CLICK TO ADD TITLE - National Association of Regulatory

Download Report

Transcript CLICK TO ADD TITLE - National Association of Regulatory

Overcoming Challenges To
Integrating Renewable Energy
Resources
Paul Roberti, Commissioner
Rhode Island Public Utilities Commission
May 16, 2013
Renewable Integration Challenges in New
England Are Regional In Nature
• Independent System Operator
of New England (ISO-NE)
• Responsible for:
– Ensuring regional reliability
– Administering electricity
markets
• Regulated by Federal Energy
Regulatory Commission
2
New England’s Electric Power Grid at a Glance
•
6.5 million households and businesses;
population 14 million
•
350+ generators
•
8,000+ miles of high-voltage
transmission lines (115 kV and above)
•
32,000 megawatts of total supply and
2,000+ megawatts of demand resources
•
28,130 megawatts all-time peak demand,
set on August 2, 2006
•
500 participants in the marketplace
•
$5 billion total energy market value in
2012
3
Fuel Mix for New England – 2012
4
Generator Proposals in the ISO Queue
Approximately 5,000 MW looking to connect to the New England
system – Greater than 50 Percent are Renewable Energy Resources
5
Challenges Posed by Greater Levels of Variable Resources
• The region’s aging generation fleet and uncertain performance of
demand response resources has increased the need for system
operations flexibility – both system wide and locationally
• As traditional units retire or are too expensive to run, and variable
resources increase on the system, the system operator will need
more resources that have quick-start capability, fast ramp rates,
and are dispatchable across seasons
• Wide spectrum of solutions available, some already underway,
each with unique costs and complexities. For example:
–
–
–
–
Increase system reserves
Enhance performance incentives and penalties in wholesale markets
Negative pricing for energy market offers
6
Integrate wind forecasting into commitment and dispatch
7
Today, MA accounts for
46% of the region’s total
electricity consumption; CT
25%; RI 6%
With passive demand
response forecasts (11.6%
energy reduction in 2021),
LSEs would need
renewables to provide
20.2% of projected electric
energy use to meet existing
targets.
By 2021, 31.8% of region’s
projected electric energy
consumption could be met
by EE, RPS targets, and
related renewable goals.
% of LSE Electric Energy Supplied by Renewables
New England Renewable Energy Targets, 2021
20
20
16
15
14
12
10
10
5
0
ME
NH
RI
State
Source: ISO-NE RSP 2012, p. 135, 138-139.
MA
CT
New England Generator Interconnection Proposals
Approximately 6,000 MW proposed; over a third are wind projects
8
Challenges for Wind Development
• Population and electricity
demand concentrated in
southern New England
• No overlap between wind
resources and high
energy demand areas
• Transmission investment
would be required for
large-scale wind
integration
9
New England Wind Integration Study (NEWIS)
New England-focused wind integration analysis
• Large-scale wind integration in
New England is technically
feasible
• Regional requirements:
– Maintaining flexible resources to
manage variability
– Transmission upgrades
– Increasing regulation service and
operating reserves
– Developing wind forecasting tools
10
Challenges of Wind Integration
• The ISO is unable to dispatch wind resources today.
– Unit dispatch software is unable to send dispatch instructions.
– Non-dispatchable resources (which includes wind) are ineligible to
set price.
– Market/operations protocol used to determine curtailment priority
generally results in wind being curtailed before other resources.
– Inability to submit negative energy offers gives competing
resources little incentive to reduce output when congestion occurs.
– System operators must rely on manual actions to ensure reliability.
• Improved short, medium, and long-term forecasting tools
are needed.
• Full integration of wind resources into automated market
and dispatch systems is needed.
11
Addressing the Challenges of Wind Integration
• The ISO is developing market and infrastructure
improvements:
– Allow negative energy offers
– Make wind resources dispatchable and eligible to set price
– Calculate and send out a do-not-exceed (DNE) limit to each wind
plant on dispatch
• The DNE limits will reflect several characteristics of each
plant:
–
–
–
–
–
Economic offer curve
Maximum output under ideal weather conditions
Short-term wind output forecast
Transmission constraints
Telemetered physical status for the next dispatch interval
• A wind plant will be free to operate anywhere between 0 MW
and the DNE limit
12
Addressing the Challenges of Wind Integration cont.
• A centralized, regional wind power forecasting system is scheduled
to be in service in early 2013.
• All wind resources will be required to provide real-time telemetry
indicating current output and weather conditions.
– Improves system operator’s situational awareness
– Enable ISO’s real-time automated communication of dispatch
instructions
– Enhances the quality of the centralized forecast
• More flexible structure for hourly day-ahead energy offers and
intraday reoffers is being developed.
– Reduces the desire to self-schedule, giving system operators
more flexibility to integrate renewable energy resources
– Increases the percentage of resources dispatched economically
– Better for efficient system operation as a whole
13
Addressing the Challenges of Wind Integration cont.
• Potential increase in regulation requirements as more
wind resources interconnect to the grid
– Current hourly requirement averages ~60 MW
– Could increase to ~300 MW if wind penetration increases to 20%
of annual energy
– New England currently has 800+ MW of regulation capable
resources
• Forward Capacity Market issues under consideration
– Pay-for-performance incentives
