Marathon Site
Download
Report
Transcript Marathon Site
Marathon Site
Marathon Battery
Cold Spring, NY
CERCLA Cleanup
Site Description
Federal Court Actions ‘70s
Project History
1st Dredging Operation
Contaminants of Concern
CERCLA Actions
Total Cd Load to Marsh
7/20/2015
W. Fish, Portland State University
Site Description
On the Hudson River in NY; Two
components:
East Foundry Cove Marsh (EFCM)
Constitution Marsh
7/20/2015
Click for Synoptic Site Map
Click for Aerial Photo
W. Fish, Portland State University
History: US Army
1952: U.S. Army Corps of Engineers
Constructed
1953, under Contract with the Army Signal
Corps, Sonotone Corporation operated plant to
produce nickel-cadmium batteries for use in the
Nike missile program
Run under Army ownership 1953-1962; declared
“excess property” in 1962.
7/20/2015
W. Fish, Portland State University
Private Owners
1962: U.S. sold it to Sonotone
Corporation.
1967: Sonotone Corporation became a
wholly-owned subsidiary of Clevite
Corporation
7/20/2015
W. Fish, Portland State University
Marathon
1969, Clevite Corporation Merged with
Gould, Inc.
1969, Gould, Inc. sold the Plant to
Business Fund, Inc.; later changed its
name to Marathon Battery Company
(MBC)
MBC operated the plant until March 1979.
7/20/2015
W. Fish, Portland State University
After the Battery Era
Plant inactive from 3/79 until 11/80
Battery manufacturing equipment
removed and shipped to an MBC plant in
Waco, Texas
Sold to the current owner, Merchandise
Dynamics, incorporated, for use as a book
storage facility
7/20/2015
W. Fish, Portland State University
Contaminants of Concern
Cadmium: Cd
Toxic to humans, animals and plants
Carcinogenic
Waste stream had large amounts of Cd,
mostly as Cd hydroxide; also caustic
wastes
7/20/2015
W. Fish, Portland State University
Original Wastewater
Treatment System
A lift station and piping for transfer of all
process wastewater into the Cold Spring
sewer: Discharged directly into the
Hudson River
Bypass Valve Was Installed
When the Lift Station Was Shut down or
Overloaded, direct Gravity Discharge
Could Be Made into a Storm Sewer
7/20/2015
W. Fish, Portland State University
Discharges to EFCM
High dissolved solids and pH of the
Effluent Resulted in Extreme Fouling
Within the Pump and Piping
Pumps Required Shut down and
Maintenance
Bypass Valve Was Opened and the Flow
Diverted to EFCM: 2x per week
7/20/2015
W. Fish, Portland State University
Cadmium Load:
Approximately 50,000 kg of
Cadmium May Have Been
Discharged to the Cove During
the Life of the Plant
7/20/2015
New Sewage Plant
1965: New York State Department of
Health said Cold Spring must build seage
treatment plant
Battery Plant effluent could not be
handled, too toxic
Sonotone ordered to disconnect from
sewer
Entire waste flow diverted to storm sewer
7/20/2015
Attempts at Treatment
Sonotone installed treatment equipment
precipitate Cd(OH)2 and neutralize
discharge
Never really worked, Cd kept on flowing
NY found lots of Cd in marsh, river
Plant given Jan 1, 1970 deadline to
comply with state discharge regulation
7/20/2015
70 Civ. 4110
Judgement of Federal Court
Suit brought under Federal Water
Pollution Control Administration against
Marathon
Enforcement then shifted to new EPA
7/20/2015
Relief Sought by US
Permanent injunction against further
discharge of Cd and other metals into
Foundry Cove
Demanded removal of Cd in sediments
Sept. 1971: Complaint amended, named
Sonotone, Clevite and Gould as additional
defendants
7/20/2015
Final Judgment
June 1972: Remove all sediment with Cd
>900 ppm (mg/kg)
1971: Discharge was stopped; routed
back to sewer after treatment
1972-1973: Hydraulic dredging by GOULD
7/20/2015
1st Dredging Operation
Hydraulic dredging of “hot” areas
Spoils dewatered in parking lot inside a
temporary dike
dewatering leaked all over the place
Effluent settle overnight, discharge to
marsh
Solids mixed with limestone, scored in
underground vault on site
7/20/2015
Areas Dredged
Outfall area
Channel leading to the marsh
About 9 hectares = 22 acres
About 4000 cu.m. stored in vault
7/20/2015
“Satisfaction”
April 24, 1974: US Attorney issues
“satisfaction of judgment”
Site is off the hook…or isi it?
Agreement included monitoring by NYS
Dept. of Environmental Conservation
(NYSDEC)
Studies by NYSDEC, EPA, NYU
7/20/2015
Whoops, There it Is
Studies showed much of area was still >
900 mg/kg
Channel area was recontaminated
Only about 10% of Cd had been removed
7/20/2015
CERCLA
1980: CERCLA Passed
1981: First NPL Prepared
Guess what was one of the first sites
proposed for the interim NPL?
1983 went on Final NPL
Also OSHA found high Cd dust inside book
warehouse
7/20/2015
CERCLA Units
1986 ROD: Three “operating Units”
Area I: EFCM & Constitution Marsh
Area II: Plant, grounds, vault
Area III: Cove itself and Hudson
7/20/2015
RI/FS Findings
~8% of EFCM had >1000 mg/kg Cd
Dust up to 120,000 mg/kg in plant
7/20/2015
ROD Plan: 1986
Dredge EFCM, dewater, haul offsite
Leave Constitution Marsh alone
Monitored Natural Attenuation (MNA)
2 other RODS issued ‘88, ‘89
7/20/2015
Final Consent Decrees
Marathon, Gould, USACOE are RPs
Total cost $109 million
Gould $57M
ACOE $43 M
Marathon $9M
7/20/2015
Dredging Began 1993
Dredging removed 55,000 cu. Yd
sediment to depth of 1 ft.
Assumed to get about 95% of Cd this way
Did not shoot for a specific target conc.
Dredging completed in 1994
7/20/2015
Marsh Cleanup
1800’ dike, 6-7 ft high
31,000 cu.yd soil excavated, treated,
shipped of site
reconstructed the marsh
7/20/2015
DELISTING
Declared finished and delisted from NPL,
October 1996
7/20/2015