project 16 – Environmental
Assessment for Decommissioning
•This project is to produce an Environmental Impact Assessment (EIA)
for the Decommissioning of Units 1 and 2
•According to Bulgarian legislation, the EIA must be completed by an
independent Contractor
•Expressions of Interest are currently being sought from interested
contractors
Group
19. Decay Storage Site for Transitional RAW
Background
 During the dismantling of the Turbine Hall and Auxiliary Buildings, a
significant quantity of category 1 radioactive waste (RAW) will be
generated. This RAW can be released from regulatory control after
appropriate treatment and/or temporary storage for a period not
longer than 5 years.
 The objective of this project is to provide a site for the temporary
storage of transitional radioactive waste for five years to allow
sufficient radioactive decay to occur to permit subsequent controlled
release.
 This storage site will be situated on the KNPP site.
Group
20. Information Centres for Decommissioning.
Background
 The existing KNPP Information Centre is focussed on
operations at Kozloduy. As the site moves into a
decommissioning regime changes are needed to reflect
this change in status, and the new operations and
procedures that will be introduced to the site as a result.
 The addition of an Information Centre in the House of
Culture will allow free access to the decommissioning
displays so that members of the public can have
access.
 The Informational displays in KNPP offices in Sofia will
display the decommissioning activities so that key
stakeholders may view.
Group
21. Storage Site for Conventional Waste from
Decommissioning.
Background
During the dismantling of Turbine Hall and Auxiliary
Building a significant quantity of solid waste will be
generated and these wastes will be released of
regulatory control.
These wastes will need to be stored temporarily
whilst waiting for removal.
This storage facility will be for clean waste, but must
comply with Bulgarian regulations for waste.
The site may be inside or outside the existing KNPP
boundary.
Group
23.Inventory, Treatment and
Conditioning of Contaminated Soil.
Background
This project is for the provision of technology for both determining the
inventory, and subsequent processing and conditioning of contaminated
soil at the KNPP site.
The project will be carried out in a number of key stages:

Procurement of the equipment for the development of the inventory.

Site surveying for the assessment of contaminated soils.

Development of a strategy for the treatment and conditioning.
 Procurement of the equipment for treatment and conditioning of
contaminated soil.
 Treatment of the soil
 Continued monitoring during the stages of decommissioning
Group
24. Concrete Core Sampling Analysis
Background
 The purpose of this project is the preliminary
investigations on concrete in the buildings of KNPP
Units 1 -4 . The main objective is to obtain information
about the contamination of the concrete of buildings
(level of contamination, penetration depth, nuclide
spectrum).
 For this concrete and epoxy resin coating samples
must be taken and evaluated (gamma-spectrometrically
and partly total alpha). These data are necessary for the
planning of the decontamination measures and free
release measurements before the demolition or
conventional use of buildings.
Group
25.Asbestos Removal Equipment.
Background
 This project is for the supply of equipment and
materials for KNPP personnel to safely remove and
store asbestos material from the Turbine Hall and other
buildings during decommissioning.
Asbestos represents a significant hazard to
decommissioning personnel during the dismantling of
redundant equipment, systems, and structures.
Asbestos removal has been recognised in the
Decommissioning Plan as a necessary early stage in
dismantling activities.
In addition a feasibility study will be carried out for the
processing of asbestos through the HVRF
Group
26.Demolition Equipment.
Background
 This project is for the supply of heavy duty equipment
for the demolition and cutting of reinforced internal
concrete structures within the Turbine Hall, Reactor
Buildings, and Auxiliary Buildings at KNPP Units 1-4
and other possible redundant structures during
decommissioning.
 Demolition of the external structures of the Turbine Hall,
Reactor Buildings, and Auxiliary Buildings is outside the
scope of the decommissioning strategy for the site.
Group
Summary
 The PMU has been established in support of the KNPP
Decommissioning Department.
 All of the Infrastructure Projects associated with
Decommissioning have been identified and are being
managed through the EBRD Procurement Process.
 The status of the twenty seven projects is as follows:
Group
Summary
Projects in approval process (PIS)
8
Project documentation being prepared 5
Projects being tendered
3
Projects in progress/contracted
6
Projects completed
5
Total 27
 Information on the projects and the PMU can be obtained through the
following contact points:
– EBRD Web site: http://www.ebrd.com/
– KNPP / PMU Web site:
http://www.kznpp.org/decommissioning/en/index.htm
– PMU e-mail address: [email protected]
Group