Transcript Slide 1

KAHC-KYTC
• Trevor Booker, PE
•
Specifications
2008 Standard Specifications
Books are now available
A PDF version can be viewed at:
http://transportation.ky.gov/construction/
“Bells” and “Whistles” will be added later
A Major portion of the changes were
prompted by the need to work smarter,
safer, and in compliance with current
State and Federal regulations.
Overrun/Underrun – to be used on specific items
Extra Work – contractor to provide justification for
prices and time when requested
Comprehensive Final Inspection Report –
revised to address striping, seeding, and landscaping.
Liquidated Damages – Just like when you are
delayed, we also have lost efficiency, overhead, and
staffing costs associated with delays
Original Contract Amount
0.00
100,000.01
500,000.01
1,000,000.01
5,000,000.01
10,000,000.01
20,000,000.01
100,000.00
500,000.00
1,000,000.00
5,000,000.00
10,000,000.00
20,000,000.00
or more
Daily Charge
250.00
750.00
1,650.00
2,400.00
3,250.00
4,000.00
4,750.00
These costs accrue regardless of the time of year:
The Department will deduct daily charges as
agreed liquidated damages for each calendar day
without regard to inclement weather or the
temperature limitations in the Contract, except that
the Department will not deduct liquidated damages
when the specified seasonal or temperature
limitations prohibit the Contractor from performing
work on the controlling item or operation.
Planning and Scheduling
Preconstruction Meeting requirements have been
updated to reflect current needs prior to starting work.
Added were:
Designated Qualified Personnel depending on job
(Traffic Control, Flaggers, Asphalt Field Tech, Erosion
Control Inspector, etc.)
Plans (Progress schedule, traffic control, blasting,
BMP, seeding, spill prevention, permits, etc)
Designated qualified contractor staffing must be in place
today, training requirements for those designated must
be successfully completed by:
• Qualified Asphalt Field Technician – January 1, 2008
• Qualified erosion and sediment control inspector
(KEPSC/Grade Level II) – July 1, 2008
• Qualified Flaggers required - April 1, 2008
• Qualified Traffic Control Supervisors and Technicians October 1, 2008. Supervisor required for Significant
projects, available for others.
Progress Schedule
Always been required, but often not provided or
what was desired. We have detailed what is
expected and will be emphasizing its importance.
Blasting Plan
A general blasting plan is required for all blasting. It
is to include working procedures, safety plans, and
address traffic impacts and how they are to be
addressed in case of an incident. Federal oversight
projects will be addressed by special note and will
require additional information and work.
Work Zone Safety
Hi-vis safety apparel must be worn by all workers
exposed to construction equipment or highway traffic.
Must meet ANSI Performance Class 2 or 3. For flaggers
at night, Class 3 is required.
Project Traffic Coordinator must conduct daily reviews.
Emphasis on covering of signs that are not applicable.
Inaccurate, turned, and tipped signs create confusion.
Plywood covers create a crash hazard, plastic bags
damage retroreflectivity. Geotextile fabric covers
required.
Emphasis on getting quality temporary and
permanent striping down ASAP. Retroreflectivity
requirements have been raised. Striping to be in
place over the winter must meet permanent
retroreflectivity.
Temp White: from 150 to 175 mcd/lux/m2
Temp Yellow: from 100 to 150 mcd/lux/m2
Perm White: from 175 to 300 mcd/lux/m2
Perm Yellow: from 150 to 225 mcd/lux/m2
Better defined what is required when
electronic surveying methods are used.
Including check stations, slope stakes and
layout references when requested, and
defined electronic field books
Clarified rock roadbed is rock, not mostly
rock, not mixed with non-durable material
We now have 3 seed mixes:
Type I for slopes 3:1 or less
Type II for slopes > 3:1
in Districts 4, 5, 6, and 7
Type III for slopes > 3:1
in Districts 1, 2, 3, 8, 9, 10, 11, and 12
We now require fertilizer and lime in the seedbed.
