Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Niland Sanitary District
Wastewater Systems Improvements
Niland, California
Presented to:
Project Sponsor and Agency
Stakeholders
November 5, 2003
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Agenda
General Aspects
Environmental and Human Health Indicators
Environmental, Human Health and Sustainable
Development Strategies
Technical Approach, Objectives and Funding Plan
Public Participation
Project Development Schedule
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Project Location
The community of Niland:
Located in eastern California, in Imperial County;
Approximately 150 miles east of San Diego;
Approximately 50 miles north of the U.S./Mexico Border.
Niland
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Project Sponsor Profile
Niland Sanitary District (NSD)
Niland Population: 1,143 (Census 2000)
Slab City – Transient community located 4 miles east of Niland; Impact
upon Niland infrastructure is currently inconclusive.
Median Household Income (Census Data): $25,592
Unemployment Rate: 15.9%
Existing Facilities
Wastewater
400 Sewer service connections;
Water
Privately owned by Southern California Water Company;
Ineligible for grant funding.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Existing
Water, approximately 60,000 gpd, is obtained from Imperial Irrigation District;
Distribution system is owned and operated by the Southern California Water
Company;
Customers may pay a flat rate of $41.78 / month or a metered service charge of
$24.10 plus $1.11 per CCF
Concerns
Existing Water Distribution System
Currently only 60% of the customers are metered; Requirement for 100% meted by
2010;
Difficulty determining illegal connections due to non-metered service;
Inadequate system pressure;
Maintenance problems with 2-inch lines;
Turbidity through the filters at the Treatment Plant has been observed;
Public perception is unfavorable. General distrust for rate increases and inadequate
servics and new requirements by PRC. .
Current Improvements
Water Treatment Plant Expansion in Calipatria;
Construction of transmission main to Niland to service both communities.
1.5 MG storage facility.
Water system privately owned and is ineligible for grant funding to develop improvements.
.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Existing Wastewater Collection and Treatment System
Collection
Lift Station
Existing system consists of 32,000 linear feet of sewer lines;
Currently exists 400 service connections.
One wastewater lift station at WWTP;
Treatment
NSD has an aeration pond system constructed in 1993;
Maximum average design flow is 0.5 MGD;
Currently operating at 50%;
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Wastewater System Deficiencies
Collection
Lift Station
Sewer mains constructed over fifty years ago;
Numerous line breaks;
Groundwater infiltration into collection system is suspected.
Internal corrosion due to operation and minimal maintenance;
Emergency provisions are inadequate;
Pump accessibility for maintenance and repairs is limited.
Treatment
Existing screening is inadequate and results in blockage throughout plant;
Elevated levels of copper, selenium and thallium with source unknown;
E. Coli detected in plant effluent;
Overflow at ponds observed;
Minimal maintenance has possibly decreased the pond capacity;
Numerous violations issued for BOD5 and Total Suspended Solids;
Condition of liners is undetermined;
Access to WWTP is hazardous.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Proposed Wastewater System Improvements
Evaluation and inspection of the existing system will assist in selecting
and implementing the necessary improvement to include the following
possible alternatives:
Collection
Rehabilitation/Replacement of existing system;
Install clean-outs at the dead ends;
Rehabilitation of existing manholes as required.
Lift Station
Rehabilitation of wet well interior;
Equipment upgrades to ensure sufficient redundancy.
Treatment
Upgrade testing laboratory as needed;
Install a commutator to improve the current screening operations;
Improve water transfer between ponds;
Provide additional aerators;
Provide stand-by power;
Total Estimated Cost - $TBD
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Existing System
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Existing System
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
General Aspects
Existing System
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Environmental and Human Health Indicators
Environmental Indicators
Levels of E. Coli, violating state regulations have been observed in
effluent and may pose potential health risk downstream of discharge
Existing plant not designed to treat copper, selenium and thallium at the
WWTP and discharge within the effluent may be occurring;
Elevated levels of BOD5 in violation of state regulations have been
observed at the WWTP effluent;
Lack of maintenance at plant may have reduced capacity thus reducing
efficiency and worsening conditions above;
Numerous lines breaks and manhole leaks have created nuisance condition
throughout Niland;
Potential groundwater contamination may affect environmentally sensitive
areas including farmland, habitats for protected species and water bodies
including the Salton Sea.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Environmental and Human Health Indicators
Compliance with Environmental Norms & Regulations
Water System
Wastewater System
Administrative Civil Liability Complaint issued by California Regional
Water Quality Control Board for numerous violations;
Majority of violations related to BOD5 in effluent;
Levels of copper, selenium and thallium exhibited a reasonable
potential to cause an excursion above water quality standards in
violation of the priority pollutant monitoring under the California Toxic
Rule (CTR).
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Environmental and Human Health Strategies
Determine the CEQA/NEPA document requirements, an EIS or
EA.
Analyze the chemical composition of the wastewater and
groundwater to determine the nature and possible source of
contaminants existing at the WWTP.
