Ad Valorem – Capital Projects

Download Report

Transcript Ad Valorem – Capital Projects

Ad Valorem – Capital
Projects
April 28, 2008
1
Purpose
Two budget workshops this week – today
and tomorrow
Focus on Ad Valorem funded projects
Gain Board direction
Other non-ad Valorem funded projects will
be reviewed at later workshops
2
Past Capital Accomplishments
-
Charlotte County has enjoyed a sustained
period of building and re-building Capital
Infrastructure.
The Event and Conference Center
Emergency Operations Center
New Fire Stations
Regional Parks
Mid County Regional Library
3
Current Budget Distribution
COUNTY BUDGET TOTALS
Other
11%
Personal Services
9%
Operating Expenses
19%
Reserves
12%
Transfers
7%
Capital Outlay
42%
4
Budget Issues
Priorities from the Board of County
Commissioners:
- Reduce Murdock Village debt and
develop a re-payment plan for the
remaining debt
- Consider delay of Capital Projects to help
fund operations during reduced revenues
from Amendment 1 and potential
de-valuations
5
The Approach
Re-think each Ad Valorem funded project
in the Adopted FY07/08 CIP
Putting projects into the following
categories:
1. Projects Eliminated
2. Projects Delayed
3. Projects Continued
6
Projects Eliminated
Projects that are suspended and budgeted
dollars can be re-directed for Murdock
debt pay-down or revenue shortfall
7
Projects Delayed
Projects that will be delayed (moved out
of the CIP for FY07/08) and re-directed
for Murdock pay-down or revenue
shortfall.
Delay includes re-thinking and reengineering
Delay period: 1-4 years
How will projects get re-funded?
- capital millage rate .3887 - $7M
8
Projects Continued
Currently in construction
Safety or ADA Issues
Concurrency
9
How much to re-direct?
Goal - $22 Million
- $11 M for Murdock pay-down
- $11 M for Revenue shortfall
Redirection comes from eliminated
and delayed projects
10
List of 42 Projects
Review key points of each project
Give staff recommendation
Seek Board agreement with staff
recommendation or provide other direction
11
The Jail Expansion
This project has significant capital
and operating dollars budgeted
Will address at the end of this
meeting or tomorrow to give
adequate time for discussion of
options and questions to BCC staff
and Sheriff Office personnel.
12
#1 – Second Floor Renovation
Project Eliminated
Amount available for re-direction = 1.9 M
13
#2 - Human Services Building
Recommendation – delay, $ 1.6 M
Staff currently at other County locations
$271,000 spent – design and construction
documents
Understanding funding needs staff
recommends re-direction of funds but if
funding is available this would be a high
priority project.
14
#3 – District 1 Sub Station
Staff Recommendation - delay
New Sheriff sub-station (West County)
project’s revenue source was from Impact
Fees
$1 million shortfall in Impact Fees
delay until Impact Fees are collected,
reduce scope of work, or consider leasing
15
#4 – Hickory House
Delay $209,000
Located at Dotzler Park
Project was to rehabilitate structure and
open to public
Will reconsider in future CIP submittals
16
#5 - Facility Parking and Lighting
Harold Ave. Walkway Lighting
Delay - $200,000
Project was to improve parking and
pedestrian lighting
17
#6 - Placida Fishing Pier / Placida
Park Area
Delay $246,000
Elements of project include: preservation
of Placida Bunk House and design Rotary Centennial Park
Bridge Construction delays project 1 year
Will be considered in future CIP submittal
18
#7 – Port Charlotte Beach Park
Continue $700,000 for boardwalk and
fishing pier deck replacement
Delay $323,000 – Maintenance Building
(delay and continue to seek FEMA funds)
- Building was destroyed during Hurricane
Charley
19
#8 - Fishing Piers and Boardwalks
Englewood Beach Boardwalk
Continue - $612,000
Replacement and repair of Beach Boardwalk
Eliminate - $52,000 – Kiwanis Park footbridge
(cost savings from in-house labor and refined
cost estimate)
20
#9 - Harold Ave. Recreation Cntr
Continue - $190,000 for gym insulation
repair and gym floor repair.
Repairs are a necessary element of
project
Delay - $760,000 – entrance and
pedestraian lighting not as critical and will
be reconsidered in future CIP
21
#10 – West County Boat Ramp
Continue - $142,000 to complete design
and permitting
Delay - $2,092,000 – construction
22
#11 - Tringali Park Bldg 3
Continue $10,000 – complete analysis of
structural repairs
Delay - $170,000 – Englewood Library reuse plan not needed at this time
23
#12 - FEMA Window Grant
5- story Murdock Admin Building
Continue - $569,000 to leverage grant $
from FEMA
Note – FEMA contribution of $1,200,000
Design complete
Eliminate - $100,000 savings from
anticipated favorable bids
24
#13 - Fire Training / Burn Building
Continue - $369,000 – to construct new
building – recommend continuing as this is
partly funded from Sales Tax Extension
along with FEMA.
Eliminate - $375,000 – reduction in size of
building and site work
25
#14 - Small Building Repairs and
Upgrades
Continue - $252,000 for Englewood
Library structural repairs and Cookie
House preservation plan
Englewood Library structural repairs are
critical due to water damage
Cookie House – to develop preservation
plan that would protect the structure from
further deterioration
26
#15 - Ainger Creek Boat Ramp
Eliminate $110,000 (Ad Valorem funding
only)
Other funding sources will allow project to
