Transcript Slide 1
2010 WATER TREATMENT DECISION 1 PRESENTATION OBJECTIVES Update information • Decision framework • Evaluation criteria for considering options • Cost estimates • Risk • Public outreach & input Identify • Areas of concern about information 2 PRESENTATION OVERVIEW Problem recap Project team & approach Water treatment alternatives analysis & what others are doing Frame alternative decision criteria – benefits & values Risks = Consequence x Likelihood Costs – Initial capital + Operations & Maintenance = Life cycle Public outreach & response Next steps & schedule 3 GREEN RIVER TREATMENT DECISION – PROBLEM RECAP Federal regulations • New federal law requires treatment for cryptosporidium to further protect public health. Beyond new law - 12 pre-existing requirements • “Criteria to remain unfiltered” Other risks & issues • Future drinking water regulations • Non-regulatory water quality challenges • Cost Cannot avoid additional water treatment • Options vs. risks = best long-term value Recommendation to be made by end of 2009 for April 2014 compliance 4 PROJECT TEAM HDR & CH2MHILL Consultant s • Water Treatment & Cost Estimating • Decision Science Tacoma Water Staff & Executive Management • Water Treatment & Operations and Maintenance • Customer relations & project financing Tacoma Public Utilities – Community & Media Services • Public Outreach planning & execution • Communications Regional Water Supply partners (Lakehaven Utility District, City of Kent, Covington Water District) •Water Treatment, Operations & Maintenance •Regional water supply perspective 5 PROJECT APPROACH We are here 11/12/09 HDR / CH2MHILL Process chart 6 WATER TREATMENT ALTERNATIVES 13 evaluated; four chosen for review (see analysis report on website) UV light disinfection 1. With storage 2. Without storage – significant discussion on feasibility of operation Filters 1. Hybrid - Pretreatment (settling of high turbidity) for winter capacity only 2. Conventional – Pretreatment (settling of high turbidity) for full plant capacity 2040 Design capacity • 90 MGD Winter Where will these fit? • 150 MGD Summer 7 HOW OTHER MAJOR UTILITIES TREAT (OR PLAN TO) Public Water System Seattle Portland UV Technology Filtration X X (Cedar Supply) (Tolt Supply) X (Bull Run) MWRA (Boston) X (Quabbin/Wachusett Supply) Vancouver B.C. San Francisco 8 X X (Coquitlam Supply) (Seymour & Capilano Supplies) X X (Hetch Hetchy Supply) (Alameda County Supply) HOW DO OTHER UTILITIES COMPARE TO TACOMA? Seattle The Cedar Supply is nearly entirely (>99%) owned by SPU; the Tolt a blend of SPU and USFS ownership. Cedar has lower routine turbidity, and SPU has the 15 billion gallon Lake Youngs reservoir for storage and sustained supply during river turbidity events. Lk. Youngs can have algae problems. Portland The Bull Run Watershed is 100% USFS owned with federal restrictions on use. Reservoir is maintained relatively full, and elevated turbidity is very rare. Water is withdrawn directly from reservoir – Portland is making a large investment in intake reconstruction. Portland can sustain operations in winter with groundwater. MWRA (Boston) Quabbin/Wachusett Supply very high quality with not a single fecal coliform sample over 20 CFU/mL since 2004, and turbidity almost always < 1 NTU. Water travel time through the reservoirs measured in years. Periodic algae challenges. Vancouver B.C. Vancouver has three, side-by-side protected watersheds. They have opted to filter two of them , largely for turbidity control reasons, and have ozone and are installing UV on the third. Reservoirs are maintained in a generally full condition, and water is withdrawn directly from the reservoirs. Canada does not have an equivalent regulatory system. San Francisco Hetch Hetchy Supply comes from Yosemite National Park, and a strongly protected watershed. Withdrawal is directly from the dam, with very low turbidity (maximum <0.5 NTU during 2006 – 2008). The Alameda supply is a smaller watershed that includes developed areas, and is filtered. 9 MAJOR DIFFERENCES FOR TACOMA Green River Diversion • Ongoing turbidity issues • Only system to dilute turbidity by blending Multiple landowners – commercial interests Federally controlled dam with defined missions • Flood control – important, but creates unique water quality challenges • Fish passage (future) – important, but will create water quality challenges • River flow augmentation • Municipal supply (full allocation awaits fish passage) No clearwell storage – an operational challenge 10 TAILOR DECISION TO GREEN RIVER SUPPLY Simple cost comparison inadequate to evaluate alternatives Root evaluation in multiple objectives of Water mission • Protect public health • Support the economy of the region • Be appropriate resource stewards • Make Tacoma a better place to live and work Aspects of the Mission difficult to monetize • Values – Identify & characterize how values relate to options & assign importance for comparison 11 FRAMING DECISION CRITERIA – BENEFITS & VALUES Water Quality & Public Health Protection Cost Regulatory Requirements Developed comprehensive list of values • All Tacoma and Partners staff and management participated Developed criteria to capture breadth of values • Criteria are exhaustive, measureable and differentiate between options Categorized values • Balanced group representation organized many values into six categories Reliability & Yield Created evaluation model • Criteria weighted by participants • Options rated against criteria Operations Interactive model will be brought to November 18 meeting Sustainability 12 Very High PICTURE OF RISK Consequence x Likelihood Categories considered Very Low 3. Non-regulatory risks could prompt action Consequences 2. The regulatory future – a cloudy crystal ball Low Medium High 1. The 12 “Criteria to remain