NRC Cyber Security Regulatory
Program Development
Background
ANSI Nuclear Energy Standards Coordination Collaborative (NESCC) Meeting
November 3, 2014
Ralph Costello, Security Specialist
Cyber Security Directorate
Office of Nuclear Security & Incident Response
Introduction
• Inter-Agency Cooperation
• NRC Cyber Security Requirements
• Consequence-Based Approach
• NRC Inspections
• Cyber Security Reporting
• Next Steps
2
Inter-Agency Cooperation
on Cyber Security
3
NRC Requirements
March 2009 Cyber Security Rule (10 CFR 73.54)
– Requires that nuclear power plant licensees:
• “Provide high assurance that digital computer
and communication systems and networks are
adequately protected against cyber attacks . . .”
• “Establish, implement, and maintain a cyber
security program” to protect critical digital
assets (CDAs).
4
Scope of 10 CFR 73.54
• Safety-related and important-to-safety
functions,
• Security functions,
• Emergency preparedness functions, including
offsite communications, and
• Support systems and equipment important to
safety and security.
5
Phased Implementation
Interim Milestones 1-7 (completed by 12/31/2012)
• Cyber Security Plans
• Addresses key threat vectors
Milestone 8 (site specific dates through 2017)
• Full cyber security program implementation
• Procedures and training
• Complete all design remediation actions
6
Consequence-Based
Approach
• Graded approach
– Focus NRC and licensee resources on most
significant issues
– Direct vs. Indirect CDAs
• Grouping of CDAs
• Development of templates and examples for
efficiency and consistent implementation
7
NRC Oversight
• NRC inspections of Milestones 1-7 are ongoing
– 39 inspections completed to date
– Completion scheduled for 2015
• NRC inspections of full implementation of
cyber security implementation will begin in
2016 (Milestone 8)
8
Cyber Security
Event Notification Rule
• Reporting requirements
• Proposed rule was issued in 2011
• Public engagement
– Public meetings
– Public comments
• Final rule scheduled for 2015
9
Thank You
Questions
Comments
Discussion
10