Minimums were established but are on the low
side. The contractor is responsible to meet
required growth and soil pH of 6.0 or greater.
Adequate quantities of seed, fertilizer and lime
should be reflected in the seed plan submitted at
the preconstruction meeting.
Straw quantities should be included as well.
Tackifier is still required but mechanically crimping
an option.
Seeding to be paid for as plan quantity increased
or decreased by authorized adjustments.
If design quantities can be shown to be off by 10
percent or more, actual quantities will be used.
Some straw erosion control blankets are now
allowed, ensure the ones you use are on the
Department’s List of Approved Materials. Colored
staples can be required.
BMPs must be installed before any disturbance.
Penalty equal to LD charged immediately – no 5-day letter
required.
Contractor required to conduct weekly and rainfall event
inspections. Corrective action should be initiated within 24
hours and completed within 5 days.
Any channel crossing needs to maintain normal flow and
be of non-erodible material
Sinkholes not filled and capped must be protected.
Pavement drainage blanket. Untreated
blankets no longer allowed. However, JPC
pavement drainage blanket may be asphalt or
cement treated, but must be treated. Will be paid
in square yards.
ASPHALT covered by Allen at PAIKY
‘F’ ant ‘t’ testing on AMAW worksheet
Asphalt Field Technician Requirements
Ride Quality Bonus
• Going from 1-mile to 0.1-mile segments, segments will
read higher and lower as the “averaging” is lessened
• Raising the bar to achieve bonus
• Weighting the bonus on the low IRI end and weighting
the deduction on the high IRI end
• Establishing a set dollar amount in place of basing bonus
unit bid price.
• Linking ride bonus with density. If the sections Density
pay factor is less than 0.95, a ride bonus will not apply.
2004:
Bonus
1-mile Segments Full Pay
2008:
IRI < 47
IRI 47 to 66
Deduct
IRI > 67
Bonus
IRI < 40
0.1-mile Segments Full Pay
Deduct
IRI 40 to 70
IRI > 71
How this changes bonus
• From 55% bonus (15% max bonus)
to approx. 45% bonus (10% max bonus)
• From 42% full pay
to approx. 50% full pay
• From 3% penalty
to approx. 5% penalty
• The percentage of segments receiving
adjustments change, but equivalent $$$$
amount paid out remains approximately the
same.
0.1-Mile Bonus
2004 1 ½-inch surface $50 ton max bonus = $3712.50 per lane mile
2008 1 ½-inch surface max bonus = $7500 per lane mile
• Adjusting Manholes. When done by
adjusting ring method was raised from
$250 to $350, when masonry work is
required, it was changed from $350 to
being paid for as Extra Work.
JPC Pavement
No longer allow tube float finishing machines
No longer allow wet sticking tie bars at the longitudinal
joint. Bars must be must now be inserted in epoxy filled
drilled holes
Ride quality now measured with profiler in IRI, will no
longer be measured in PI with profilograph. Pay will be
under same system as asphalt with a different range.
Diamond Grinding – target IRI will be based on profile
Detectable Warnings for sidewalks and entrances
no longer a special note, now in Section 505
Additional requirements for concrete producers
when supplying to projects that contain 250 cy or
more concrete
Added emphasis on cold weather plan for placing
concrete. Recording thermometers required.
Cleaning and painting of structural steel updated
A2 material no longer allowed for pipe granular backfill.
New bedding requirements for concrete pipe
Plastic pipe must be NTPEP evaluated
Signed certification required for polish resistant aggregate
Traffic control devices updated to address LED assemblies
Special Note 10B Geogrid for Subgrade and Base
Courses now in Section 304
Special Note 10D geogrid for Asphalt Pavements
now in Section 412
Special Note for SMA now in Section 413
Special Note for Detectable Warnings now in
Section 505
Special Provision 13 for Crash Cushions now in
Section 725
Special Note 10U for Right of Way Monuments
now in Section 726
2008 Standard Specifications
A PDF version can be viewed at:
http://transportation.ky.gov/construction/
Order forms available up front.