Portland District Navigation Update
COL Steve Miles
Commander
Portland District
PNWA Annual Meeting
13 October 2009
US Army Corps of Engineers
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
2
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
What Happened:
Mar 07, 08, 09: Intermediate Repairs
Nov 07: Instrument Install
28 Sep 09:
►
►
►
►
Operator Identifies Possible Problem
Instrumentation Review
Remote Vehicle Inspect
Project Stops Operation
29 Sep 09:
►
►
Corporate Review
River Closed
30 Sep 09:
►
►
►
Diver Inspection
Dewatering
Letter Contract to AAC
1 Oct 09:
►
►
Cleaning / Inspection / Repair Plan
Repairs Begin
12 Oct 09: Lock Re-Opens
PORTLAND DISTRICT
3
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
The Problem:
PORTLAND DISTRICT
4
►
Cracks in both miter
gate leaves.
►
Gate vibrates upon
un-mitering/opening.
►
Gate has no
adjustability.
►
Lower 30’ not
mitering.
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
The Fix:
►
PORTLAND DISTRICT
6
Interior girder pockets
reinforced with boxes
bolted in place.
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
PORTLAND DISTRICT
7
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
The Fix:
►
►
►
►
►
►
PORTLAND DISTRICT
8
Interior girder pockets
reinforced with boxes
bolted in place.
Web of lower girder
doubled up and bolted into
place.
Replace and Re-tensioned
all pintle bolts.
Repaired 32 different areas
where cracks existed by
welding.
End post to quoin block
stiffeners reinforced with
bolted plates.
Additional Instrumentation
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
The Fix:
Interior girder pockets
reinforced with boxes
bolted in place.
► Web of lower girder
doubled up and bolted into
place.
► Replace and Re-tensioned
all pintle bolts.
► Repaired 32 different areas
where cracks existed by
welding.
► End post to quoin block
stiffeners reinforced with
bolted plates.
► Additional
Instrumentation
• Additional
Instrumentation
►
PORTLAND DISTRICT
9
BUILDING STRONG®
The Dalles Downstream Miter Gate
- Emergency Repairs
The Future:
►
Increased Monitoring
• Instrumentation
• Periodic ROV / Dive Inspections
PORTLAND DISTRICT
10
►
Engineering Review of repair work
needed during Long-Term Outage
►
Dec 09 (tent.): Interim Inspection &
Lock Closure (ICW Walla Walla)
►
Mar 10: Annual Outage
►
Mar 10 – Dec 10 (if needed):
Interim Inspection / Lock Closure
►
Dec 10 – Apr 11: Long-Term Outage
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
11
BUILDING STRONG®
Columbia River Channel Improvements
Project Completion: 31 Dec 10
FY 10 Work:
►
Completion of Dredging w/
Dredge Oregon (Summer ’10)
►
St. Helens:
•
•
•
►
Slaughter’s Bar:
•
•
PORTLAND DISTRICT
12
Dredging Begins 13 Oct 09
Blasting 1 Nov 09 – 28 Feb 10
Ross Island Disposal
Dredging RM 66+00 to RM 67+05
Dibblee Point Disposal
BUILDING STRONG®
Columbia River Channel Improvements
http://www.youtube.com/watch?v=tMxyspJgGHk&feature=related
PORTLAND DISTRICT
13
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
14
BUILDING STRONG®
MCR Jetty Major Rehab
View to NE
Columbia River
Estuary
Oregon
Washington
Jetty “A”
1 mile long
1938-39
North Jetty
2.5 miles long
1914-1917
South Jetty
6 miles long
1885-1913
Pacific
PORTLAND DISTRICT
15
Ocean
BUILDING STRONG®
MCR Jetty Major Rehab
Final approval in March 2010 (For FY ’12 Budget Cycle)
►
►
►
Recommended Plan: Review - Agency Technical Review