proceed with a decreased scope of work
or seek other funding
This project was to create a formal paved
parking area.
27
#16 – Horse Arena
Delay - $81,000 – Score Tower
replacement (damaged from Hurricane)
FEMA and Insurance not adequate for rebuilding at current standards
Will seek other funding sources
28
#17 – South County Annex
Project Eliminated
Amount available for re-direction =
$850,000
29
#18 - Spring Lake Park Restroom
Delay - $50,000
Plan was to construct new restroom –
recommend delay construction until
alternate funding is available through
parking fees or Boater Improvement
Funds.
30
#19 – Carmalita Park
Delay -Concession Building replacement $383,000
Destroyed by Hurricane
FEMA and Insurance funds inadequate
31
#20 – Holiday Lakes Boat Ramp
Eliminate - $75,000 for parking
improvements and dock repair
Eliminate Ad Valorem funding only –
Boater Improvement Funds ($50,000) will
allow for a reduced scope of work
Seeking additional Boater Improvement
Funds
32
#21 - Bayshore Live Oak Park
Continue - $149,000 Interpretive Sign
Program – park of Master Plan
Delay - $125,000 playground
Delay of playgrounds – countywide
discussion to include Oyster Creek and
Charlotte Sports Park
33
#22 - Renovation of Fire Stations
Continue - $2,689,000 – to complete
construction of:
Station #9 (S.R. 31)
Station #11 (Harbour Heights)
This completes an on-going program of
renovating fire stations
Eliminate - $400,000
34
#23 - Oyster Creek Regional Park
Delay - $55,000 – to complete Park
Signage
35
#24 - Sunrise Park
Continue - $200,000 to complete
contracted construction work
On Edgewater Drive
Project: - Fishing dock, restroom, canoe
launch and parking, etc.
36
#25 - Event and Conference Center
Continue and complete construction
37
#26 - Florida Friendly Landscape
Eliminate $80,000 (Ad Valorem)
Project continues (reduced scope) with
Native Tree Trust Funding
38
#27 - Pavement Maint. &
Resurfacing
Delay - $987,000
Various County locations – program
expands, resurfaces, re-stripes and
maintains parking areas
This action delays this program for 1-year
39
# 28 - Security Upgrades
Postpones security for 2nd floor of newly
renovated historic Courthouse - $179,000
Will re-program when Court occupies the
space
40
#29 - Playground Replacement and
Purchase
Delay - $425,000
Locations include:
Oyster Creek Reg. Park –
Charlotte Sports Park and
Various replacements
Delay period – based on funding
availability and prioritization
41
#30 - Park Land Acquisition
Delay $160,00
Funding was for purchase of properties
near existing park facilities
42
#31 - Parking / Stormwater
Improvements
Harbour Heights Park
Delay - $540,000
This funding was to address an existing
drainage / flooding item
43
#32 - Various Facility
Improvements
Continue - $300,000
Delay - $380,000
Program continued for improvements and
renovations to county facilities to comply
with building codes and ADA requirements
44
#33 - Sports Lighting
Continue - $20,000 – replacement of
Camalita Field #3 – electrical switch gear
due to critical safety issue.
Delay - $180,000 – New skate park
lighting at Oyster Creek Regional Park.
The $180,000 was to supplement a
$20,000 donation for the skate park
lighting.
45
#34 - ADA Renovations
Continue - $415,000
Historical Center
Cedar Point
Harold Ave. Park
ADA and Safety requirements
46
#35 - Ambulance Replacement
Continue $360,000 to replace two (2)
ambulances due to high milage
This is an on-going annual replacement
program
Eliminate - $18,000 – favorable pricing
47
#36 - Family Services Center
Continue - $200,000
Eliminate - $2,000,000
Delay - $1,600,000
Continue – ADA & Safety issues
Delay – re-evaluate highest priorities and
have future discussion with Board
Eliminate – previously requested
expansion
48
#37 – West County Regional
Library
Delay - $863,000 – (design)
Spent to date – $337,000
49
#38 – RR Trestle Removal / Repair
Delay - $700,000
Locations: Boca Grande and Myakka
River
Board previously discussed – contract not
awarded
50
#39 – Cape Haze Pioneer Trail
Eliminate $33,000
State will now fund
51
#40 - Neighborhood Parks
Delay - $900,000
Project funding was for Rickardway Park
in the Murdock area for exotic control and
design / construction of park amenities.
Construction of new neighborhood park is
not a priority
52
#41 - Radio System Upgrade
Continue - $2,477,000
Eliminate - $5,209,000
Continue is for the upgrade of 5 controllers
to extend the life of the radio system
($296,000).
Continue for additional tower. This site will
enhance South County coverage. One
time cost of $2,181,000.
53
Other Projects - Non Ad Valorem
Bachmann (Future Public Works / Fleet / Fuel)
$629,547 Spent to date – design and preconstruction
FY08 project element was to construct a Fleet /
Fuel Facility. Recommend delay to complete
analysis of operation and capital options (revisit
alternate suited locations, consider partnerships
and lease / purchase opportunities).
54
Other Projects - Non Ad Valorem
San Casa – recommend continuing
Expand existing space (Public Works West
County Facility)
$546,000 – from gas tax
This project is to correct an existing inadequate
space issue and will allow for maximum
efficiency and savings; being able to fully utilize
this facility. Savings comes from fuel, time,
scheduling and supply and material storage.
55
April 29th Meeting
Jail Expansion Discussion / Direction
56