TPA ACTION PLANS TO ADDRESS
CONGESTION AT THE PORT OF
DAR ES SALAAM
Mr. Jason Rugaihuruza
Port Manager
Dar es Salaam Port
25th – 26th September 2008
1
AN OVERVIEW
1.
2.
3.
4.
5.
6.
INTRODUCTION
PORT CONGESTION
MAIN CAUSES OF CONGESTION
DECONGESTING STRATEGIES
ACTION PLANS TO ADDRESS PORT CONGESTION
CHALLENGES
2
1. INTRODUCTION
1.1
DSM Port berths


1.2
Total berths: 11 and lighter quay
Total quay length: 2,600m
Port Terminals




General Cargo Terminal - 8 berths
Container Terminal – 3 berths
Oil terminals
• SPM
• KOJ I & II
Grain Terminal
3
1.3
Transit corridors:
The transit corridors served by the port of Dar-es-Salaam
are TAZARA corridor, Central corridor, Tanga
corridor and Mtwara corridor.
These corridors are supported by road, rail, lake or/and
pipeline transport system.
4
4
DR
DR
CONGO
CONGO
3
4
3
2
2
1
1
NB: NB:1- Mtwara
corridor,
2- DSM
TAZARA
corridor,
1- Mtwara
corridor,
2- DSM
TAZARA
corridor,
3- DSM
Central
corridor,
4- Tanga
corridor
3- DSM
Central
corridor,
4- Tanga
corridor
5
2. PORT CONGESTION
2.1 Port started to experience congestion end of year 2006,
and severe congestion was from November 2007.
2.2 Main congestion indicators include:
(a) Long waiting times for ships at outer anchorage,
and high ship turnround times.
6
(i) Waiting time (days/ship)
8
7
Days/ship
6
5
4
3
2
1
0
2000
2001
2002
2003
2004
2005
2006
2007
Aug08
GCT
0.4
0.4
0.2
0.3
0.5
0.4
0.5
0.9
0.7
CT
0.2
0.2
0.2
0.2
0.4
0.5
1.6
4.3
7.5
GCT – General Cargo Terminal
CT – Container Terminal
7
(ii) Turnround time (Days/ship)
12
Days/ship
10
8
6
4
2
0
2000
2001
2002
2003
2004
2005
2006
2007
Aug08
GCT
2.7
2.8
2.9
3.5
4.3
3.8
4.1
4.6
3.5
CT
1.2
0.7
0.9
1.1
1.5
1.9
2.9
6.2
10.9
GCT – General Cargo Terminal, CT – Container Terminal
Long ship turnround times since 2006, indicates slow
quay and yard operations. This is a sign of congestion
of ships at outer anchorage and congestion of
containers in the terminal.
8
(b) High berth occupancy rates
90
80
70
%
60
50
40
30
20
10
0
GCT
CT
2000
2001
2002
2003
2004
2005
2006
2007 Aug-08
41.1
33.4
40.6
32.4
46.6
32.7
43.6
47.1
44.7
45
43.5
47.5
48.5
46.3
53.8
59.2
71.2
83
The berth occupancy for Container Terminal for
year 2007 and 2008 level above 60% which is a
sign of congestion.
9
High dwell times of containers
30
25
Days/container
(c)
20
15
10
5
0
Days/Container
2000
2001
2002
2003
2004
2005
2006
2007
Aug08
25.9
16.6
16.7
17
17.1
20.2
22.2
19.8
25
The dwell time for the terminal from the design
perspective was 10 days. The actual dwell time as
shown above indicates that containers overstay in the
terminal thus creating congestion and slowing down10
operations.
(d) Lower crane productivity (moves per crane net hour)
30
Moves per hour
25
20
15
10
5
0
2000 2001 2002
Moves/hour
15
19
20
2003 2004 2005 2006
23
24
24
22
2007
Aug08
19
16
The crane productivity has been falling down since
2006, an indication of long ship waiting times,
turnround times and yard congestion.
11
3. MAIN CAUSES OF CONGESTION
3.1 Insufficient container storage space.
The Container Terminal intrinsic capacity is 250,000
TEUs per annum. This capacity was surpassed in year
2004, where the Terminal handled throughput of
259,369 TEUs. In year 2007, the Terminal handled
343,436 TEUs, surpassing its designed capacity by
37.4%.
12
Terminal throughput versus its capacity
400000
TEU'S
300000
200000
100000
0
2002
2003
2004
2005
2006
2007
Throughput 149100
166327
201058
259369
293919
307791
343436
250000
250000
250000
250000
250000
250000
250000
Capacity
2001
13
3.2 Long container dwell times
Long Container dwell times have direct impact on
Terminal capacity. The higher the dwell time the
lower the capacity, resulting in yard congestion.
