Transcript Document

Opal
“Rockies Express
Pipeline”
Wamsutter
Clarington
Tuscola
Cheyenne
Meeker
Lebanon
1
Market Assessment
•
Production of Rockies gas is expected to increase
•
There is insufficient pipeline capacity to export this increasing supply
•
Potential expansion projects for existing pipelines would deliver gas to
low-price markets in the Southwest or Mid-Continent
•
Increased LNG deliveries to the West Coast and Gulf Coast will compete
with the Rockies
•
The highest premium-priced market for gas is the Northeast
•
Large basis differentials exist between the Rockies and the East Coast
•
Producers seek the highest netback and greatest optionality on where to
deliver gas
2
Reserve Base Supports New Infrastructure
Huntsman
• 20 year supply requirement for existing
pipes = 36 Tcf
• 20 year supply requirement for existing
pipes + Rockies Express = 50 Tcf
• 20 year supply requirement for existing
pipes + Rockies Express + 50% excess
= 75 Tcf
3
To support Rockies production, additional
pipeline capacity must be built
Total Exports 4.9 Bcfd
Rocky Mountain Production Forecast*:
2004 – 5.8 Bcfd
2007 – 7.0 Bcfd
2009 – 7.6 Bcfd
2012 – 8.3 Bcfd
*Source: CERA Wet Gas Capacity Outlook.
To maximize basis there should be ~10% excess capacity
4
Basis Spreads Support New Pipeline
•Basis differential versus Henry Hub
•Source: Historical Prices – GasDat, Forward Prices – Sempra Commodities Oct 05 Curve
5
Project Overview
• Construction of 42 inch or larger, 1350 mile pipeline from
Cheyenne Hub to Clarington, Ohio with 2 Bcfd transport capacity
• Purchase Entrega Pipeline - 330 miles of 36 and 42 inch from
Meeker to Wamsutter to Cheyenne.
• 180 miles of 36 inch pipeline from Opal to Wamsutter
• Over 20 interconnections with interstate pipelines and multiple
supply points
• Staged FERC Certificates will enable access to mid-continent
delivery points in Dec. 2007; access to Tuscola or Lebanon
delivery points in Dec. 2008 and access to eastern Ohio, delivery
points in July 2009
• Final design based on Open Season binding bids
• Expected rates of about $1 plus fuel of about 2% to 3%
6
Development Status
• Route follows over 90% of existing pipeline or utility ROW
corridors
• Detailed engineering, environmental, and ROW studies due Nov.
15th
• Proposing 3 certificate FERC filing process and construction
schedule to maintain 4Q07 in-service date to mid-continent
– Certificate I route follows Kinder´s Trailblazer and Terasen’s Platte
Valley pipelines
– Existing Trailblazer and Platte ROW and project records help
accelerate permitting
• Discussions with FERC yielded positive feedback on staged
development
• Project is in to hold Open Season later in Q405
7
Rockies Express Pipeline Proposed Route
8
Significant Developments
• Kinder & Sempra Joint Development
– Kinder 2/3 equity and Sempra 1/3 equity
– Sempra Affiliate committing to 200,000 Dth/d
• EnCana & Entrega Support
– 500,000 Dth/d of firm long haul commitment
– Incorporation of Entrega into the project
• Wyoming Natural Gas Pipeline Authority
Negotiations
• Exclusivity Agreements with End-Use Markets
9
WNGPA
• Provides for 90 period of exclusive negotiations
• Subjects of negotiations include:
– WNGPA providing competitive financing for Rockies
Express
– WNGPA facilitating extension of Project to Opal Hub
– A conditional capacity commitment of up to 200 mmcfd
under the proposed Aggregation Services
– Potential interim financing through 2008 or beyond for
the Project’s acquisition and/or construction of assets
upstream of Cheyenne
• Any transportation commitment will be subject to
Board approval by January 31, 2006
10
Aggregation Services
• Would allow for the WNGPA to serve as
Aggregator:
– Gas-in-kind
– Small producers
• WNGPA would not need to hold title to gas
• “Pool Members” could change over time
• Relationship of Aggregator and Pool Members is
a private contractual relationship (not subject to
FERC review or jurisdiction)
• Provide credit assurances for Pool Members
11
Next Steps
• Negotiate and execute shipper precedent
agreements
• Start NEPA Pre-filing in late October, 2005
• Conduct binding open season in Nov. – Dec, 2005
- Long haul bids coordinated with completion of
construction phases are conforming
• Shipper Board approval required by Jan. 31, 2006
• A minimum of 1,500,000 Dth/d is needed
• Determine economic viability by February, 2006
12
Contact Information
• Kinder Morgan
Jeff Rawls
Vice President Business Development
West Region Gas Pipelines
303-914-4903
[email protected]
• Sempra Pipelines & Storage
Ryan O’Neal
Vice President
619-696-4585
[email protected]
13