Transcript Slide 1

J&K Economic Reconstruction Agency
J&K Govt. Nodal Agency for Implementing External Aided Projects
http://www.jkera.org
Opportunities in J&K
Presentation by: Er. O. P. Dubey
Director (Urban), ERA
Economic Reconstruction Agency (ERA)
Hotel Tramboo, Dal Gate, Boulevard, Srinagar
13C/C, Near Aquaf Market Gandhinagar, Jammu, J & K 180004
Tel.: 0191-2549664/2455412/2455198 Fax:0191-2547133/ 2455153
Email: [email protected]
1
 J&K Economic Reconstruction Agency (ERA) is a
Special Purpose Vehicle constituted by Govt. of
Jammu & Kashmir for executing externally aided
projects.
 ERA is guided by Governing Body headed by
Hon’ble Chief Minister of the State.
 ERA presently executing ADB Loan-I & Loan-II
2
LOCATION
JAMMU CITY
 Jammu city:
 Status:
 Connectivity:
 Climate:
560 Kms from Delhi
Winter capital of J&K State
Civil Airport, National Highway – 1A & Rail link
connection with rest of the country
Hot & Humid during summer & cold in 3 winter months
 Altitude:
305 m above MSL
 Working Season:
12 months
SRINAGAR CITY
 Srinagar city:
 Status:
 Connectivity:
 Climate:
 Altitude:
 Working Season:
290 Kms north of Jammu city
Summer Capital of J&K State & famous Tourist destination
International Airport & National Highway 1A, connection
with rest of the country
Pleasant in summer & extremely cold in winter
1730 m above MSL
3
8 months
Facilitation by ERA















Loan-II (JKUSDIP)
Use of FIDIC contract conditions
Quick bid evaluation and award process in Transparent manner
10% Interest free mobilization advance against bank guarantee
Provision of Price Adjustment
Excise and custom duty exemption benefits on items to be used in the works
Entry Tax exemption on construction equipment as per rules
Adequate availability of funds & timely release of Payments
Quick decision on contractual issues through TAC within ERA
Experienced Staff in Project Implementation Units (PIU)
Professional Management (Directors with Engineering background)
Regular coordination at level of Divisional Commissioner
Implementation through the experienced Consultants
Rehabilitation & Resettlement followed as per ADB guide lines
Right of way available
Contract award only after shifting of utilities and R.P implementation.
4
LOAN-I (2151-IND) – Multisector Project for Infrastructure Rehabilitation
 Loan Size
-
Rs. 1611 Crores
 Date of start
-
Dec, 2005
 Date of closing
-
Dec, 2012
 Sectors covered
• Urban
-
• Transport
• Reforms
-
Water Supply, Sewerage, Drainage,
Solid Waste Management & other
Municipal Facilities
Roads, Bridges
Capacity Building & Institutional
Reforms.
 Overall progress
• Physical
• Financial
-
80%
75%
5
LOAN-1 (2151-IND)
Milestones
A. URBAN SECTOR
 Water Supply Sector:
 Augmentation of 103.00 MLD of water by construction of 54 No Tube wells
 Storage capacity – 37.00 MLD by constructing 50 No OHT/GLSR
 Water supply Pipe laying
-
423.00 Kms
 Equipments (Water tankers + Pumping machinery + Sewer & Garbage)
 Drainage
 Rehabilitation of Nallahs / Deep drains
-
43 Kms
 Storm water deep Drains
-
54 kms
-
36 Nos.
 Roads 40 Nos.
-
613 Kms
 Bridges
-
25 Nos.
 Sanitation
 Pay and Use Public toilets
 TRANSPORT SECTOR
LOAN-II (IND-2331)
 Jammu & Kashmir Urban Sector Infrastructure Development Program
(JKUSDIP) having multi-tranches
 To improve Urban Infrastructure in Capital cities of Jammu & Srinagar
 Loan Size
-
Rs. 2425 Crores
 Date of start
-
May, 2008
 Consultants :
• Jammu – Shah Technical Consultants Pvt. Ltd. in association with
Mott Mac Donald Pvt. Ltd.
• Kashmir – Poyry Environment GmbH
 Process for engaging New Project Support Consultant is in progress
7
PROJECTS UNDER EXECUTION IN TRANCHE-I, Loan-II (JKUSDIP)
Jammu City
 Sewerage Network laying in Jammu (03 Packages)
 Cost
-
Rs. 114.01 Crores
 Scope (length of sewers)
-
146 Kms
 Sewerage Treatment Plant 30 MLD with MBBR Technology
 Cost
-
Rs. 28.61 Crores
Srinagar City
 Development of Landfill site in Srinagar city
01 Cell
 Laying of raw water pipeline from Harwan to Nishat, Srinagar
 Cost
-
Rs. 35.98 Crores
 Scope
-
6.00 Kms
8
SUB-PROJECTS APPROVED UNDER TRANCHE-II
 Estimated cost
-
Rs. 714.20 Crores
Status of Bidding
-
Under process

