Transcript Bogue Banks Carteret County, North Carolina Coastal Storm
West Onslow Beach/ Topsail Beach
Coastal Storm Damage Reduction Project
Town of Topsail Beach Board of Commissioners Brief July 9, 2014
Presented by U.S. Army Corps of Engineers Wilmington District US Army Corps of Engineers BUILDING STRONG ®
OVERVIEW
Project Update: Current Status Process to get to a Federal Project: Steps Project History: How did we get where we are?
Project Description and Cost: What will the Federal Project achieve?
Fiscal Overview: How much have we spent and on what?
Project Authorization – FINALLY!
The Path to Construction
BUILDING STRONG ®
2
PROJECT UPDATE
General Reevaluation Report defining the project was approved in final form in 2009 Preconstruction, Engineering and Design Phase of Work: preliminary design documentation completed Project is ready for preparation of construction documents once real estate acquisition has been completed Project authorization received in 2014
BUILDING STRONG ®
3
PROCESS TO GET TO A FEDERAL PROJECT
Request from a local entity and, in most cases, Congressional study authority Cost-shared study completion to identify Federal interest in a potential project Cost-shared preconstruction, engineering and design for preparation of project plans and specifications Project authorization (can occur at any time after study completion) Construction appropriation/Project Partnership Agreement Execution Real Estate Acquisition Construction Contract Award
BUILDING STRONG ®
4
WOB/TOPSAIL BEACH PROJECT HISTORY
4 Congressional study resolutions were used to undertake the original Feasibility Study that recommended a project at Topsail Beach. Feasibility Report was completed in 1990.
Project was authorized in Water Resources Development Act of 1992 Design activities were completed in 1992; Town decided not to sign the Project Cooperation Agreement Request was received to re-look at a Federal project in late 1990s, and General Reevaluation Report (GRR) was completed between 2001-2009 Design activities for modified project were initiated in 2010 and preliminary design was completed in 2014 Locally Preferred project was authorized in WRRDA 2014
BUILDING STRONG ®
5
UPDATED AUTHORIZED PROJECT
6
BUILDING STRONG ®
UPDATED AUTHORIZED PROJECT
Project life: 50 years Initial construction cost: $39.4M
($25.6M Fed/$13.8M Non-Fed) Renourishment cost/life: $265.5M
($132.8M Fed/$132.8M non-Fed) 7 23,200 feet long Dune and Berm
BUILDING STRONG ®
FINANCIAL SUMMARY
PROJECT PHASE FEDERAL NON-FEDERAL TOTAL COST
Feasibility Report (1990) $963,000 $963,000 Project Design $346,200 $115,400 $461,600 GRR (2001-2009) 75/25 cost share $2,025,750 $675,250 $2,701,000 50/50 cost share $ 499,000 $499,000 $ 998,000 $2,524,750 $1,174,250 $3,699,000 Project Design $685,500 $228,500 $914,000 TOTALS: $4,519,450 $1,518,150 $6,037,600 Available funds remaining: $25k (coordination, budget process, PPA dev) Additional funds required for Econ Update: $60k ($45 Fed/$15 non-Fed)
BUILDING STRONG ®
8
PROJECT AUTHORIZATION
AT LAST: Water Resources Reform and Development Act of 2014
BUILDING STRONG ®
9
THE PATH TO CONSTRUCTION
Complete economic/project cost update Request and receive construction funds Develop and execute a Project Partnership Agreement Obtain Real Estate Finalize construction bid documents Award construction contract and initiate construction
BUILDING STRONG ®
10
QUESTIONS?
BOTTOM LINE
: 13 years to study, design and authorize a project Over $4.5M Fed and $1.5 Non-Fed funds invested to date Over $150M Fed funding share once construction has initiated Project authorization allows us finally to request funds for construction Federal Project life: 50 years
Initial construction cost
:
Renourishment cost/life : TOTAL: Federal Non-Fed Total
$25.6M $13.8M
$39.4M
$132.8M $132.8M $265.6M
$158.4M $146.6M $305M