Model Code: Review - Planning Center of Expertise
Environmental Assessment: Public Review in November
The Recommended Plan:
►
►
Addresses North, South and Jetty “A”
Include spur groins and capping
View to NE
Columbia River
Estuary
Oregon
Washington
Jetty “A”
1 mile long
1938-39
North
Jetty 2.5
South
Jetty 6
miles long
1914-1917
Pacific
PORTLAND DISTRICT
Ocean
miles long
1885-1913
16
BUILDING STRONG®
=optional area to use concrete armor units - would preclude land access along crest for futre repair
50
Ocean Side
Mouth of Columbia River
Channel Side
40
Ocean Side
Channel SideInterim Re
Relic Armor
Core Ston
1v:2h
all st
MCR Jetty Major Rehab Elevation, MLLW
30
1v:3h
1v:3h
20
1v:2h
1v:3h
10
N
0
-10
MCR SouthRelic
Jetty
Nominal CrossCore
Section
Stone for Existing HEAD Condition STA 316
Armor Stone
and Proposed Head Rehab -20
Example
Original Seabed
Relic Armor Stone
50
40
-30
Core Stone
Original Seabed
30
-140
= spur groin
-120
-100
Elevation, MLLW
-40
SH1 concrete armor units: 10 to -10 ft MLLW = 15-25 ton (mean = 20 ton), or sized as needed
to resist
-260 -240
-220 wave
-200 action
-180 -160
0 -200 -180 -160 -140SH2
-120
-20= 25-45
0 ton20(mean
40 = 3460
100
120
Relic-100
Stone:-80
-10 to-60
-20 ft-40
MLLW
ton) 80
South
all stone
has gamma=167
lb/ft3
Distance from
centerline,
ft
North
South
-80
-60
-40
-20
0
North
Ocean/Beach Side
Channel Side
60
80
100
10
120
New Rock
0
Existing Rock
-10
Sand Foundation
-30
-40
-260 Section
-240 -220
-200 -180Condition
-160 -140
for Existing
1v:2.5hMCR South Jetty Nominal Cross
1v:2.5h
and Interim Repair Template
SA1 stone: 25 to 0 ft MLLW = 35-60 ton (mean = 50 ton)
SA2 Stone: 25 to -10 ft MLLW = 8-20 ton (mean = 14 ton)
SA3 Relic Stone: -10 to -20 ft MLLW = 5-15 ton (mean = 10 ton) Re-worked
RelicStone
Armor
Stone
Reworked Relic Armor
= 5-15
ton (mean = 10 ton) Relic Armor Stone
Reworked Core Stone = 0.5 - 7 ton (mean = 4 ton)
all stone has gamma=167 lb/ft3
Pacific
Ocean
40
North
-20
1v:3h
MCR South Jetty Nominal Cross1v:3h
Section for ENCASEMENT
REHAB OPTION - SA
20
20
Distance from centerline, ft
-120
Dis
Interim Repair = Reach A, 9-22 ton (mean = 15 ton) / Reach B, 13-32 tone (mean 22 ton)
Relic Armor Stone = 5-15 ton (mean = 10 ton)
Core Stone = 0.5 - 7 ton (mean = 4 ton)
all stone has gamma=167 lb/ft3
Original Seabed
= SA2 select armor units: 5 to -10 ft MLLW , stone = 18 - 30 ton (mean =24 ton)
=optional area to use concrete armor units - would preclude access along crest for future repair
South
-200 -180 -160 -140 -120 -100 -80
-60
-40
-20
0
20
40
50
60
North
80
100 120 140 160 180 200
Distance from centerline, ft
Ocean Side
40
Channel Side
Ocean Side
1v:2h
Relic Armor Stone
Elevation, MLLW
30
1v:2h
1v:2h20
Existing Core Stone
Channel Side
10
0
-10
Existing Core Stone
SOUTH JETTY MAJOR REHABILATION
PORTLAND DISTRICT
Original Seabed
-20
-30
-40
Relic Armor Stone
17
Original Seabed
BUILDING
STRONG®
MCR Jetty Major Rehab
Initial Priorities:
- Major scour areas on South Jetty Beach
- Depressed area north of North Jetty
South Jetty
HIGH
DUNE
31 JAN 2006
LOW Backshore
Trestle Bay
North Jetty
PORTLAND DISTRICT
18
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
19
BUILDING STRONG®
MCR Buoy Installation
DATAWELL
Directional
Wave Buoy
CDIP Wave Rider
Buoy
PORTLAND DISTRICT
Constructed in the Netherlands
Centimeter accuracy in wave height
Data transmitted via satellite.