Sub-projects in Jammu City
09

Water Supply Sector – 5 No. projects
-
Cost Rs. 111.54 Crores

Drainage Sector – 3 No. projects
-
Cost Rs.
95.69 Crores

Transport Sector – 1 No. project
-
Cost Rs.
95.50 Crores
Total
-
Sub-projects in Srinagar City
Rs. 302.73 Crores
05

Water Supply Sector – 1 No. project
-
Cost Rs.
3.80 Crores

Drainage Sector – 1 No. project
-
Cost Rs.
24.60 Crores

Solid Waste Management – 1 No. project
-
Cost Rs.
6.90 Crores

Transport Sector – 2 No. projects
-
Cost Rs. 376.17 Crores
-
Rs. 411.47 Crores
Total
9
Brief Description of Sub-projects – Tranche-II (JKUSDIP)
Jammu City
Water Supply
1. 19 Tube wells and 10 RCC Over Head Tanks
2. Replacement of worn-out pumping machinery
3. Replacement of worn-out pipes
-
Rs. 37 Crores
Rs. 40 Crores
Rs. 15.5 Crores
 Sites
-
Available
 Type of contracts
-
NCB
 Date of IFB
-
June, 2012
 Expected date of contract award
-
Oct - Dec, 2012
 Date of start of work
-
Feb - March, 2013
 Completion Period
-
24 months
 Rehabilitation
-
Not required
Status:
10
Brief Description of Sub-projects – Tranche-II (JKUSDIP)
Jammu City
Transport Sector
Road widening & flyover from Bikram chowk to Convent School
 Estimated construction cost
-
Rs. 75 Crores
 Flyover length
-
1.3 Kms (4-lanes)
 Road widening length
-
1.5 Kms (8-lanes from 6-lanes)
 Busbays / Subway
-
6 Nos.
 Type of Contract
-
ICB
 Date of IFB issue
-
June, 2012
 Expected date of contract award
-
Nov, 2012
 Completion Period
-
36 months
11
Brief Description of Sub-projects – Tranche-II (JKUSDIP)
Drainage Sector
Jammu City
1. Digiana, Gangyal, Ashram &Thanger Nallahs
-
Rs. 56 Crores
 Length
-
20 Kms (RCC with culverts)
 Type of contract
-
ICB
 Date of IFB
-
June, 2012
 Expected date of contract award
-
Nov, 2012
 Completion Period
-
36 months
-
Rs. 15 Crores
 Length
-
8.2 Kms (RCC with culverts)
 Type of contract
-
NCB
 Date of IFB
-
June, 2012
 Expected date of contract award
-
Dec, 2012
2. Channi Himmat drains.
 Completion Period
-
24 months
12
Brief Description of Sub-projects – Tranche-II (JKUSDIP)
Srinagar City
Transport Sector
1. Flyover/Elevated expressway corridor form Jehangir chowk to Rambagh, Natipora
 Estimated construction cost
-
Rs. 208 Crores
 Flyover length
-
2.41 Kms (4-lanes)
 Width of flyover
-
4-lanes
 Type of Contract
-
ICB
 Date of IFB
-
June, 2012
 Expected date of contract award
-
Nov, 2012
 Completion Period
-
36 months
 Rehabilitation
-
Done
13
Tranche-II (JKUSDIP)
Srinagar City
Transport Sector
2. Multi Storied Parking facility at KMD Adda -
Rs 25.00 Crores
 Type
-
5 level Automated Puzzle parking
 Land
-
Available
 Total no. of parking slots
-
288 Nos.
 Type of Contract
-
NCB
 Date of IFB
-
June, 2012
 Expected date of contract award
-
Nov, 2012
 Completion Period
-
24 months
14
Tranche-II (JKUSDIP)
Srinagar City
Procurement of Equipment – 02 Packages
-
Rs. 10.70 Crores
 Type of Contract
-
NCB
 Date of IFB
-
June, 2012
 Date of start of work
-
Nov, 2012
 Completion Period
-
6 months
(Water tankers, Jetting machine, Motorized Waste Collector ,
JCB, Compactors, Hook Loaders, Dumper Placers, etc )
15
Tranche-II (JKUSDIP)
Srinagar City
Drainage Sector
Construction of Storm water drains
-
Rs. 24.6 Crores
 Scope
-
9.20 Km Deep drains &
1 no. pumping station
 Type of Contract
-
NCB
 Date of IFB
-
June, 2012
 Date of Contract award
-
Nov, 2012
 Completion Period
-
36 months
16
Sub-Projects likely to be taken up under Tranche-III
Jammu City
Tentative cost
1. 225 MLD Jammu Water Supply from Chenab river, Phase-I
-
Rs. 491.50 Crores
-
Rs. 90 Crores
-
Rs. 80.00 Crores
-
Rs. 250 Crores
-
Rs. 120 Crores
(Project principally agreed upon by J&K Govt.)
2. 02 Nos. Water Supply pipe laying sub-projects
3. Development of 2 Nos. Regional towns
(Kathua & Udhampur)
Kashmir City
1. Sewer & Drainage
2. Development of 3 nos. Regional Towns
(Kargil, Baramulla & Anantnag)
17
ERA invites you……..
Thank You…………
18