Conduct an analysis of the WWTP influent to detemine the
sufficiency of oxygen as it is introduced in the treatment process.
Describe the environmental and human health risks associated
with the deteriorated conditions of the existing collection system
infrastructure as well as with the WWTP and effluent violations.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Sustainable Development Strategies
Two stakeholder workshops to be conducted. The baseline conditions report is
complete.
Demonstrate appropriate institutional capacities:
Establish permanent operation staffing
Regional Operations – Shared operators with City of Calipatria or other.
Improve rate structure and collections
Restructured User Rate collected monthly – Agreement with water provider/Imperial
County.
Seek Training
NADB UMI; Operator and administrative development
An operation and maintenance program will be developed as part of the
project.
Coordinate with water provider to develop a water usage assessment,
including possibilities for conservation/reuse.
Determine if there is a need for industrial pretreatment.
30% design review by system operator
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Technical Approach,Objectives
and Funding Plan
Project Objectives
Provide the NSD customers with adequate, affordable wastewater service in
compliance with State regulations;
Rehabilitation of existing centralized wastewater collection system and
improvement to existing treatment facilities;
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Technical Approach,Objectives
and Funding Plan
Recommended Technical Approach
PDAP Eligible Tasks:
Preliminary Engineering Report
Quality Assurance Program Plan (QAPP) - TBD
Environmental Report – Complete comprehensive MultiAgency Environmental Checklist to ensure all requirements
are satisfied.
Financial Analysis
Public Participation Program
Final Engineering Design
Non-PDAP Eligible Tasks:
Rate study.
Training and institutional strengthening.
Contingency Plans
Project Management
Operation and Maintenance Plan
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Technical Approach, Objectives
and Funding Plan
Institutional Capacity
The Frank M. Tejeda Center has been contacted to prepare a Statement of
Institutional Capacity of the City of Calipatria addressing the following :
Outsourcing
Regulatory Compliance Issues
Operational Capacity
On-going Projects and Planning
Management Capabilities
Existing Planning
Governance
Project Development and Funds
Management
Institutional Development RAP Recommendations:
Revised Rate Structure/Collections Procedures
Administration/Operations Staffing – Potentially Regional Effort
Training
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Technical Approach, Objectives
and Funding Plan
Project Sponsor Financial Potential
Revenue generated by collections of a $279 annual property tax assessment;
Imperial County has a role in the financial operations;
Fiscal year from July 1st to June 30th for each year;
Wastewater Fund
2000
2001
2002
Operating Revenues
146,254
161,032
205,816
Operating Expense
260,576
257,282
199,658
114,322
96,250
6,158
Total
Current Rate Structure
400 service connections;
Annual assessment $279 collected by Imperial County through taxes ($23.25/month);
Annual assessment also includes bond portions.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Technical Approach, Objectives
and Funding Plan
Identified Potential Funding Sources
USDA-RUS
Colonias Grant and Water and Waste Disposal Program.
California Housing and Community Development (HCD)
Small commiunity Grants – Provides grants up to 97 ½ % with population < 5,000;
State Revolving Fund – Loans for construction maximum $50M and 20 year payback.
NADBank
CDBG Fund - Grants for communities with population <50,000 maximum $500K
CDBG Program Planning and Technical Assistance Grants – Providing funds to small
cities for planning and evaluation studies related to CDBG-eligible activity.
State Water Resources control board (SWRCB)
USDA-RD – In 1993, the NSD received Sewer Revenue Bonds in the amount of $545,000.
To date, the City owes approximately $503,000 on this loan.
BEIF to support construction, service connections, project management and rate transition.
A rate study and additional capacity building tasks may be funded through the IDP.
BECC
The community is eligible through the Project Development Assistance Program (PDAP).
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Public Participation Strategy
Potential Obstacles
Largest obstacle is cost associated with repaying loans;
Requirements to establish monthly user rates;
Operation of system currently performed on a part-time basis as available. Sharing a fulltime operator with City of Calipatria or other may not be feasible.
Local Politics
Niland Township is not incorporated and does not have a local government;
Regulated by Imperial County Board of Supervisors;
The NSD was created in 1970’s, by Imperial County to operate the wastewater
facilities, and is managed by a five member Board of Directors. Typically less
than 10% of residents participate in the election.
Socio-Economic Indicators
Approximately 26.1% of the population, over the age of 25, has completed a high
school education;
2002 Census denotes 6.2% unemployment rate.
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Project Schedule
Niland Sanitary District
Rapid Assessment Process Project Strategic Plan
Action Items
BECC
Modify PSP with Final Comments – 11/21.
Develop Scope of Work (SOW),
Send Sample TA Agreement to NSD and assist with resolution.
Project Sponsor - NSD
Provide any additional comments – 11/12.
Consider Resolution – Accept PSP, request recommended TA Tasks, and
designate lead contact – 11/27.
Participate in development of SOW – approve SOW by letter.
Invite participants for Steering Committee.
Stakeholder Agencies
Provide any additional comments – 11/12.
Participate in SOW development – approve SOW.