Winchester Medical Center Campus Expansion June 21, 2011

June 21, 2011

CONTENTS

1. PROJECT UPDATE 2. EXTERIOR CONSTRUCTION 3. INTERIOR CONSTRUCTION 4. LOOK AHEAD SCHEDULE (3 Months)

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

PROJECT UPDATE

1. Heart and Vascular – Phase II, III and IV interior renovation underway 2. Laboratory

complete 3. North Tower – canopy steel forthcoming, exterior close-in nearing completion, interior gwb ongoing 4. Loading Dock – forthcoming all bays open, new walls almost complete, new ceiling install

June 21, 2011 AERIAL FROM NORTH

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 AERIAL FROM WEST

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 AERIAL FROM SOUTHEAST

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 AERIAL FROM NORTHWEST

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 TOWER ELEVATION

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 MAIN ED ENTRY PROGRESS

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 OBS UNIT OVER ED

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 PEDESTRIAN BRIDGE TO EAST

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 LDR CABINETRY MOCK-UP

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 ICU CORRIDOR AT NURSES STATION

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 ICU NURSES STATION

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

June 21, 2011 ICU ROOM PROGRESS

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

LOOK AHEAD SCHEDULE

June 2011

continue exterior window installation continue elevator installation continue above ceiling work in ED complete above ceiling and utility work at Loading Dock continue interior renovation of Heart and Vascular wk of 6/6/11 begin interior wall close-in wk of 6/6/11 begin erection of canopy steel wk of 6/6/11 turn on new AC units wk of 6/13/11 begin exterior skin of ED and Boiler Plant wk of 6/20/11 begin sitework at ED wk of 6/20/11 begin curtainwall installation at stairs June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

LOOK AHEAD SCHEDULE

July 2011

complete exterior window installation continue elevator installation continue above ceiling work in ED continue interior renovation of Heart and Vascular complete exterior of ED and Boiler Plant complete curtainwall installation at stairs continue canopy installation wk of 7/11/11 begin interior finish install June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion

LOOK AHEAD SCHEDULE

August 2011

continue elevator installation continue above ceiling work in ED continue interior renovation of Heart and Vascular continue interior finish install continue canopy installation wk of 8/22/11 start final inspections @ ED wk of 8/15/11 begin medical equipment installation @ ED June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER WMC Campus Expansion