– Identification of operational needs of resources to be acquired in
the capacity auction
14
Current Situation
• Wind resources and other Intermittent resources are “nondispatchable”
– Unit Dispatch Software (UDS) is unable to manage congestion by
sending dispatch instructions
– Wind resources not eligible to set price in LMP calculator
– System operators must manually curtail resources if necessary to
ensure reliable operation of the grid
• Anticipated wind production generally not reflected in unit
commitment for real-time
• Manually curtailing non-dispatchable resources when required
to manage congestion does not result in price separation
– Non-dispatchable resources are effectively zero-priced
– Resulting LMPs are inconsistent with “dispatch” decisions to curtail
zero-price resources
15
Existing RT Curtailment Procedure
• When economic dispatch is insufficient to manage
congestion, priority goes to resources that cleared or
self-scheduled in Day-Ahead.
• As a practical matter, this leads to economically
inefficient outcomes
– Renewable energy credits and production tax credits result
in wind plants having a negative energy price
– Interconnections on weaker portions of the grid, and fast
ramp rates mean wind plants are typically curtailed more
frequently than other resource types
16
Existing Manual Procedure Will Not Be Adequate
Going Forward
• Lack of real-time telemetry and uncertainty about anticipated
wind output lead to:
– More conservative operating practices and limits
– Less optimal resource commitment
• Suboptimal dispatch and inappropriate pricing
– Low cost resources may be curtailed before higher cost
resources
– Manual curtailments to manage congestion don’t result in
price separation
• With higher wind penetration, system operators with only
manual dispatch & curtailment procedures will be overloaded
during dynamic weather conditions
17
Near Term Improvements
• Wind short-term forecast – early 2013
– An accurate forecast is critically dependent on wind
resources providing detailed plant data ASAP
• OP-14 & OP-18 – real-time telemetry from wind
plants
• Both of these:
–
–
–
–
Greatly improve operator situational awareness
Reduce uncertainty
Improve commitment and dispatch of all resources
Make possible a real-time “Do Not Exceed” (DNE) dispatch
of wind resources
18
Wind RT DNE Dispatch - Objectives
• Secure, reliable, and efficient operation of the system
through normal economic dispatch of the system.
• Reduced need for manual curtailments of nondispatchable resources.
– Improved opportunities for wind production
• Allow wind resources to impact energy prices in a
manner consistent with their economic value and
energy market offers.
19
How Will Wind RT DNE Dispatch Work?
• UDS will calculate and send out a Do Not Exceed limit to
each wind plant on dispatch
• The DNE limits will reflect
–
–
–
–
Economics
Constraints
plant status (RTHOL and persistence)
high-confidence “next 5 minutes” wind output forecasts
• Will consider both energy balance (i.e. gen = load) and
reliability
• Will allow price-based congestion management based on
offer parameters
– Contemplates the eventual introduction of negative energy offers
20
How Will Wind RT DNE Dispatch Work? (cont.)
• Wind plants will be considered “following dispatch” if operating
between 0 MW and the DNE limit and not exceeding ramping
limits.
– Output can vary with changing weather conditions
– Downward ramps due to plant emergencies and/or decreasing
wind not counted for “following dispatch”
• Will allow wind plants on dispatch to be eligible to set price
• Accurate forecasts and frequent telemetry should reduce
curtailments and provide greater opportunity to maximize
output.
• Will prevent “manual procedure” overload for system operators
21
Who is Affected and When?
• No one is affected until the DNE dispatch software can be
implemented (estimated for 2014)
– ISO efforts have been unable to identify a feasible way to dispatch wind
manually
• Once software is in place, DNE dispatch may be optionally selected by
wind plants through their offer data
• DNE dispatch is planned to become mandatory when negative energy
offers are implemented, for wind plants that meet one or more of the
following conditions:
– Interconnect to a transmission facility or a FERC jurisdictional distribution
facility
– Has a Capacity Supply Obligation
– Is a Capacity Network Resource
– Has a total nameplate capacity at the point of interconnection of >= 5 MW
22
How Will a Wind Plant Participate
• Submit an economic offer curve into the Day-Ahead or Real-Time
Energy Markets
• Must be providing all weather and plant data required by recent OP14 & OP-18 changes
– This data supports the forthcoming real-time wind forecast system
– Accurate real-time wind production forecasts are critical to effective operation of
the DNE dispatch
• No requirement to offer into Day-Ahead
• Self-scheduling will continue to be permissible while Wind RT
Dispatch is voluntary.
• Assuming a dispatchable wind plant offers $0 commitment costs, it
will be treated as “committed” whenever available (i.e. RTHOL > 0)
– Otherwise, must offer & clear in DA, or self-schedule in RT
23
New England’s Current Implementation Plan
• Voluntary Wind RT DNE Dispatch – mid-2014
– Market rules being presented today address only voluntary DNE
dispatch
• Implementation on a voluntary basis provides some early
operational/reliability benefits, but will not fully resolve
pricing and congestion management issues until all wind
plants are responding to DNE dispatch instructions
• Becomes mandatory when negative offers are
implemented.
– Likely not until 2014 or 2015
– Will require a separate rule change at that time
24
THANK YOU
Paul Roberti, Commissioner
Rhode Island Public Utilities Commission
89 Jefferson Blvd.
Warwick, RI 02888
Tel: (401) 780-2147
Email: [email protected]
25