PPP in Baltic States

Mitigating Project Risks by Insurance Mark Courtneidge

November 2006 Aon Limited is authorised and regulated by the Financial Services Authority in respect of insurance mediation activities only

• • • •

Presenter

Mark Courtneidge BA(Hons), FCII, AIRM - Director 29 years in insurance industry, 12 at Aon Is responsible for the risk and insurance aspects of numerous projects in the UK and overseas – Project Allenby and Connaught – – – UK Immigration and Prison Services A130 A55 Much of Mark’s vast experience has been gained within in house risk management

Aon London PPP Experience

• UK – Approx 350 projects – – All sectors Concessionaires/Authority/Financiers • Overseas – South Africa – Japan – – – Poland Holland USA

Aon Worldwide

• Primary Activities – Risk Indentification & Analysis – Risk Transfer & Management – Insurance Solutions – Claims & Loss Solutions • Corporate Numbers – 120 countries – 550 offices – 46,000 FTEs – 9,8 Bln USD revenue (‘05)

Aon in The Baltics States

PPP Contacts

Aon Estonia

Erko Toomet

  +372 699 6226 [email protected]

Aon Latvia

Ivars Kiecis

  +371 789 2551 [email protected]

Aon Lithuania

Andrius Masteika

  +3705 252 6099 [email protected]

The Players in PPP

Authority Special Purpose Vehicle (SPV) Construction Sub-contractor Designers/ Engineers Sub/Trade contractors Facilities Management Sub-contractor Equity/Partners Banks Service Provider Sub-contractor

Insurance as a Risk Management Tool

• Identify Risk • Quantify Risk • Manage Risk: – Avoid – Control – Transfer: Insurance

Why Insure in PPP

• SPV balance sheet/cash flow protection • Bank’s comfort and protection of their loan • Authority’s comfort that SPV can continue to operate in event of “defined” losses • Debate on PPP is risk transfer - Insurance provides this

Core Insurances Construction Phase

• Contract Works • Construction Plant • Existing Assets • Marine Transit (Cargo) • Advanced Loss of Profits (works and cargo) • Third Party Liability • Professional Indemnity • Employers Liability • Motor

Core Insurances Operation Phase

• Material Damage • Business Interruption • Third Party Liability • Employers Liability • Motor

Other Insurances

• • • • • • Environmental Impairment (Gradual) Latent Defects (New Assets) Directors & Officers Liability Crime Archaeological Finds Keyman

Insurance Programme Design

• Conformity with agreed requirements of – – – – Concessionaire (SPV) Authority Financiers Sub contractors • Broad Coverage • Insurer Security • Competitive Premiums • Longevity of Programme

PPP Contract/Loan Agreement Insurance Structure

• Insurance Administration – To effect insurance – What if insurance is not available – Special Requirements of Authority &/or Banks • Details of Minimum Insurance Requirements – Construction Phase – Operational Phase

Special Requirements of Authorities &/or Banks

• Non-vitiation • Subrogation waivers • Cross liability clauses • Loss payee requirements • Notification of changes • Minimum cancellation periods • Joint Named Insured • Acceptable Insurers Security • Brokers Letter of Undertaking • Third Party Claims Handling Rights • Right not to reinstate

Things To Watch Out For

• Involving Insurance advisers too late • Unclear risk allocation and insurance requirements • Unrealistic insurance advice • Have all risks been fully considered and priced – eg. “As new” values on existing structures • Construction to Operation Gap • Are Changes catered for

Aon PPP Services

Concessions

• Risk Analysis • Advice on Contractual Risk Management • Risk and Insurance Negotiations • Design Insurance Programme • Place and Service Insurance Programme

Aon PPP Services

Financiers & Authorities

• Risk Analysis • Advice on Contractual Risk Management • Advice on Insurance Requirements • Risk and Insurance Negotiations • Audit Insurance Programme • Ongoing Monitoring

Aon Approach

• Teamwork – Non adversarial – – Experienced Focused, project specific • Philosophy – Proactive – Practical • Worksteps – In depth knowledge of Project – – – In depth knowledge of Players Risk matrix Contract advice and negotiation

A130

• Two separate phases • Construction plus 5 years minimum period • Cross class programme • Single Insurer Panel all classes Works DSU TPL Operational MD/BI/TPL EL Crime

HET

• Specialist/unique vehicles • War zones risk – Vehicles – Drivers • Consequential loss on vehicles

Aspire

• GBP 1 billion existing assets • GBP 1 billion new/refurbishment values • 11 year construction • Multiple sites • Project PI

South Tees

• Major existing assets • Major new build • Multiple handovers • Multiple decants • Latent defects • Major variation order