Transcript WMC – Expansion Project Updates
Winchester Medical Center Campus Expansion June 21, 2011
June 21, 2011
CONTENTS
1. PROJECT UPDATE 2. EXTERIOR CONSTRUCTION 3. INTERIOR CONSTRUCTION 4. LOOK AHEAD SCHEDULE (3 Months)
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
PROJECT UPDATE
1. Heart and Vascular – Phase II, III and IV interior renovation underway 2. Laboratory
–
complete 3. North Tower – canopy steel forthcoming, exterior close-in nearing completion, interior gwb ongoing 4. Loading Dock – forthcoming all bays open, new walls almost complete, new ceiling install
June 21, 2011 AERIAL FROM NORTH
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 AERIAL FROM WEST
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 AERIAL FROM SOUTHEAST
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 AERIAL FROM NORTHWEST
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 TOWER ELEVATION
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 MAIN ED ENTRY PROGRESS
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 OBS UNIT OVER ED
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 PEDESTRIAN BRIDGE TO EAST
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 LDR CABINETRY MOCK-UP
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 ICU CORRIDOR AT NURSES STATION
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 ICU NURSES STATION
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
June 21, 2011 ICU ROOM PROGRESS
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
LOOK AHEAD SCHEDULE
June 2011
continue exterior window installation continue elevator installation continue above ceiling work in ED complete above ceiling and utility work at Loading Dock continue interior renovation of Heart and Vascular wk of 6/6/11 begin interior wall close-in wk of 6/6/11 begin erection of canopy steel wk of 6/6/11 turn on new AC units wk of 6/13/11 begin exterior skin of ED and Boiler Plant wk of 6/20/11 begin sitework at ED wk of 6/20/11 begin curtainwall installation at stairs June 21, 2011
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
LOOK AHEAD SCHEDULE
July 2011
complete exterior window installation continue elevator installation continue above ceiling work in ED continue interior renovation of Heart and Vascular complete exterior of ED and Boiler Plant complete curtainwall installation at stairs continue canopy installation wk of 7/11/11 begin interior finish install June 21, 2011
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion
LOOK AHEAD SCHEDULE
August 2011
continue elevator installation continue above ceiling work in ED continue interior renovation of Heart and Vascular continue interior finish install continue canopy installation wk of 8/22/11 start final inspections @ ED wk of 8/15/11 begin medical equipment installation @ ED June 21, 2011
VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion