Concrete Structures - An-Najah National University

Download Report

Transcript Concrete Structures - An-Najah National University

Concrete Structures
DR. Nabil Dmaidi
Units of Measure
Concrete
:
Cubic Yard
Steel
:
Lb or tons
Formwork :
Square feet per contact area
DR. Nabil Dmaidi
Types of Concrete construction
1.
Foundations
2.
Columns
3.
Slabs and beams
DR. Nabil Dmaidi
Foundations
Isolated
footing
Combined
footing
Shallow
Deep
Strap
footing
Wall
footing
DR. Nabil Dmaidi
Raft
foundation
Shallow Foundation
Isolated
Footing
Combined
Footing
Strap
Footing
Raft
Foundation
DR. Nabil Dmaidi
Continuous
Wall Footing
Deep Foundation
Caissons
Piles
DR. Nabil Dmaidi
Columns

Shapes
–
–

Square - Rectangle - Circular
Others
Reinforcement
–
Ordinary - Spiral
DR. Nabil Dmaidi
Slabs and Beams: One-Way slabs
One-Way Slab, Beam, and Girder
One-Way Slab, Supported
by Beams or Walls
One-Way Joist Slab
DR. Nabil Dmaidi
Slabs and Beams: Two-Way Slabs
Flat Plate
Waffle Slab
Flat Slab
Two-Way Slab
Supported by Beams
DR. Nabil Dmaidi
Estimating Issues
1.Formwork is the largest cost item that
represents 40% to 60% of concrete structure
cost.
Distribution of costs for cast-in-place concrete slab wall:
Slab
Concret e
21%
Reinforcing
28%
Concret e
Placing
3%
Wall
Concret e
Mat erials
30%
formwork
Mat erials
10%
Formwork
Labor
38%
DR. Nabil Dmaidi
Formwork
Labor
52%
Concret e
Labor
7%
Formwork
Mat erials
11%
2.Waste allowance from 2% to 10% should be
added for concrete and concrete formwork.
DR. Nabil Dmaidi
1. Center Line Method
30’10”
30’
Building size: 30’ x 40’
40’0”
40’10”
Calculations:
1. Length = 30’10” - 1’6”
= 29’4”
2. Width = 40’10” - 1’6”
= 39’4”
3. Perimeter = 29’4” + 29’4” + 39’4” +39’4”
= 137”4”
4. Volume of concrete = 137.33’ x 1’ x 1.5’ = 206 ft3
DR. Nabil Dmaidi
2. Sectional Method
Calculations:
1.Length = 10.833’+40.833’ = 81.67’
2.Width
= 27.833’+27.833’ = 55.67’
3.Perimeter
= 81.67’+55.67’
= 137.34 Total Linear ft
4.Volume = 137.34’x1’x1.5’ = 206 Cubic feet
= 7.6 Cubic Yards
30’10”
27’10”
5.volume in CY = 206/27
40’10”
DR. Nabil Dmaidi
COST OF OTHER COMPONENTS OF
CONCRETE WORK
1.Reinforcement Steel
2.Forms
3.Concrete Mix
4.Finishing
5.Curing
DR. Nabil Dmaidi
Table 1.
DIMENSIONS & WEIGHT OF WELDED WIRE FABRIC
SPACING
WIRE GAUGE
POUNDS/100 SF
4" X12"
NO. 6 XNO. 6
41.6
4" X12"
NO. 8 XNO. 8
29.6
6" X12"
NO. 4 XNO. 4
43.8
6" X12"
NO. 6 XNO. 6
31.8
6~ X6"
NO. 6 XNO. 6
42.8
6" X6"
NO. 8 XNO. 8
30.0
6" X6"
NO. 9 XNO. 9
25.8
6" X6"
NO. 10 XNO. 10
20.7
4" X4"
NO. 6 XNO. 6
61.9
4" X4"
NO. 8 XNO. 8
44.1
DR. Nabil Dmaidi
Table 2
SIZES & WEIGHTS OF REINFORCING BAR
BAR NUMBER
SIZE (IN.)
WEIGHT (LB./FT.)
2
3
1/4 ROUND
3/8 ROUND
0.167
0.367
4
5
6
1/2 ROUND
5/8 ROUND
3/4 ROUND
0.668
1.043
1.502
7
8
7/8 ROUND
1ROUND
1SQUARE
1- 1/8 SQUARE
1- 1/4 SQUARE
2.044
2.670
3.400
4.303
5.313
9
10
11
DR. Nabil Dmaidi
EXAMPLE:
How many pounds of rebar are required for the
concrete floor area below?
6” Concrete slab with #4 rebar 15”
on center each way
40’
20’
60’
30’
DR. Nabil Dmaidi
Step #1: Calculate the total SF of area involved.
20'0" X 30'0"
= 600 SF
30'0" X 40'0"
= 1 200 SF
Total
= 1,800 SF floor area
Step #2: Calculate the pounds of rebar per SF of floor based on the unit
spacing of the rebar at any point of intersection.
Unit area:
15" X 15"
= 1.25' X 1.25'
= 1.56 SF
Unit rebar length: 1.25' + 1.25'
= 2.5 LF
Lbs. of rebar/unit:= 2.5 LF X .668 lbs/ LF = 1.67 lbs
It is now known that there are 1. 67 lbs of rebar per 1.56 SQ FT of floor
area.
1.67 / 1.56
= 1.07 lbs/SF of floor area.
SO: 1.07 lbs/ SF X 1,800 SF
= 1,926 lbs of #4 rebar required.

DR. Nabil Dmaidi