Protecting Electric Power Systems

Download Report

Transcript Protecting Electric Power Systems

SC B5 - Protection and Automation
Report to
the Canadian National Committee of Cigré
2007
Simon R. Chano
Protection Specialist
Hydro Québec
TransÉnergie
800 de Maisonneuve est, 22ième étage
Montréal, QC H2L 4M8
CIGRÉ STUDY COMMITTEES
B5 Protection and automation



System protection
Substation control, automation, monitoring and
recording including internal and external
communications, substation metering systems and
interfacing for remote control and metering
All technical, organisational and economical aspects
are considered including staff education and training.
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-2-
B5 Subcommittee Organization
SC B5 Chair – Ivan Mesmaeker (CH)
SC B5 Secretary – Paul Hindle (UK)
Three Advisory Groups (Since August 31 31,2006)
 AG 51 – Substation Automation and Remote Control:
Convenor J.M. Ordacgi Filho (BR)
 AG 52 – Protection of main plants and circuits:
Convenor M.S. Sachdev (CA)
 AG 53 – Metering, monitoring, recording and overall
power system protection:
Convenor G.J. Amantegui (ES)
 AG 4 – Asset and Information Management:
Convenor F. Koers (NL): Prior to August 31, 2006
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-3-
AG 51 - Substation Automation and Remote Control
WG B5-11 The introduction of IEC 61850 and its impact
on protection and control within substations
 preparing a report – expected completion 2007
WG B5-13 Acceptable functional integration in HV
substations
 preparing a report – expected completion 2007
WG B5-36 Application for protection scheme basedon
IEC 61850
 preparing a report – expected completion 2009
WG B5-92 Functional testing of 61850 based systems
 preparing a report – expected completion 2010
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-4-
AG 52 – Protection of main plants and circuits
WG B5-02 Coordination of digital relays and conventional
instrument transformers
 preparing a report – expected completion 2007
WG B5-04 Modern techniques for protecting and
monitoring of generating plants
 preparing a report – expected completion 2008
WG B5-05 Modern techniques for protecting, controlling
and monitoring power transformers
 preparing a report – expected completion 2007
WG B5-07 Modern techniques for protecting and
monitoring of transmission lines
 preparing a report – expected completion 2008
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-5-
AG 52 – Protection of main plants and circuits
WG B5-10 Protection of series compensated lines and
series capacitor banks
 preparing a report – expected completion 2007
WG B5-15 Modern applications of distance protection
 preparing a report – expected completion 2007
WG B5-16 Modern techniques for protecting busbars in
HV networks
 preparing a report – expected completion 2007
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-6-
AG 53 – Metering, monitoring, recording and overall power
system protection
WG B5-03 Fault and disturbance data analysis including
intelligent systems
 preparing a report – expected completion 2007
WG B5-19 Protection relay coordination
 preparing a report – expected completion 2007
WG B5-20 New trends for automated fault and
disturbance recording and analysis
 preparing a report – expected completion 2009
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-7-
AG 53 – Metering, monitoring, recording and overall power
system protection
WG B5-08 Protection and control for dispersed
generation and impact on transmission
 preparing a report – expected completion 2007
WG B5-34 The Impact of Renewable Energy Sources
and distributed Generation on Substation Protection and
Automation
 preparing a report – expected completion 2008
WG B5-21 New local protection and control approaches
to minimize the impact of system disturbances
 preparing a report – expected completion 2007
TF B5-94 High impedance faults
 preparing a report – expected completion 2007
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-8-
Newly Formed WG
WG B5-31 Management of protection settings
 preparing a report – expected completion 2009
WG B5-37 Protection, Monitoring and Control of Shunt
Reactors
 preparing a report – expected completion 2010
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
-9-
Canadian participation
Leadership roles
 Simon Chano (HQ)
 B5 Canadian Representative
 B5-52 Advisory group member
 Convenor WG B5-07
 Secretary WG B5-15
 Corresponding member WG B5-19
 Corresponding member B5-05
 Federcio Lopez (SNC-Lavalin)
 Member WG B5-07
 Pouria Naisani
 Convenor WG B5-37
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
- 10 -
Canadian participation
Leadership roles
 Mohindar S. Sachdev (U of Saskatchewan)
 Convenor Advisory Group 2
 Web Master
 Member Strategic Advisory Group of SC B5
 Convenor WG B5-05
 Member WG B5-07
 Member WG B5-15
 Member WG B5-17
 Brian Sparling
 Corresponding Member WG B5-05
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
- 11 -
2007 SC meeting
Madrid, Spain
 October 15 to 20, 2007

Highlights:

PS1: New Trends on Bus Bar Protection
PS2: Acceptable Functional Integration in Substation
P&C for Transmission Systems
PS3: Protection of Transmission Lines & Coordination
of Transmission System Protection


2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
- 12 -
Concluding Remarks
Study committee actively examines protection and
automation issues
Discusses the issues and provides reports on those
issues
Promotes power engineering education
Conducts tutorials at the SC meetings
B5 tries to get participation from utility engineers,
consultants and academia
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
- 13 -
Web site
SC address : web site is
http://www.cigre-b5.org
For additional information, you can contact me
[email protected]
2007 - 08 -26
Simon R. Chano, Hydro Québec TransÉnergie
- 14 -