Transcript Slide 1

One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Southern WV 340 Environmental
Infrastructure Program
Sherry Adams
340 Program Manager
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Southern WV
Environmental
Infrastructure
Section 340
Webster
Krouts Creek
Cabell
Nicholas
Wayne
Lincoln
Boone
Boone County
Mingo
Pageton
Fayette
Greenbrier
Raleigh
Logan
Gilbert
Pocohontas
Wyoming
McDowell
Summers Monroe
Mercer
Kilsyth
Fayette County
Marsh Fork
Cool Ridge / Flattop and
Piney Creek
Mercer Co. and Oakvale Road
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District

Authorized by WRDA 92 (Sec. 340)
●
●
Amended by WRDA 96 (Sec. 359)
Amended by WRDA 99 (Sec. 368)
■
●
●


●
●

Increased authority to $40M
Amended by WRDA 2000 (Sec. 550)
75 / 25% cost share
Inventory of needs – $1.1B
Scope
●

Southern WV Environmental
Infrastructure – Section 340
Water and wastewater
Surface water resource protection and development
Environmental restoration
$20.2M Appropriated thru FY 05
$750K Appropriated in FY 06 (Corps)
●
$2M ARC
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District

Water quality improvement project
●
Part of a comprehensive watershed restoration plan for Dunloup
Creek
■
■
■

●


Phase I – Design of Kilsyth Collection System and upgrade of Mt.
Hope wastewater treatment plan (WWTP)
Phase II – Construct WWTP upgrade at Mt. Hope
Phase III – Construct Kilsyth collection system
Total Corps Project Cost – $2.5M
●

Kilsyth / Mt. Hope
Environmental Infrastructure
Design cost – $340K
Construction cost – $2.1M
Local Sponsor – City of Mt. Hope (25%)
Source of Non-Federal funds – SCBG, DEP Stream
Restoration Funds, SRF Loan
Current Status
●
Initiate Phase II – Mt. Hope WWTP construction
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Cool Ridge / Flat Top
Environmental Infrastructure
 Construction
of new WWTP, pump station,
force main and collection system
 Total Corps Project Cost – $3.6M
 Local Sponsor – Shady Spring PSD (25%)
 Source of Non-Federal funds – SRF Loan,
IJDC Loan, Flat Top Lake Grant
 Current Status
●
Initiated construction Dec 05
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Boone County PSD
Environmental Infrastructure
 New
WWTP and collection system to improve
local environment
 Total Corps Project Cost
●
●
Design Cost - $450K
Construction Cost - $2M
Sponsor – Boone County PSD (25%)
 Source of Non-Federal funds – SCBG, ARC
grant, IJDC loan, IJDC grant
 Current Status
 Local
●
Execute construction agreement and initiate
construction of WWTP
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
 Stormwater
Krouts Creek
Environmental Infrastructure
diversion
5’ x 9’ underground box culvert
● 1,250 feet long
●
Project Cost – $3.3M
 Local Sponsor – City of Huntington (25%)
 Source of Non-Federal funds – WVCA,
City of Huntington
 Current Status
 Total
●
Complete construction Mar 06
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
 Replacement
●
Piney Creek Interceptor
Environmental Infrastructure
of gravity sewer line
In close proximity to Whitestick Creek and runs
through the incorporated Town of Mabscott
Corps Project Cost – $1.3M
 Local Sponsor – Beckley Sanitary Board (25%)
 Source of Non-Federal funds – Beckley Sanitary
Board
 Current Status
 Total
●
●
Execute design / construction agreement Feb 06
Initiate construction Mar 06
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District

Water system extension/upgrade to Southern Hollow
Road
●
●




Oakvale Road PSD
Environmental Infrastructure
Serves 30 new customers
Additional phases allow potential of providing water service and
fire protection to another 1,100 customers
Total Project Cost – $830K
Local Sponsor – Oakvale Road PSD (25%)
Source of Non-Federal funds – State Digest, WVAWC,
Mercer Co. Commission, IJDC Grant
Current Status
●
●
Initiate construction Mar 06
Complete construction Aug 06
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Completed 340 Environmental
Infrastructure Projects
340 Projects
Total Project
Cost (000s)
Date PCA
Executed
Date
Complete
Gilbert Sewer (Design)
$209
Jun 95
Dec 97
Gilbert Sewer (Construction)
$3,107
Mar 98
Dec 99
Mercer Water (Design)
$209
Aug 95
Jun 98
Mercer Water (Construction)
$2,333
Sep 98
Mar 01
Krouts Creek (Design)
$344
Dec 98
Sep 00
Pageton (Design)
$156
Oct 99
Jun 01
Pageton (Construction)
$2,367
Sep 01
Sep 02
Fayette Co. Wastewater
(Design)
$2,367
Sep 99
Aug 01
One Team – Relevant, Ready, Responsive, Reliable
US Army
Corps of Engineers
Huntington District
Questions