Transcript Document
Presentation to Select Committee on Economic Development NERSA CEO: Smunda Mokoena 24 August 2010 1 AGENDA Mandate of the Energy Regulator Current structure of the ESI Objects of the Electricity Regulation Act Extract from the RE white paper of 2003 REFITs I and II Facilitators Conclusion 2 MANDATE 1. 2. 3. NERSA was established in terms of the National Energy Regulator Act, 2004 (Act No. 40 of 2004) Mandated by the Electricity Regulation Act, 2006(Act No. 4 of 2006) (“the Act”) to regulate the Electricity Supply industry in South Africa. s4 (a) (iv) of the Act states “The Regulator must issue rules designed to implement the national government’s electricity policy framework, the integrated resource plan and this Act.” 3 Current structure of the ESI IPPs Eskom Generation Imports / Exports Eskom Transmission Municipal Generators Eskom Distribution D1 Large Power Users Customers a D2 D3 Customers b Dn Local Authority Distributors Customers n 4 Objects of the Act These are listed in s2 of the Act and the relevant ones for this presentation are to: (c) facilitate investment in the Electricity Supply Industry (e) promote the use of diverse energy sources and energy efficiency 5 Renewable Energy Policy The RENEWABLE ENERGY WHITE PAPER of 2003 states: In order to meet the long-term goal of a sustainable renewable energy industry, Government has set the following 10-year target for renewable energy: 10 000 GWh (0.8 Mtoe) renewable energy contribution to final energy consumption by 2013, to be produced mainly from biomass, wind, solar and small-scale hydro. The renewable energy is to be utilised for power generation and non-electric technologies such as solar water heating and bio-fuels. This is approximately 4% (1667 MW) of the estimated electricity demand (41539 MW) by 2013. 6 Renewable Feed-In Tariffs (REFITs) 1. Based on the above requirements NERSA introduced a REFIT framework in two phases. 2. A REFIT is a pre-approved tariff for a specific Renewable Energy generation technology eg., wind 3. By nature REFITs include a premium above tariffs for conventional generation mainly to attract investors and developers 7 REFIT FINANCIAL ASSUMPTIONS Financial parameter Unit IPP REFIT Debt % 70 Equity % 30 Nominal cost of debt % 14.9 Inflation % 8 Real cost of debt after tax % 6.39 Tax rate % 29 Real return on Equity ROE after tax % 17 Weighted Average Cost of Capital (WACC) % 12 8 REFIT PHASE I Renewable Energy Feed – in Tariffs approved March 2009 This is largely aligned with the technologies mentioned in the REWP of 2003. 9 REFIT PHASE II Renewable Energy Feed – in Tariffs approved October 2009 10 Important features of the REFIT The REFITs will be escalated by CPI annually. A full tariff review will take place every year for the first five year period of implementation and every three years thereafter. The term of the Power Purchase Agreement (PPA) is twenty (20) years. The carbon revenue from the Clean Development Mechanism (CDM) was not included in the REFIT. Independent Power Producers (IPPs) may apply for CDM revenues separately. 11 Way Forward 1. The NewGen regulations of 5 August 2009 require that NERSA issues rules on selection criteria for the REFIT programme. 2. NERSA is currently finalising the rules and the standard REFIT PPA after a lengthy public consultation process 3. Once the rules are finalised they will be forwarded to the System Operator or the Buyer. 4. The Buyer will then kick start the process by issuing a Request for Qualification (RfQ) and a Request for Proposals (RfP). 12 FACILITATORS 13 Rules for Power Purchase Cost Recovery 1. Regulation 10 of the NewGen regulations requires that NERSA passes rules for the purpose of cost recovery by the system operator and the buyer. 2. In response to this NERSA gazetted rules on Power Purchase Cost Recovery (CRM) after a public consultation process. 3. The CRM basically addresses: 1. 2. 3. 4. Check of whether the proposed IPP will be affordable The allocation of risk between the buyer and the IPP Process to be followed by the buyer in seeking approval of pass through costs A list of recoverable/pass through costs 14 Kusile DoE OCGT IPP Ingula MTPPP REFIT Wind REFIT Other Sere Other capacity and Decommissioning Net new capacity Total capacity Demand Forecast original MYPD DSM Net peak demand (after DSM), MW Annual energy net sent out DSM YEAR 2009 2010 2011 2012 2013 Medupi gazetted on 29 January 2010 MW 772 683 404 0 0 MW 0 0 0 0 723 MW 0 0 1020 0 0 MW 0 0 0 0 666 MW 0 168 168 84 0 MW 0 0 200 200 0 MW 0 175 150 0 300 MW 0 100 0 0 0 MW 0 30 55 0 0 MW 772 1419 2355 1146 2127 MW 44157 46393 47380 48082 50809 MW 37845 39432 40914 42373 44238 MW 432 923 1343 2118 3056 MW 37413 38509 39571 40255 41182 GWh 248517 258706 267771 276705 288066 GWh 426 1864 3453 6561 10642 Annual energy net sent out after DSM Integrated Resource Plan 1 (IRP 1) GWh 248091 256842 264318 270144 277424 15 Multi-Year Price Determination 2 (MYPD 2) SUMMARY OF ALLOWED REVENUE Eskom’s own primary energy cost 2010/11 2011/12 2012/13 R’m R’m R’m 36 464 40 486 45 351 2 304 4 299 5 819 32 611 34 727 36 847 Depreciation 9 356 12 812 17 880 Return on assets 3 039 15 936 33 163 Demand Side Management 1 406 1 688 2 351 85 180 109 948 141 411 IPP and Co-generation Operating Expenditure 16 In Conclusion 1. The Energy Regulator believes that: – all perceived regulatory risks have been mitigated. – once the rules on selection criteria for the REFIT Programme have been finalised the Buyer will be in a position to invite interested parties to bid before the end of 2010. 17 THANK YOU www.nersa.org.za 18