Diapositive 1 - Barents Service

Download Report

Transcript Diapositive 1 - Barents Service

Thibaut CARTIGNY
Guillaume PRADURAT
Engineering school, Nancy, FRANCE
5th and last year
1 year as ERASMUS students
Project about Transportation of natural gas from Hammerfest to
Norrbotten and Northern Finland
04/10/2007
CARTIGNY PRADURAT TEDELID
1
Introduction
Semi-trailer
Pipeline
Melköya, Hammerfest
30 years
Train
04/10/2007
Ship
CARTIGNY PRADURAT TEDELID
2
Liquefaction
Liquefying plant
2.5 G$
1-15 Mtons LNG/ year
6TWh equivalent to 400 000tons
04/10/2007
CARTIGNY PRADURAT TEDELID
3
Regasification
-Warm the gas in a
controlled environment
- Either a big plant or
small ones
-Small plants: from 23
to 1500m3, from 400
000 to 10M$.
- Big plant: from 100
000 to 1M m3, around
500M$.
04/10/2007
CARTIGNY PRADURAT TEDELID
4
The total demand of LNG in Norrbotten and in
the north part of Finland
Total [GWh]
Area 1
691
Area 2
2189,3
Area 3
3157
6037,3
Sum [GWh]
04/10/2007
CARTIGNY PRADURAT TEDELID
5
Transportation by semi-trailers
• Size: 50 m3 of LNG per truck so 0.3GWh
• 800km of road from Hammerfest to Kiruna or to
Lulea
• 1.5 hours for loading and same unloading
• Cost: 440 000 $
• This option Needs:
– 330 trucks at the same time for 6TWh per year!!
– Many small re-gasification plant
• But the cost doesn’t depend of the demand
04/10/2007
CARTIGNY PRADURAT TEDELID
6
04/10/2007
CARTIGNY PRADURAT TEDELID
7
Transportation by trains
• Size: 30 wagons per train, one wagon transports 110 m3 of
LNG so 690MWh
• 500km of railway between Narvik and Lulea
• 2 travels per week per train maximum to distribute all
destination so 2TWh per year
• Cost: 135$/day/wagon
• This option needs:
–
–
–
–
–
04/10/2007
One ship between Hammerfest and Narvik
3 trains for 6TWh
One tank per destination because the train can’t wait
Some trucks for the industries far from the railway
Many small re-gasification plants
CARTIGNY PRADURAT TEDELID
8
Transportation by ship
•
•
•
•
•
•
•
Size: between 40 000 and 200 000 cubic meter of LNG
125 000 m3 of LNG represent 750GWh
4000km from Hammerfest to Lulea so 1 week
For 6TWh we need 8 ships per year, one ship every 45 days
One ship consumes 1080 tons of gas per travel
Cost: 150 millions $
This option needs:
– One ship
– One big terminal next to Lulea
– A network of pipeline to distribute gas to each industry
04/10/2007
CARTIGNY PRADURAT TEDELID
9
Transportation by pipeline
•
•
•
•
•
•
•
•
•
•
Pipes, compression stations, valves…
The gas is moved by the pressure gradient
The pressure is around 70bars
For 10TWh/year, we need a 8” main pipe
For 40TWh/year, we need a 16” main pipe
Power installed: 11MW for 10TWh, 50MW for 40TWh
Nearly no leakage, pipeline buried, very few accidents
No terrorism in Northern Scandinavia
Compressors driven by electrical motors
Compressors themselves environmentally friendly
04/10/2007
CARTIGNY PRADURAT TEDELID
10
Pipelines planning
04/10/2007
CARTIGNY PRADURAT TEDELID
11
Pipelines economy
10TWh
Capacity per year
Cost per year for transportation only
Cost per MWh for transportation only
6 TWh
7,2 M$
1,2 $/MWh
Cost per MWh on 10 years with investment
8,1 $/MWh
Cost per MWh on 30 years with investment
3,5 $/MWh
40TWh
Capacity per year
Cost per year for transportation only
Cost per MWh for transportation only
6 TWh
32,4 M$
5,4 $/MWh
Cost per MWh on 10 years with investment
18,4 $/MWh
Cost per MWh on 30 years with investment
9,7 $/MWh
04/10/2007
CARTIGNY PRADURAT TEDELID
12
Comparison of the different options for a demand of 6TWh
per year and without the cost for extraction of natural gas
Type of
transport
Cost in $/MWh with a
paying off investment
in 10 years
Cost in $/MWh with a
paying off investment
in 30 years
Construction
time
including
study
Capacity maximum
that can transport
per year
Ship
19.26
10.18
5 years
26TWh (re-gasify
plant capacity)
Train
9.95 (13.15 if not next
to a railway)
8.28 (11.48 if not
next to a railway)
3 years
~8TWh (4 trains)
Truck
21.3
21.3
1 year
~1TWh (55 trucks)
Pipeline,
10TWh
8,11
3,51
5-6 years
10TWh
Pipeline,
40TWh
17,71
9,11
5-6 years
40TWh
04/10/2007
CARTIGNY PRADURAT TEDELID
13
Comparison of all options in function of the demand
with a paying off investment in 10 years
Costs in $/MWh
70
pipeline
10TWh
60
pipeline
40TWh
50
ship +
pipeline
10TWh
ship +
Pipeline
40TWh
40
Trucks
30
Trains
20
10
0
0
04/10/2007
5
10
15
CARTIGNY PRADURAT TEDELID
20
25
Demand in TWh
14
Comparison of all options in function of the demand
with a paying off investment in 30 years
Costs in $/MWh
60
pipeline
10TWh
50
pipeline
40TWh
40
ship +
pipeline
10TWh
ship +
pipeline
40TWh
30
trucks
trains
20
10
0
0
04/10/2007
5
10
15
CARTIGNY PRADURAT TEDELID
20
25
Demand in TWh
15
Conclusion
• Demand of roughly 6TWh per year at the moment
• Either on environmental or economical point of
views, the best way is to start with trucks until 1TWh,
then to continue with pipelines
• The size of the pipeline will depend on the demand
for the next 30 years
• Trains could be used until 8TWh during the
construction of the pipeline
• Ships are too expensive compared to the others
04/10/2007
CARTIGNY PRADURAT TEDELID
16
Thanks for your attention !
04/10/2007
CARTIGNY PRADURAT TEDELID
17