STACKING HEIGHT
Dwell time
(in days)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
3 high
4 high
5 high
2,127,332
1,063,666
709,111
531,833
425,466
354,555
303,905
265,917
236,370
212,733
193,394
177,278
163,641
151,952
141,822
2,836,443
1,418,222
945,481
709,111
567,289
472,741
405,206
354,555
315,160
283,644
257,858
236,370
218,188
202,603
189,096
3,545,554
1,772,777
1,181,851
886,388
709,111
590,926
506,508
443,194
393,950
354,555
322,323
295,463
272,735
253,254
236,370
Based on current Container Terminal area of 3,157
groundslots.
14
Capacity versus dwell times
Annual capacity (in TEUs)
4,000,000
3,500,000
3,000,000
2,500,000
2,000,000
1,500,000
1,000,000
500,000
0
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15
Dwell time in days
3 high
4 high
5 high
15
3.3 Sharp increase of container volumes
400000
TEU'S
300000
200000
100000
0
2000
2001
2002
2003
Imports
62119
68921
73090
90135 105594 115215 121471 160100
Exports
60549
66519
68297
77663
93730 113513 120776 145065
Transshipment
1980
6280
12409
18319
27790
Total
2004
2005
29661
2006
30453
2007
28815
124648 141720 153796 186117 227114 258389 272700 333980
Containerized cargo traffic trend has been reflecting a positive
increase of 15.1% per annum as from year 2000 to 2007. In year
2007, the proportion of containerized cargo to dry cargo traffic was
62%, as compared to 48% in year 2000.
16
3.4
Poor inland transport:
•
Many roads are not fully paved (85% of the roads)
resulting in long travel times.
•
Low availability of locomotives and rolling stock.

TRL : 1.0 metres gauge, with capacity of 2.5 million
tons and achieving less than 30% per annum.

TAZARA: 1.067 metres gauge, with capacity of 5 million
tons, and achieving less than 12% per annum.
17
Cargo clearance (in ‘000 metric tons)
3000
2500
2000
Metric tons
(i)
1500
1000
500
0
Road
Rail
2000
2001
2002
2003
2004
2005
2006
2007
1089
1061
1160
1307
1606
1646
2069
2478
333
351
266
273
258
233
208
204
The Cargo clearance by all modes has been increasing
by 9.5% per annum since 2000. Clearance by road
has been increasing by 12.5% while by rail has been
declining by 6.8%.
18
(ii)
Cargo clearance (in ‘000 tons) and percent share by modes
2001
ROAD
TRL
2002
2003
2004
2005
2006
2007
1061
1160
1307
1606
1646
2069
2478
168
104
89
79
185
133
83
35
57
51
73
48
75
121
TAZARA
%Share
ROAD
83.9
87.8
90.3
91.4
87.6
90.9
92.4
TRL
13.3
7.9
6.2
4.5
9.8
5.8
3.1
TAZARA
2.8
4.3
3.5
4.2
2.6
3.3
4.5
The share of cargo cleared by road has been keeping on
rising while that of rail has been falling. The shortage of
wagons contributes to decline of cargo clearance share
compared to road mode of transport.
19
4.
DECONGESTING STRATEGIES
4.1 Increase of Container Terminal capacity
(groundslots) and use of Inland depots.
4.2 Better utilization of terminal capacity within the port
(equipment, workforce, space, procedures, IT).
4.3 Joint effort by stakeholders to reduce dwell time of
cargo in the port.
20
5. ACTION PLANS TO ADDRESS PORT CONGESTION
5.1 Short-term measures
No.
Action plan
Implementation
Computerize all
operations and
interface with terminal
operators
Harbour view has been put in
place, and now cargo system is
being installed and training is in
progress.
Working 24 hours
Operations and billing system are
on 24 hours basis.
3
TPA General Cargo
Terminal has started
handling containers
since June 2007.
Todate 112 container ships with
containers 24,267 TEUs have been
handled at General Cargo
Terminal.
4
Port Community
network should be
adapted.
Looking for a developer,
Consultant and funds
1
2
21
No.
Action plan
Implementation
5
Enforcing a punitive tariff
to discourage shipping
Continues to be being implemented.
agents who delay
submitting manifest.
6
Vessels to discharge
containers at Mtwara
port for transhipment to
DSM port
TPA and TRA are setting up modalities
of starting operations in October
2008.
