Transcript Document

Presentation
on
Kaladan Multimodal Transit
Transport Project
(Port & IWT component)
23rd February 2011
1
•Aizawl
•I
N
D
I A
•B A N G L A D E S H
N
D
• ROAD IN INDIA
•I
I A
•Lawngtlai
•Myeikwa
(IM Border)
•Paletwa
Ch. 158 Km
ROAD
IN
MYANMAR
•Kaletwa
(Ch 225 km
•Myanmar
•Kyauktaw
DISTANCES
Sittwe
539 km
Sittwe
Paletwa
158 km
Paletwa
Kaletwa
67 km
Kaletwa
Myeikwa (IM Border)
62 km
Myeikwa
(IM Border)
Lawngtlai
Lawngtlai
100 km
Aizawl
334 km
IWT
Kolkata
•Bay of Bengal
Kaladan Multimodal Transit Transport System
•Sittwe
Ch. 0.0 km
Project Implementation Framework
• MEA is the nodal agency on Indian side – Ministry of
Foreign Affairs on Myanmar side
• Framework Agreement and two Protocols (Protocol on
Transit Transport and Protocol on maintenance) signed on
2nd April 2008
• Article-4 of the Framework Agreement provides for
appointment of a Project Development Consultant (PDC)
• IWAI is the Project Development Consultant (PDC) vide
Agreement dated 19.3.2009 with MEA
3
Project Details .…an overview
•
Piloted and funded by MEA .
•
Based on DPR prepared by RITES in 2003.
•
Project area entirely in Myanmar.
•
Transport infrastructure components planned originally
•
Port/IWT development between Sittwe and
along Kaladan river
•
Road form Kaletwa to Indo-Myanmar border(Mizoram)
Kaletwa
4
Responsibilities of PDC
• Preparation for selection of main contractor for Port & IWT
components (Agency to execute Road component to be
selected by MEA)
• Construction supervision and overall project management .
• Co-ordination / Liaison between nodal agencies and
contractors
5
Project details ….. an overview
Components (Original DPR)
 Fairway development/ Sea-dredging in Sittwe port area
 Construction of Port/IWT terminals at Sittwe
 Fairway development/Dredging on Sittwe - Kaletwa stretch
of Kaladan river( 225 Km)
 Construction of IWT Terminal at Kaletwa
 Construction of 10 IWT vessels (260 ton each)
 Highway (62 kms) from Kaletwa to Indo-Myanmar Border.
6
Project Components …post review
 Fairway development/ Sea-dredging in Sittwe port area
 Construction of Port/IWT terminals at Sittwe
 Fairway development/Dredging on Sittwe - Paletwa stretch
of Kaladan river (158 Km)
 Construction of IWT Terminal at Paletwa
 Construction of 6 IWT vessels (300 ton each)
 Highway (129 kms) from Paletwa to Indo-Myanmar Border.
7
Transit Route (Modified)
Stretch
Mode
Distance
(in km)
Sea route
539
Sittwe- Paletwa*
IWT (Kaladan)
158
Paletwa-KaletwaIndo Myanmar
border*
Road
129
Total
826
Kolkata- Sittwe
* Post DPR review
8
Project cost (Awarded) for Port & IWT component
Sl.no.
Description
Amount in Rs(Cr.)
1
Dredging Access Channel and Port Basin at Sittwe
78.26
2
Construction of rubble mounted Dyke at Sittwe for
reclamation area.
11.31
3
Dredging of Navigational Channel along the River upto
Paletwa .
10.42
4
Navigational Aids
1.75
5
Port at Sittwe (Civil Works & Handling Equipments)
134.49
6
IWT Terminal at Sittwe (Civil Works & Handling Equipments)
30.32
7
IWT Terminal at Paletwa (Civil Works & Handling
Equipments).
23.42
8
Design, Construction and Supply of 6 nos. 300 T. cargo
vessels.
52.44
Total for Port & IWT development up to Paletwa
342.41
9
Progress made
•
MEA issued Letter of Acceptance(LoA) to Essar Projects
India Ltd. on 12 April 2010 at a cost of ` 342 Crores.
•
Agreement between MEA and Contractor signed on
14.05.2010 and Letter of Commencement (LoC) issued
on 9. 6.2010.
•
Port & IWT works to be implemented in 36 months.
•
Government of Myanmar has provided land for setting up
contractor’s camp and land for construction at Sittwe
during September 2010. Clearances / permissions for
import of construction equipments & Materials as well as
for opening of bank account has been received by the
Contractor during October 2010.
10
Progress made… contd.
•
Contractor has mobilised Men and Materials to the site
and construction work started in December 2010.
•
Consequent to relocation of terminal to Paletwa , a fresh
DPR for New road section between Paletwa and Kaletwa
is to be prepared.
•
MEA has appointed M/s IRCON Infrastructure & Services
Ltd . as the agency for preparing the D.P.R. for the new
road section.
11
Progress made… contd.
•
Construction activity at Sittwe started in December 2010.
•
Preparation of detailed design & working drawings by the
Contractor is in progress .
•
Site office has been established at Sittwe in the space
provided by Govt. of Myanmar.
12
Implementation Schedule (PORT & IWT)
13
Important issues
•
MEA to finalize arrangements for construction of the
highway link from IWT terminal at Paletwa to the IndoMyanmar border.
•
Necessary land at Paletwa is to be allotted by Govt. of
Myanmar for construction of IWT Terminal. Requirement of
land identified and submitted to Govt. of Myanmar by IWAI
in February 2011.
14
Thank you
15