The ESF in Flanders

Download Report

Transcript The ESF in Flanders

Management and implementation
of ESF in Flanders
An overview of a system and
procedures to manage the ESF
programme and monitor and control
projects
Subjects









Principles
Management
IT systems
Financial rules
Call for proposals
Selection of projects
Payments
Implementation, monitoring, evaluation
Audit and control
ESF-Ag, LV, Brno 04-12-07
2
Principles that guide us







Partnership
Trust
Open and Transparent
Cost / benefit
good housefather
Rules established in advance
Legal certainty
Control and audit closes the circle
ESF-Ag, LV, Brno 04-12-07
3
Management of the
programme
Bodies involved and their role
Bodies involved
 Flemish Monitoring Committee (VMC)
– Horizontal commission
– Thematical commission
– Evaluation commission
– Commission of appeal
 Partnership principle
ESF-Ag, LV, Brno 04-12-07
5
Flemish monitoring committee VMC
 Articles 63-66
 Chaired by Managing Authority
 Composition:
– Minister-president
– Ministers of Employment, Social Economy and
Foreign Affairs
– Administrations of Employment, Social
Economy and Education
ESF-Ag, LV, Brno 04-12-07
6
VMC
- All social partners (3 TU, 1 LE, 1SME, 1F)
– Institutional training bodies (VDAB, Syntra)
– NGO’s
– Local authorities
– European Commission with advisory vote
– Certifying and Audit Authorities with advisory
vote
– Can invite experts
– ESF-Agency is secretariat
ESF-Ag, LV, Brno 04-12-07
7
VMC
 Mission
– Improve selection criteria and procedures
– Monitor implementation of programme via
indicators
– Approve annual and final reports before sending
to EC
– Evaluation of programme via external body
– Formulate adaptation of the programme
ESF-Ag, LV, Brno 04-12-07
8
VMC
 Meets at least twice a year
 Draw up its own rules of procedures within
legal framework
 Has 4 commissions for the day by day work
 Decides by consensus
ESF-Ag, LV, Brno 04-12-07
9
Horizontal commission
 Policy forum – chaired by MA - consensus
 Composed out of representatives of
ministers, social partners, labor marked
director and “pilots”
 Determines on yearly basis the large
political lines to be used on Innovation and
Transnationality
 Budget split on political lines on other
priorities of the OP
ESF-Ag, LV, Brno 04-12-07
10
Thematical commission




Defines concrete priorities per call
Defines readers/annalists
Takes the final decision in case of nonconsensus among readers/annalists
Composition varies according to subject of
call (policy makers and potential promotors)
Chaired by MA - consensus
ESF-Ag, LV, Brno 04-12-07
11
Evaluation commission
 Follow up of external evaluation
 Defines the specific themes and work
programme of evaluators
 Every interested party represented in the
VMC included the EC
 Chaired by Department of Work and Social
Economy
 Advices the VMC by consensus
ESF-Ag, LV, Brno 04-12-07
12
Commission of appeal
 “Internal” appeal open for promoters on
payment decisions
 Hears all parties and studies the reports and
decisions taken
 Takes the final decision in the discussion
between ESF-Agency and promoter
 Composed out of people that were not
involved in the decision making
 Chaired by MA - consensus
ESF-Ag, LV, Brno 04-12-07
13
IT systems used
Systems to support and facilitate
the job
What for
 For the application of proposals and reports
by promoters
– Created on request by external firm
 For registration of final beneficiaries
– CVS
 For bookkeeping
– PROACC
 For internal reporting
– ACCESS
ESF-Ag, LV, Brno 04-12-07
15
What for
 Communication between the different
authorities and the EC
– SFC 2007
 Available only for selected and registered
functions and persons
ESF-Ag, LV, Brno 04-12-07
16
Communication
 All systems work independently from one
another
 Promoters have to register before they can
enter the applicationsystem
 Promoters have to apply for the CVS at
VDAB who manages the system
 ESF-Agency can abstract whatever report
that is needed
ESF-Ag, LV, Brno 04-12-07
17
Financial rules used
Though but transparent, made
public and never changed in the
live cycle of project
Filosophy
 European rules and national bookkeeping
rules
 Every cost necessary for the approved
project
 Cost / benefit and principle of good
housefather
ESF-Ag, LV, Brno 04-12-07
19
Public procurement
 Specifications need to be clear on what will
be paid for
 Invoice need to demonstrate the
concordance between services delivered
and specifications
 Registration of delivered services is the
main problem
ESF-Ag, LV, Brno 04-12-07
20
Real costs
 Staff costs
 Clients or participants costs
 Functioning costs including usage goods
and development costs
 Indirect costs as a flat rate
 Transnational costs
ESF-Ag, LV, Brno 04-12-07
21
A. Staff
 Salaries
– Total costs including social security