To transfer containers to
ICDs.
There are now 6 ICDs that are
receiving containers from the port;
TRH, MOFED, AMI, MCCL, DICD and
UICD. Total capacity of ICDs is 8,300
TEUs.
7
22
No.
Action plan
Implementation
8
Three auctions are now being conducted
To speed up auctioning of
at various stations per week; DSM port
cargo overstayed in the port
and Ubungo.
9
TPA continue to acquire
sufficient cargo handling
equipment including heavy
lift equipment - for general
cargo berths
TPA has acquired more cargo handling
equipment such as 2 mobile cranes, 3
reachstackers. Four Mobile cranes are on
order.
Campaign on ensuring
faster container clearance
from the port/ICDs
Preparations are underway to educate
customers on cargo clearance procedures.
10
23
No.
Action plan
Implementation
11
Space of Ex-TANESCO, copper yard and
Securing and providing
New TISCAN are being paved. The
more space within the port
additional space can accommodate about
for container handling.
3,000 TEUs.
12
The use of space for
stuffing, stripping and
verification of all local
cargo outside the port
area.
TPA has discouraged stuffing/stripping
activities inside the port.
13
To utilize Mbeya and Isaka
as fully fledged ICDs
Efforts are underway to reopen and
utilize Mbeya and Isaka dry ports by end
of 2008.
24
No.
14
15
Action plan
Implementation
TPA to improve entry and
exit gates.
Tender document is being prepared. The
project is expected to end by March
2009.
TPA to liaise with
government on the need to
change land use in favour
of port industry of the area
surrounding the port
Efforts are underway to make use of the
ex-NASACO area, Kurasini area in favour
of the Port industry;
25
No.
Action plan
16
TICTS and TRL to co-ordinate
on availability of wagons, and
establish procedures and
identify improvements
17
18
To change the tariff that will
ensure customers take their
cargo in time and bring dwell
time to below 10 days.
TICTS to introduce truck
safety check for all trucks
entering the terminal to avoid
breakdowns and accidents.
Implementation
Use of block trains to Kigoma and
Isaka is underway.
Recommendations are with SUMATRA
Safety Marshall procedures are already
in place.
26
No.
Action plan
Implementation
19
Submission of complete
manifest by Shipping lines.
Submission of partial manifest is now
allowed by TRA.
20
Scanning of containers
immediately after discharging
from vessel; will reduce
Pending acquiring considerable extra
space and improvements of
documentation. This is being done for
ICDs today.
clearance process time.
21
TICTS to improve productivity
and purchase of additional
equipment.
Additional equipment have been
ordered and some have arrived such
as 9 TTs, 2 mobile cranes, 4
reachstackers, 7 RTGs. 1 SSG is
expected in 2009.
27
No.
22
23
24
Action plan
Implementation
All overstayed containers to be
Containers are moved from TICTS to
moved immediately to their
Ubungo ICD in order to create space
designated bonded
at main terminal.
warehouses.
TICTS to transfer all local
cargo (containers) for
verification to ICDs and leave
space for other use.
Plans are underway
TICTS to provide online
information of invoices and
improve method of payment
to include electronic transfers
and/or debit cards
Done - possible from EDI receipt from
shipping line
28
No.
Action plan
25
Large importers should be
allowed to collect their
containers direct from the
port.
26
TICTS should maximize
transfers of containers to
Ubungo by rail locomotive/wagons.
27
TICTS to ensure port tariff
encourages early off take and
reduction in use as storage
area. Tariff also to include
penalty for removal of long
stay boxes.
Implementation
Being done but space does not fully
permit.
TICTS has started transferring
Containers.
To be submitted to SUMATRA for
approval.
29
No.
Action plan
28
TRL to bring into service MV
Kaawa and Pamba to increase
haulage capacity of
wagons/transit cargo to and
from Uganda/Kenya as MV
Umoja capacity is limited.
29
Shortage of wagons and
locomotives (TRL and
TAZARA).
Implementation
The operation is Underway
Recently TAZARA received new 100
and 2 locomotives, and TRL has
acquired 69 wagons. TRL to
rehabilitate 300 wagons and will be
available for use towards the end of
year 2009.
30
No.
Action plan
Implementation
30
To reduce road blocks to at
least by 75%. E.g from DAR to
TUNDUMA there are 25 of
In progress
them! Introduce a sticker
system to show that the traffic
has been checked.
31
Government to maintain roads
and infrastructure - this is a
major block and restriction to
efficient trade - Nelson
In progress
Mandela Road, Port Access
Road must be urgently
upgraded and widened.