All data are disseminated on the
CDIP
Website updates @ 30 minutes.
Alert system if buoy breaks loose.
20
BUILDING STRONG®
Washington
Mouth of the
Columbia River
(MCR)
South Jetty
Oregon
PORTLAND DISTRICT
21
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
22
BUILDING STRONG®
Portland / Walla Walla District:
5-Year Planning
Joint Portland / Walla Walla Long-Term Planning
since 2006
In 2007: Identified Columbia and Snake River Project
Maintenance / Repair Needs and draft timeline
Served as basis for Dec 10 – Apr 11 Outage
Next steps: Update and Refine FY 12 to FY 14 Needs
PORTLAND DISTRICT
23
BUILDING STRONG®
Columbia River Long-Term Outage
(Dec 10 – Apr 11)
The Dalles, John Day & Lower Monumental
Extended Navigation Lock Outage
Dec
Jan
Feb
Mar
5
May
June
27
16 Weeks
The Dalles
13
?
Incentive (The Dalles)
5
27
10-14 Days
13
14 Weeks
John Day
13
10
Lower Monumental
Apr
13 Weeks
27
Normal Outage
13
14 Days
3
………….
BIOP
27
Unscheduled Extension
PORTLAND DISTRICT
3
5 Days
24
BUILDING STRONG®
The Dalles Critical Repairs
(Dec 10 – Apr 11)
History
Mar 06, 07, 08: Intermediate
Repairs
Mar 07: Instrument Install
Sep 09: Emergency Outage
Dec 09: Tentative Short-Term
Outage
Mar 10: Normal Outage –
Prep for Long-Term Repairs
FY 10: $5 mil for TD Repairs
PORTLAND DISTRICT
25
BUILDING STRONG®
The Dalles Critical Repairs
(Dec 10 – Apr 11)
Scope of Repairs
Replace Pintle Bearing
Assembly
Replace Quoin Block Assembly
Replace Miter Assembly
Replace lower Portion of Gate
Re-establish Load Path
-Quoin Block
-Miter Blocks
PORTLAND DISTRICT
26
-Pintle Bearing
BUILDING STRONG®
The Dalles Critical Repairs
(Dec 10 – Apr 11)
Acquisition Strategy
Feb 10:
2 Supply Contracts
►
►
Pintle Assembly
Adjustable Quoin and Miter
Block Assembly
Apr 10: Repair Contract
-Quoin Block
-Miter Blocks
PORTLAND DISTRICT
27
-Pintle Bearing
BUILDING STRONG®
John Day Critical Repairs
(Dec 10 – Apr 11)
History
Mid -90s: Critical D/S Gate Repairs
Jul 07: Cracking in Friction Drum
FY 08 – FY 10: Major Rehab Study
Jan 08: Friction Drum Cracks Expand
Mar 08: Friction Drum Emergency Repair
FY 10: Friction Drum Replacement
FY 09: ARRA for D/S Gate Replacement
PORTLAND DISTRICT
28
BUILDING STRONG®
John Day Critical Repairs
(Dec 10 – Apr 11)
Scope of Work
Replace D/S Gate
Replace Friction Drums
Acquisition
Contract Awarded to Advanced American
Construction (AAC) for Fabrication and Installation
PORTLAND DISTRICT
29
BUILDING STRONG®
John Day Major Rehab Report
3 Year Study (2008-2010)
Issues / Concerns
► At Start (62)
► Currently (4) (Includes D/S Gate
and Friction Drums)
► In Final Report (Est 2)
• Movement of Lock Monoliths
(Needs Stabilizing)
• Spillway Gates (May Need
Strengthening)
North Wall
Monolith Cracking
PORTLAND DISTRICT
30
Implement Repairs
► Depends on Report Approval and
Funding (Approx 3-5 Years)
BUILDING STRONG®
Topics
The Dalles D/S Gate Emergency Repairs
Columbia River Channel Improvements
MCR Jetty Major Rehab
MCR Buoy Installation
Long-Term Planning
► Joint Portland / Walla Walla 5-Year Planning
► Columbia River Long-Term Outage (Dec 2010)
• The Dalles
• John Day
PORTLAND DISTRICT
31
BUILDING STRONG®
Portland District Navigation Update