unfiltered” – filtration triggers Very Low 13 Low Likelihood Medium High Very High PICTURE OF RISK - Criteria to remain unfiltered Very High 1. Source water Fecal Coliform limits (6 month running average) 2. Disinfection Byproducts (chlorine + natural organics) below specific levels High 3. Turbidity Limits 4. Watershed Control 5. Giardia and virus disinfection Medium 6. Daily certified laboratory access 7. No waterborne disease outbreaks 10.Maintenance of chlorine throughout the system 11.Compliance with Coliform bacteria requirements 12.Annual inspection of watershed & treatment facilities 14 Low Very Low 9. Continuous chlorine into the system Consequences 8. Redundant disinfection equipment Very Low Low Likelihood Medium High Very High RISKS - continued Regulatory “Crystal ball” • We believe with high certainty regulatory complexity will not decrease • EPA is compelled to publish a “Contaminant Candidate List” every five years & make regulatory determinations for at least five contaminants. • Regulatory evolution – Cryptosporidium case study 15 RISKS - continued Non – regulatory water quality risks • Multiple issues at Howard Hanson Dam Fish passage (change in temperature, algae impacts & organics) Sediment management (Increasing issue in recent years & likely to continue) Structural repairs • Elevated Iron & manganese (yellow water) • Railroad operations & expansion • Fire potential Non – regulatory, non-water quality risks • Lost opportunity risk – product acceptance 16 COST ESTIMATES Refine initial 2008 estimates • Critical objectives Establish one set of capital & long-term operating costs Consider life-cycle costs Clearly define assumptions • Use CH2MHILL cost estimation model – initial estimates out 9/09 (still -30% / +50% level of estimate) • Refine cost estimating criteria – finalized 9/09 • Further define issues with narrow & wider uncertainty (10-13-09 workshop) • Capture best cost estimates for capital, operations & maintenance 17 PREVIOUS AND UPDATED COSTS Treatment Option Previous (2008) Cost Estimate (millions) Range (-30%/ +50 %) Best Estimate Capital Conventional Filtration Hybrid Filtration UV with Clearwells UV without Clearwells O&M Not Estimated Revised Cost Estimates (millions) Estimate Range (-15 % / +30%) Low Estimate Capital Best Estimate Capital High Estimate Capital O&M $162 $187 $239 $5.1 $140 $6.5 $146 $169 $217 $4.1 $70 $1.0 $68 $80 $105 $1.5 $40 $47 $63 $1.2 Not Estimated Areas of change: UV with Clearwells: Added pump station, site work, electrical facilities , added project delivery costs. Hybrid Filtration: Added sitework piping, interconnection with existing facilities, added project delivery costs. 18 ESTIMATED RATE IMPACT OF ALTERNATIVES Treatment Option Average Existing Bill $/Month % Increase* Inside City** Outside City** Impact to Bill $/Month* Inside City Outside City Hybrid Filtration $24.18 $32.36 16% - 20.8% $3.87 - $5.03 $5.18 – $6.73 UV with Storage $24.18 $32.36 6% - 7.8% $1.45 - $1.89 $1.94 - $2.52 *Impact due to treatment alone. These ranges are rate impacts based on the Best Estimate capital and O&M costs, and the Best Estimate costs plus 30%. ** These are averages across the Residential Class for 2008 Please note that these are estimates based on an assumption that the average system-wide rate impact will be used for this rate class (residential). Additional analysis is required to complete the detailed rate impacts across all customers. 19 COST AVOIDANCE, SAVINGS & POTENTIAL REVENUE ECONOMIC ASSUMPTIONS Assumption Inputs Bonding for Entire Project Cost Best Estimate Bond Horizon 30 years Annual Bond Interest Rate 5.0% Annual Inflation Rate 3.0% Infrastructure Lifecycle 40 years Discount Rate 4.5% 21 40-YEAR LIFECYCLE COST COMPARISON PUBLIC OUTREACH Communication • Protect & Serve Your Water 2008 – Water Quality Report • U* customer newsletter articles Summer & Fall 2009 • Dedicated informational Web page: tacomawater.com/decision • Tacoma Water home page ad • Bill insert mailed to 180,000 customers September & November 2009 • Water Treatment Decision – CityScape & Cityline, TV Tacoma September 2009 • Power Point presentations to target audiences • The News Tribune – Kathleen Cooper • Handout - TNT article, Tacoma Water’s worries • Water Treatment Decision newsletter (business customers) •Q&A • Citizen Stakeholders’ Survey 23 PUBLIC OUTREACH What we’ve heard Stakeholder Advisory Panel survey 24 SCHEDULE November 4, 2009 Presentation to the Public Utility Board with information about the public input, risks, considered benefits & costs for options December 16, 2009 Presentation to Public Utility Board with information about public input & a staff recommendation for treatment November 12, 2009 Third meeting of the Citizen Advisory Committee – review risks, benefits & costs for options January – March, 2010 Follow up with any additional information requests from the Public Utility Board & City Council November 18, 2009 Continued presentation to the Public Utility Board with information about the alternatives analysis and interactive work with the decision model. Develop additional information on project delivery alternatives Finalize project report November 19, 2009 Presentation to City Council Environment & Public Works Committee on project approval, execution, timing & cost of options Other presentations, including to Pierce County Council Committee, University Place Council and public, and interest groups are not all listed. 25 FOR MORE INFORMATION On the Web Tacoma Water www.tacomawater.com/decision EPA – New Surface Water Treatment Rule www.epa.gov/safewater/disinfection/lt2/ Contact Us Community and Media Services Water Conservation Sonja Hall Dan Muir (253) 502-8223 [email protected] [email protected] Water Quality Chris McMeen (253) 502-8723 (253) 502-8210 [email protected] 26