32
TRA to streamline document
verification work to avoid
duplication.
In progress
31
2.2 Medium-term measures
No.
Action plan
Implementation
1
To improve and use
Mwanza South port
warehouses for Uganda
TPA/TICTS are following up.
cargo, and also Isaka dry
port for Burundi cargo.
2
TPA to do maintenance
dredging along the quay
to increase draft.
3
TRL to encourage private
investment in wagon
Plans are underway
ferries and locomotives.
A contractor has been engaged and
work has started and expected
finishing time is in December 2008.
32
No.
4
5
Action plan
TICTS to secure areas
outside the port for ICDs
operations.
Implementation
Plans are underway.
TPA to establish one stop
shop for cargo clearance
Surveys and designs are ready.
so that all customers and
Feasibility study is underway.
stakeholders are under
one roof.
33
5.3 Long-term measures
No.
Action plan
Implementation
1
Construction of multistorey car park by TPA so
that cars are moved out
To be ready by end year 2010.
of the port and leave
space for container
handling.
2
Construction of Container Terms of reference are being prepared
Terminal at Bagamoyo.
for feasibility study.
3
Construction of container
berths 13 and 14
To be ready by 2012.
adjacent to KOJ.
34
5.4
Short term Action plans implementation
results:
(a)
Container stock level
Short term action plans implementation have shown
positive results by reducing congestion of the
containers at the terminal from stock level of 11,714
TEUs mid-February 2007 to 6,315 TEUs mid-March
2007. Stock level increased again to 7,897 TEUs
mid-September 2008. The terminal holding capacity
is 7,500 TEUs.
The number of import containers at the terminal has
significantly declined from 7,521 TEUs beginning of
February 2008 to 4,021 TEUs mid-September 2008.
35
Ship at outer anchorage
Number of ship at outer anchorage has decreased
from 14 vessels per day beginning of February
2007 to 0 vessels beginning of September 2008.
SUM M ARY OF VESSELS STATUS AT OUTER ANCHORAGE
FROM 01/01/2008 - 24/09/2008
20
18
16
Days
14
12
10
8
6
4
2
08
1S
ep
-
08
1A
ug
-
08
1Ju
l-
-0
8
1Ju
n
1M
ay
-0
8
08
1A
pr
-
08
1M
ar
-
eb
-0
8
1F
-0
8
0
1Ja
n
(b)
No of Vessels at OA
Maximum waiting time per vessel (Days)
36
04
/0
2
12
/0
2
28
/0
2
07
/0
3
12
/0
3
17
/0
3
21
/0
3
25
/0
3
29
/0
3
03
/0
4
08
/0
4
15
/0
4
21
/0
4
25
/0
4
30
/0
4
9/
5
16
/5
23
/5
29
05 /5
-J
u
11 n
-J
u
23 n
-J
u
28 n
-J
u
02 n
-J
u
06 l
-J
u
10 l
-J
u
14 l
-J
u
18 l
-J
u
22 l
-J
u
26 l
-J
u
30 l
-J
03 ul
-A
07 ug
-A
11 ug
-A
15 ug
-A
20 ug
-A
24 ug
-A
28 ug
-A
01 ug
-S
05 ep
-S
09 ep
-S
13 ep
-S
17 ep
-S
ep
TEUS
CONTAINERS ON HAND (IN TEUs): CONTAINER TERMINAL MAIN TERMINAL
28/2/2008 - 21/9/2008
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
Import full
Export full
Empties
TRM
Total
Holding Capacity (7500)
37
6.0
CHALLENGES
6.1
Creating port capacity ahead of demand.
6.2
To handle the increasing general cargo, bulk cargo
and container traffic.
6.3
Coordination with inland transport modes through
business corridors to achieve high utilization of
available capacity and seamless transfer of cargo along
the entire logistic chain.
6.4
To continue improving port facilities and capacity in
order to handle efficiently the increasing traffic.
38
6.5
Inter-connectivity and cooperation with other ports to
face challenges of traffic increase.
6.6
Setting up a good port community system with the
challenge of promoting port efficiency, cost
effectiveness and marketing. The Port Community
system entails exchange of information on cargo and
vessels among stakeholders. This will also involve
information on port related activities such as booking
of wagons.
6.7
To improve security and safety of people, cargo, port
facilities and vessels in accordance with ISPS code.
39
7.8
To continue creating a productive and motivated
workforce and manage the intellect created in the
workforce.
7.9
To complete and implement the Port Master Plan
study.
40
THANK YOU
FOR
YOUR ATTENTION