FLAO commissioning with InfraRed Test
Camera (IRTC)
S. Esposito, G. Brusa, A. Riccardi
FLAO system external review, Florence, 30/31 March 2009
The Bent Gregorian Focus @ LBT
FLAO system external review, Florence, 30/31 March 2009
2
Commissioning campaign activity
rationale
The two main phases of the commissioning campaign follow the idea to
proceed in the test advancing in all system aspects (HW, control SW,data
reduction SW) at the same time. So, the first phase milestones is a closed
loop on-sky test with 200 modes and a bright star. This to recognize any
serious problem in any of the components or procedures used.
The second phase will then optimize the system in all aspects and will
contains the final test of the system on sky.
From FLAO_07 TOC
Phase I
Phase II
FLAO system external review, Florence, 30/31 March 2009
3
FLAO commisioning task list
Task name
Duration
(days)
Description
Milestone
Success criteria
LBT672a &
W#2 reintegration
10
Reintegration of LBT672
and W unit. Alignment
check. Units & FLAO
system functional checks
FLAO subsystem reintegrated.
Functional check
passed
FLAO System
compliance to
requirements
(compliance matrix)
FLAO
functional test
Commissioning
campaign
duration:
12
a) Telescope Installation of
FLAO system
FLAO system
W#2, retroaligned. IRTC
alignment in
-total timeLBT672a,
93 optics.
days
reflecting
IRTC.
aligned.
specifications.
(FLAO_09,FLAO_06)
b) FLAO aligned with retro-days 57 reflector.
15 days
a) Control SW test.
1 corrected
Closed loop done with
-nights
36
images
200 modes for high
5 nights
b) 1 light on sky in closed
Telescope
installation of
FLAO system
FLAO initial
test and 1st
light on sky
st
st
flux.
loop
FLAO closed
loop test.
20 days
17 nights
Closed loop test with FLAO
with different fluxes:
a) Engineering mode
b) Observing modes
Final system
test
14 nights
System performance test
FLAO closed
loop achieved in
engineering and
observing
modes.
SR values >= baseline
values defined in
FLAO_01.
FLAO system
FLAO performance >=
commissioned
baseline performance
FLAO system external review, Florence,
March 2009 defined in FLAO_01
with30/31
IRTC
4
FLAO re-integration & alignment
Total duration: 22 days, daytime 22 days
1. System and sub-system functional test completed (compliance matrix).
2. LBT672, W#2 and IRTC installed at the telescope.
3. FLAO aligned with retro-reflecting optics (including IRTC). (see
FLAO_06, FLAO_09)
FLAO system external review, Florence, 30/31 March 2009
5
FLAO system 1st light
Total duration: 25 days, daytime 20 days, nighttime 5 nights
Task summary: verification of system performance at the telescope
site in daytime. On sky test of source acquisition, pupil geometry
verification, close loop with high flux (engineering mode).
1st corrected images on sky with 200
modes (engineering mode).
FLAO system external review, Florence, 30/31 March 2009
6
Observing modes daytime & on sky
test
Total duration: 37 days, daytime 20 days, nighttime17 nights
Task summary: daytime fine calibration of system. Daytime closed
loop test with verification of system performance in engineering and
observing modes. On-sky test of system performance (both modes).
On sky system performance vs. star mag, r0, v0:
-engineering mode (baseline)
-observing mode (ACE/ICE) (baseline)
- ACE with on sky parameters optimization (goal)
FLAO system external review, Florence, 30/31 March 2009
[SR >= baseline
performance
(FLAO_06)]
7
Final on-sky FLAO test
Total duration: 14 days, nighttime14 nights
FLAO final test on sky:
repetition of a specific set of tests already done
in phase II (see FLAO_06)
Test list:
Closed loop test with:
-Engineering mode
-Observing modes
a) SLM, FSM
b) ACE
FLAO system external review, Florence, 30/31 March 2009
SR better then
baseline
performance
(FLAO_06):
8
FLAO commissioning resuming
table
The required manpower is found compatible with the available
resources of the group. The group relevant personnel is composed by
17 persons. About 5-7 FLAO
personnel
units will be available in Arcetri to
system external review, Florence, 30/31 March 2009
progress with FLAO#2 test in solar tower (13/01/10-06/07/10).
9
Conclusion
 The FLAO system telescope
commissioning plan with IRTC
has been formulated.
 Main tasks of commissioning
campaign have been identified.
 Duration of each task and
required manpower has been
evaluated.
 The schedule of the
commissioning campaign has
been shown.
FLAO system external review, Florence, 30/31 March 2009