TSLOST Update - Columbus, Georgia

Download Report

Transcript TSLOST Update - Columbus, Georgia

TSPLOST Update
River Valley Region
TIA Citizen’s Panel
April 24, 2014
COLUMBUS
TSPLOST PROJECT LISTING
TSPLOST PROJECTS
Band 1
CY 2013 - 2015
COLUMBUS
RIVERWALK
Project Description:
The extension of the Riverwalk behind Bibb and
City Mills to complete the project
Riverwalk at Bibb Mills and
North Highland Dam
Projected Costs: $10,000,000
• PE - $1,000,000
• CST - $9,000,000
Status:
• Notice To Proceed – April 24, 2013
• Hecht Burdeshaw is preparing construction
plans
• All ROW has been identified. No additional
property will be required
• Construction is anticipated by the first of
2015
Riverwalk at City Mills
As of February 20, 2014
INTERCITY EXPRESS BUS
PARK-N-RIDE SERVICE
Project Description:
Construction of three express bus Park-N-Ride
locations in Columbus using existing sites.
Projected Costs: $22,400,00
• Costs to include design, maintenance
and operation
• Budget for these items still to be
determined
Status:
Proposed Trail From Infantry
Museum to Levy Road
•
•
Notice To Proceed – April 24, 2013
Connectics Transportation Group was hired
in October 2013 to perform a Public Transit
Needs Assessment
•
Current METRA Route
System
•
•
•
Assessment needed to determine how best to
serve our citizens
Study includes route analysis, rider surveys
2nd Public meeting to hear citizens needs and
concerns on May 8, 2014
No other activities will begin until study is
completed
As of February 20, 2014
SOUTH LUMPKIN
MULTI-USE FACILITY
Project Description:
Proposed
New Trail
From
Infantry
Museum
to
Cusseta
Road
A pedestrian/bicycle facility to be built along an
abandoned rail road line. This linear greenway
corridor is divided by Old Cusseta Road, Victory
Drive, and Fort Benning Road
Projected Costs: $3,500,000
•
•
PE – $ 500,000
CST - $3,000,000
Status:
•
•
•
•
•
•
•
Notice To Proceed – September 10, 2013
Heath & Lineback Engineers are the lead
consultants on this project
Public meeting was held on January 16, 2014
Preliminary design – May 2014
Final design – November 2014
Project Bid & Construction – January 2015
No other activities will begin until study is
completed
As of February 20, 2014
US 27/CUSTER ROAD INTERCHANGE
RECONSTRUCTION/MODIFICATION
Project Description:
This project will provide permanent public access to
the proposed property bounded by US 27 to the
south, I-185 to the west, and Cusseta Road to the
north and east, which is the western boundary of
Fort Benning
Projected Costs: $20,000,000
• PE – $ 1,000,000
• CST - $19,000,000
Status:
•
•
•
Proposed property to be
accessed by project
•
Notice To Proceed – April 19, 2013
MOU with Ft. Benning has been signed by all
parties
Wolverton & Associates have begun
preliminary design on project – expect
completion by December
Construction projected to begin Spring 2015
As of February 20, 2014
TSPLOST PROJECTS
Band 2
CY 2016 - 2019
BUENA
US
27/CUSTER
VISTA ROAD
ROAD INTERCHANGE
RECONSTRUCTION/MODIFICATION
INTERCHANGE
Project Description:
The purpose of the project is to reconstruct the
interchange of I-185 and Buena Vista Road
Projected Costs: $47,670,000
• ROW - $28,700,000
• PE – GDOT Authorized in 2001
• CST - $18,970,000
Status:
• Notice To Proceed – Will not be authorized by
GDOT until 2016
• GDOT has expressed an interest to accelerate
this project by authorizing the engineering to
begin in 2014
Buena Vista Road Interchange
As of February 20, 2014
INTERSECTION IMPROVEMENTS
ALONG BUENA VISTA ROAD (Spider Web)
Project Description:
The project will include road realignments and/or a
possible overpass on Buena Vista Road
Projected Costs: $40,000,000
• PE – $ 2,522,522
• ROW - $ 8,649,648
• CST - $ 25,225,225
• UTL - $ 3,603,605
Status:
Spider Web Area
• Notice To Proceed – Will not be authorized by
GDOT until 2016
• City has taken the initiative to fund the
preliminary concept and design of this project
now
• Public hearing on this has been scheduled
for May 12
• GDOT has expressed an interest to accelerate
this project by authorizing the engineering to
begin in 2014
As of February 20, 2014
SR 219 PASSING LANES FROM LUTHER
LANDING BRIDGE TO HAPPY HOLLOW ROAD
(River Road)
Project Description:
A passing lane will constructed along SR 219 from
Luther Road Bridge to Happy Hollow Road
Projected Costs: $17,690,438
• PE – $ 1,597,736
• ROW - $ 403,427
• CST - $ 14,187,438
• UTL - $ 1,501,837
Status:
• Notice To Proceed – Will not be authorized by
GDOT until 2016
• This project will eventually be the sole
responsibility of GDOT
As of February 20, 2014
TSPLOST PROJECTS
Band 3
CY 2020 - 2022
CUSSETA/OLD CUSSETA
ROAD IMPROVEMENTS
Project Description:
Project consists of improvements
on Cusseta and Old Cusseta Road,
from Fort Benning Road to Staunton
Drive
Projected Costs:
$58,289,412
• ROW - $ 41,402,448
• CST - $ 16,866,964
Status:
• Notice To Proceed – Will not
be authorized by GDOT until
2020
As of February 20, 2014
DISCRETIONARY
FUNDS
YTD Collections = $2,422,548
TSPLOST UPDATE
April 24, 2014
QUESTIONS?