Getting started Use this page to locate the text formats

Download Report

Transcript Getting started Use this page to locate the text formats

IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
IEA HIA Task 24
“ Wind Energy and Hydrogen Integration”
TASK REPORT
Dr. Luis Correas
Mr. Ismael Aso
57th EXECUTIVE COMMITTEE Meeting , Montecatini (Italy)
1
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
OBJECTIVES TASK 24:
To explore in detail all possible issues (Technical, Economical, Social,
Environmental, Market and Legal) related to hydrogen production using
electrolysis with wind energy.
To explore in detail possible applications for hydrogen produced by
electrolysis using wind energy, with special emphasis on full wind & hydrogen
integration by means of hydrogen storage and electrical conversion that
balances the original wind energy production, allowing an approach to demand
that closes the gap with conventional energies.
2
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
PRIOR STEPS
53rd IEA HIA ExCo meeting (Singapore, November 2005): The interest on starting a new
task on “wind energy & hydrogen integration” is endorsed by the ExCo. The Spanish
representative takes the lead.
54th IEA HIA ExCo meeting (Lyon, June 2006): Dr. Luis Correas (Fundación Hidrógeno
Aragón) and Mr. Fernando Tamayo (Gamesa Energía), presented a first draft of the new
task.
Project Definition Meeting (Brussels, 4th October 2006): attendance of 15 people from 7
countries. A revised draft has been released, with a matured work plan proposal. Pending
confirmation of participation, especially from electrolyser manufacturers.
55th IEA HIA ExCo meeting (Petten, November 2006): the Task is finally approved by the
ExCo, and a kickoff meeting was made for spring 2007, in order to confirm participation.
56 th IEA HIA EXCo Meeting (Rapperswill, May 2007): First SAR showed and first
Meeting , Canary Island October 2007
3
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
Creation of a new Web Page for Task 24 (July 2007)
http://task24.hidrogenoaragon.org
4
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
Private web page accesses
5
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
Diffusion Control for Task 24
6
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
“ Home work” sent July
7
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
“ Home work” filled: Example Jórg Linnemann (Planet Gbr, Germany)
8
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
Meeting with WIA (September 2007)
9
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (23-25 October 2007)
Name
Enterprise
Country
1
Rupert Gammon
Director, Bryte Energy Ltd
Uk
2
Ken-ichiro Ota
Yokohama National University
Japan
3
Sam Miyashita
ENAA
Japan
4
Pablo Fontela
Endesa
Spain
5
Joerg Linnemann
Planet GbR
Germany
6
Claus Jorgensen
RISO
Denmark
7
Ernest Burkhalter
IHT
Switzerland
8
Eli Varkaraki
CRES
Greece
9
Javier Pino
Seville University
Spain
10
Salvador Suarez
ITC
Spain
11
Hoskin, Aaron
Natural Resources of Canada
Canada
12
Felipe Rosa
INTA
Spain
13
Luis Correas Uson
Aragon Hydrogen Foundation
Spain
14
Ismael Aso
Aragon Hydrogen Foundation
Spain
15
Kevin Harrison
NREL
EEUU
16
Pilar Argumos
INTA
Spain
List Participants 1 Meeting ( 9 Countries, 16 Attendees)
10
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (23-25 October 2007)
RES2H2 Wind-Desalination Plant in Pozo Izquierdo.
Site of Fall 2007 Expert meeting.
Visit to RES2H2 Project
11
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (26 October 2007), 8 speakers belonged to Task 24
12
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (23-25 October 2007)
13
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (23-25 October 2007)
Collaborations between Task 24 and Task 18 : Subtask B Leader Task 18
Free : www.hidrogenoaragon.org
14
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
WORK PLAN Task 24
Subtasks
A
S1 07
S2 07
PRELIMIN
ARY
REVIEW
REPORT
ON STATE
OF THE
ART
D
S2 08
S1 09
METHOD
OLOGY &
TOOLS
CASE
STUDIES
DEFINITIO
N
S2 09
S1 10
S2 10
UPDATE
PRELIMINI
ARY
REDESIG
N
B
C
S1 08
FINAL
REDESIG
N
REPORT
FINAL
UPDATE
WIND
ENERGY
CONSTRA
INTS
ANALYSIS
FULL
INTEGRAT
ION WIND
TO H2
DOCUME
NT
15
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ACTIVITIES DURING THE LAST 6 MONTHS
First Meeting Canary Island (23-25 October 2007)
Decisions taken during the 1 st Meeting
16
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
REVIEW ABBREVIATED WORK PLAN AND MILESTONE FOR THE
LAST SEMESTER
-
Confirm participation of attendees in the Task. Submission of National Participation Letters
(Alredy 6 NPL) and volunteers for Subtask leadership (DONE)
-
Contact Task 18 at OA level to detect cooperation opportunities and avoid duplication of efforts.
(DONE, Subtask B Leaders)
-
Contact WIA Annex 25 at OA level to detect synergies. Contact WIA to present Task 24 (if agreed
by HIA ExCo) (DONE)
-
To elaborate a preliminary report on the state of the art, regarding existing and on-going hydrogenwind projects, literature of reference, technology state of the art for wind turbines and
electrolysers.(Semi DONE, “Collected Home Work” , work with Subtask A Leader)
-
Develop the methodology and tools requires to develop Subtask C. A report will be issued
regarding the status of regulations on electricity and fuels in a country basis, prognosis on wind
electricity penetration, existing studies and working groups, potential markets for hydrogen (niche willingness to pay – and mass markets - competition in commodity markets -), methodology for
calculations (definition of terms and tools and software). .(Semi DONE, “Collected Home Work” ,
work with Subtask C Leader)
-
Next meeting will be hold coinciding with Task 18 semester meeting, in mid October (date to be
confirmed), hosting ITC (Instituto Tecnológico de Canarias - Canary Islands). (DONE)
17
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
ABBREVIATED WORK PLAN AND MILESTONE FOR THE NEXT
SEMESTER
18
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
THE EXCO COULD ANALYZE THE POSSIBLE PARTICIPATION AS
“ASSOCIATE MEMBERS”
“ This propose participation, will not attend the Meetings, but
contribute to the Task , in order to better accomplish the
activities agreed by all members, The associate member would
have limit access to the private information”
Cases :
Geoff Dutton : H2NET Director, United Kingdom
Hernán De Battista (LEICI), Argentina (NOT IEA HIA Member)
Suzanne SHAW European Union DG JRC
.
19
IEA HIA Task 24: WIND ENERGY AND HYDROGEN INTEGRATION
57th Ex-Co Meeting Montecatini, Italy November 2007
THANK YOU FOR YOUR ATTENTION !!!!
Dr. Luis Correas
Mr. Ismael Aso
57th EXECUTIVE COMMITTEE Meeting , Repperswil
20