Work – home transport
Legal insurances
Others to specify
NO extra legal costs
ESF-Ag, LV, Brno 04-12-07
22
B. Participants





Total salary cost, including social security
Limited to 50% of total project costs
Transport home-work
Legal insurances
Other to specify
ESF-Ag, LV, Brno 04-12-07
23
C. Functioning - development
 Every cost made with a direct link to the
project, eg timber, stones, pens and paper…
 Depreciations of eg machines, computers,…
 Subcontracting necessary services consultants (not the essence of the project)
added value and marked price
 Dissemination
ESF-Ag, LV, Brno 04-12-07
24
D. Indirect costs
 1. 3P-model
 2. Maximum used
 3. Kind of costs
ESF-Ag, LV, Brno 04-12-07
25
3Processes-model
 Dynamical approach of structuring
organisations
 3 main processes
 Client perspective
ESF-Ag, LV, Brno 04-12-07
26
3Processes-model
– Primary processes




The hart of the matter, core business
They show the transformation of input in output
What a client sees directly and pays for
Is related to the mission of an organisation
ESF-Ag, LV, Brno 04-12-07
27
3Processes-model
– Secundary processes
 Direct support for the core
 Specialised processes that are to be considered as
subprocesses of the primary processes
 Clients can judge the quality and accepts paying for
them
ESF-Ag, LV, Brno 04-12-07
28
3Processes-model
– Tertiary processes
 Necessary to support, facilitate the other two
processes
 What has to be included in the price, but of no intrest
to client
ESF-Ag, LV, Brno 04-12-07
29
Maxima
 Based on averages of 2000-2005 projects
 Projects related to unemployment, insertion,
social inclusion
– 20% on staff and functioning
 Projects related to employed persons,
adaptability, innovation and transnationality
– 15% on staff and functioning
ESF-Ag, LV, Brno 04-12-07
30
E. Transnational
 Coordination
 Travel and subsistence
 Subcontracting
ESF-Ag, LV, Brno 04-12-07
31
Call for proposals
Defining policy and criteria,
informing and supporting potential
promotors
Methodology
 Proposal drawn up in ESF-Agency using
PCM
 Partnership discussion with labor market
director and or pilot
 Finalizing proposal and submit to TC
ESF-Ag, LV, Brno 04-12-07
33
Defining policy and criteria
 Horizontal commission defines policy items
 Thematical commission defines per call:
–
–
–
–
–
–
The concrete issues
Admissibility – selection - priority criteria
Budget
Start and end of call period
Running time for projects
Other relevant issues s.a. thematical work,…
ESF-Ag, LV, Brno 04-12-07
34
Precondition
 Organizations need to have started the procedure
to get a quality label before they can apply
 They need to get the basic label before they can
start the project
 Promoters need to maintain and improve the
quality level of the organization or their project
may be suspended or stopped
ESF-Ag, LV, Brno 04-12-07
35
Informing and supporting





ESF-Agency opens call on the system
Publishes call where needed
Organizes information sessions
Organize training in PCM
Supports potential promoters in checking
ideas versus policy and into projects and
applications
ESF-Ag, LV, Brno 04-12-07
36
Supporting
 Act as free consultant for promoters but NEVER
WRITE A (PART OF) PROJECT
 Multimedia and face to face
 WHY?
 Let’s get to know each other and start building
trust
ESF-Ag, LV, Brno 04-12-07
37
The end
 Promotor introduces the application in
system
 Signed hard copy via post
 Respect dates set in advance
ESF-Ag, LV, Brno 04-12-07
38
Selection of projects
Guaranteeing an objective and
broad perspective
Selection procedure
 Applications come in through electronic system
and signed copies via post before end date
 Applications go to three different organizations that
provide for annalists for parallel analyses
 All 3 annalists get the same instructions on
criteria, scoring and procedure
 Annalist have access to electronic system and all
use the same format
ESF-Ag, LV, Brno 04-12-07
40
Selection procedure
 Analyses are brought together in ESFAgency and a proposal for decision is drawn
up
 Annalists meeting discusses proposal for
decision
 If consensus is reached, this is a final
decision and report is made for the TC that
checks procedures and criteria used
ESF-Ag, LV, Brno 04-12-07
41
Selection procedure
 Applications get no consensus
 TC takes the final decision
– Basis
3 analyses
 Promoters are informed of decision
 No appeal
 Contract is drawn up in ESF-AG and send to
promoter to sign
 MA signs
 Project can start
ESF-Ag, LV, Brno 04-12-07
42
Administration
 All texts are uploaded in the electronic
system
 Projects get an account “for live”
 Copy decision goes to
– Certifying Authority
– Bookkeeping
– Q audit team
ESF-Ag, LV, Brno 04-12-07
43
Payments
Getting the money where it is
needed most
Getting ESF money out
 No advance payments but swift payments after
decisions
 Intermediate payments
– After approval of intermediate report (desk or OTS)
– Amount approved in report, balanced with advance
– Within 14 days of approval of report
ESF-Ag, LV, Brno 04-12-07
45
Getting ESF money out
– Final payments
 After approval of final report (desk or OTS)
 Balance between initially awarded and finally
accepted in final report
 Within 14 days of approval of final report
ESF-Ag, LV, Brno 04-12-07
46
Flemish cofinancing
 Advance payments
– 70% of the approved sum on annual basis
– Automatically within 14 days of the project approval
 Pre-finance on the actions
 Intermediate payments
 Final payments
ESF-Ag, LV, Brno 04-12-07
47
Implementation, monitoring
and evaluation of projects
Supporting promoters in reaching
the highest quality
Implementation
 Designing account “for live”
 Info sessions on administrative rules and
necessities
 Training in project management, financial
management,
 Providing instruments for monitoring and
self evaluation
ESF-Ag, LV, Brno 04-12-07
49
Implementation
 Coaching visits
– On the spot assistance in checking organization
of administration, setting up of registration of
services rendered, staff and final target group
– Positive support through point for improvement,
no financial cuts
– Selection basis: risk analyze - on request
ESF-Ag, LV, Brno 04-12-07
50
Monitoring





