Technical Audit Pipelines @ PNIS

Download Report

Transcript Technical Audit Pipelines @ PNIS

Technical Audit of Oil & Gas
Pipelines PNIS Project
Contract : 1,4 M €
Consortium : Technipipe/AETS
www.technipipe.com
from July 2005 to December 2006
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Maintain and improve the long-term integrity of the
Central Asian Oil & Gas pipelines export to EU,
Overcome the gap of working environment between NIS
and Western oil & gas pipeline companies.
Use the establishment of a Pipeline Network Information
System as a basis for transfer of technology and
procedures to the gas transmission companies of
Central Asia.
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Overall objectives
The industrial tool, the pipeline network should
no longer be seen as a black box and should
become totally transparent (glass box). At any
moment, the actual state of the pipeline system
and its evolution in time can be displayed.
The best way to get people to really care for the
cathodic protection is to show them concretely
the consequences of an ill maintained system.
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
SWOT of The Beneficiaries
Strengths
-Large experience in pipelines & Strong organization
-Good education background & Common working language (Russian)
Weaknesses (issues)
-Poor overall status of pipeline & no separate regulation organization
-Lack of exposure to the new technologies and Western standards
Threats (risks)
-Competition between the Beneficiaries for leadership
-Gaps of competence, procedures and technology will have to be filled
Opportunities and Assumptions
-The Steering Committee to reinforce the regional approach.
-The ground for a team of regional expert will be explored
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
 Project Team based in Tashkent
-Project Manager
-Team Leader
-Software Expert (PNIS)
-Inspection/Maintenance Expert
-Training/Inspection Expert
-Teachers from Gubkin oil & gas University (Moscow)
-Local Coordinator, Junior Expert, services
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
MAIN ACTIVITIES\ # MAN DAYS Team
\ EXPERTS
Leader
Maintenance Software
Expert
Expert
Junior
Expert
Russian
Senior
Expert
Western
Senior
Expert
Total
1/ in line inspection of selected
essential pipeline section
25
5
15
20
65
2/ Above ground inspection of
these pipelines
40
5
15
20
80
9
27
194
10
108
60
5
10
3/ Provision of know-how for the
development
of
a
data
information system on the oil &
gas pipelines networks
4/ training of local personnel
5/ procurement of equipment
6/ Dissemination
results
of
240
118
25
10
311
15
40
project
X/ various (project
management, Steering
Committees…)
TOTAL
Brussels April 16th 2007
35
19
10
64
91
10
5
106
243
206
224
50
118
65
906
Technical Audit Pipelines @ PNIS
Various phases of the Project :
-Inception
-4 Steering Committees (France, UZ, KZ)
-4 Dissemination seminars (UZ, KZ, KY,TU)
First 4 months : « Inception trips » :
..Analysis of environment, identification and contact of partners/ beneficiaries,
clarification of project objectives and strategy,
..Approval from Beneficiaries of planned activities, specification of PNIS…
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Khiva Training Center
Intensive usage of Khiva Training Center
(Gas transportation Training Center
assigned to the project by Uztransgaz).
Training Plan made up of 8 Modules
designed after Competence/knowledge
assessment
Modules 1 & 2 : engineering, design,
construction and maintenance of
pipelines (Khiva, Almaty & Moscow)
Modules 3 & 3bis : Inspection (using tools
sourced from European suppliers)
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Khiva Training Center
Module 4 : On site Above ground
Inspections (in Bishkek area)
Module 5 : On line Pigging (in Samarkand
with Rosen) of 40’’ x 156 km.
Modules 6 & 7 : PNIS implementation
operation & maintenance (theory only)
Module 8 : Train the trainers (for the
Beneficiaries to be able to train in their
own countries)
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Conclusion
Priorities as per the 4 dissemination seminars :
1) Build/refurbish Cathodic Protection on full pipeline network.
2) Implement a large training program on Cathodic Protection
3) Collect the Cathodic Protection status by transmission network
4) Walk Survey weekly (Cathodic Protection efficiency, coating damage)
5) Prioritize above ground inspection (DCVG) where the Cathodic Protection
has failed or if the Cathodic Protection data are wrong
6) Dig out the pipeline where coating defects are suspected and carry out US
measurements, eventually repair
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
Priorities as per the 4 dissemination seminars :
7) Carry out intelligent pigging in the High Risk Areas
8) Develop an Integrity Management System/RBI (Risk Basis Inspection)
9) Develop repairs by clock spring method
10) Collect the Cathodic Protection Data in real time
11) Implement a PNIS
12) Implement a SCADA system (for new or revamped pipelines)
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
PNIS is a “Pipeline oriented Geographical Information System”
applied as a “Pipeline Integrity Management System”
It provides a tool to store and display the pipeline system (with pipe
characteristics and inspection data) in its geographical environment
It provides the computational analysis to determine segment length &
segment proximity to geographical land marks
It allows queries & reporting
It helps the user to classify the pipeline segments by pipe
characteristics (diameter, pressure, coating, etc.) by pipe status
(inspection data) or by geographical land marks
Brussels April 16th 2007
Technical Audit Pipelines @ PNIS
PNIS optimizes maintenance through Risk Based Inspection
RBI uses PNIS to :
Segment the pipeline according to risk factors
Identify risk contributors and deduce corresponding risk reducers
Rank / Assign weights to the risk contributors
Compute a risk factor per pipeline segment
And then to focus inspection on segments that most need it
Brussels April 16th 2007