Through reports (intermediate and end),
Thematical work,
Control visits
Direct request
Multimedia contacts
ESF-Ag, LV, Brno 04-12-07
51
Evaluation
 End report
 Product validation (intermediate and end)
– By peers and experts
– Condition to receive special budgets for
dissemination
ESF-Ag, LV, Brno 04-12-07
52
Audit and control
Partners have an open book for
each other
We can proof what we say
Who and why
 MA
Final Beneficiaries
– Approve and pay
 CA
MA
– Certify and ask for refund at EC
 AA
MA + CA
– Certification and opinion to EC and MA+CA
 EC
MS
– Get reasonable assurance
ESF-Ag, LV, Brno 04-12-07
54
MA versus final beneficiaries
 Audit
– Q-audit
 On paper with desk control (ex ante)
 Follow up visits on the spot (on going)
 Control
– Desk (on basis of report – no invoices)
 100% of the reports – payment claims
– On The Spot (OTS) (check all proof)
 5-10% of total cost on programme level
ESF-Ag, LV, Brno 04-12-07
55
Reports – Payment claims: What
 Content part:
– Intermediate: what differs from approved
application on workprogramme and goals
– Final: what did we do, difficulties encountered +
end result / product
 Financial part:
– Intermediate and final accounts consisting with
reality and in line with content
ESF-Ag, LV, Brno 04-12-07
56
Report – Payment claim: When
 Introduction by promoter via system
– After every calendar year (n)
– Delivered before end of march n+1
 Processed by ESF-Agency
– 90% of claims checked within 90 days
ESF-Ag, LV, Brno 04-12-07
57
Report – Payment claim: Process
 DESK: done by the account using
criteria,…. and COMMON SENSE
– Check contract with report
– Start with content, check criteria and special
conditions
– Make link with finances
– Check respect criteria
– Draw up proposal for decision
– Submit to Programme manager
ESF-Ag, LV, Brno 04-12-07
58
Report – Payment claim: Process
 Letter send to promoter / copy to
bookkeeping and CA
 Promoter can accept
or

file a complaint
 Complaint: recheck by desk and decision by
programme manager
 Appeal: decision by commission of appeal
ESF-Ag, LV, Brno 04-12-07
59
Report – Payment claim: Process
 On the spot: done by desk in collaboration
with colleague,
healthy mistrust
– Prepare like desk
– Agree date with promoter
– Check whatever is needed
– Agree if possible and sign
– If not, make report
– Send over to promoter for comments
ESF-Ag, LV, Brno 04-12-07
60
Report – Payment claim: Process
– Make final report and draw up proposal for
decision, where needed inform of divers
opinions
cfr desk for complaint and appeal
ESF-Ag, LV, Brno 04-12-07
61
Questions






Some will get a straight answer
Some will be more difficult
Some will need to look beyond the horizon
Others will never get an answer
BUT
You must always ask them
ESF-Ag, LV, Brno 04-12-07
62
Thank you very much
 Louis Vervloet
 Director Programme manager
 ESF Agentschap Vlaanderen vzw
Gasthuisstraat 35 5th floor
1000 Brussel
+ 32 2 546 22 38
+ 32 478 50 07 10
[email protected]
www.esf-agentschap.be