Transcript Slide 1

Injector/BC1 Commissioning
(Dec. 1, ’06 through Aug. 1, ‘07)
P. Emma
LCLS FAC Meeting
Accelerator Systems Breakout
April 20, 2006
LCLS
April 20, 2006
Injector/BC1 Commissioning
1
Paul Emma
[email protected]
LCLS Accelerator Schematic and Time Frames
6 MeV
z  0.83 mm
  0.05 %
4.30 GeV
z  0.022 mm
  0.71 %
13.6 GeV
z  0.022 mm
  0.01 %
Linac-X
L =0.6 m
rf= -160
Linac-0
L =6 m
rf
gun
250 MeV
z  0.19 mm
  1.6 %
135 MeV
z  0.83 mm
  0.10 %
Linac-1
L 9 m
rf  -25°
...existing
linac
21-1
b,c,d
DL1
L 12 m
R56 0
Linac-2
L 330 m
rf  -41°
Linac-3
L 550 m
rf  0°
21-3b
24-6d
25-1a
30-8c
X
BC1
L 6 m
R56 -39 mm
Commission in Jan. 2007
BC2
L 22 m
R56 -25 mm
Commission in Jan. 2008
SLAC linac tunnel
April 20, 2006
Injector/BC1 Commissioning
2
undulator
L =130 m
DL2
L =275 m
R56  0
research yard
Paul Emma
[email protected]
Machine Commissioning Plans
Schedule developed in MS-Project
One file/manager per system
Link to milestones and events in Master file
install
Dec.
‘05
Injector-BC1
Sep.
‘07
Aug. Dec.
‘06
‘06
April 20, 2006
Injector/BC1 Commissioning
install
3
BC2
Dec.
‘07
LTU-und.
Mar.
‘08
Paul Emma
[email protected]
April 20, 2006
Injector/BC1 Commissioning
4
Paul Emma
[email protected]
Injector Through BC1 Commissioning
no laser-heater
gex,y
RF
deflector
April 20, 2006
Injector/BC1 Commissioning
and slice
5
E
E
Paul Emma
[email protected]
Injector Through BC1 Commissioning (2)
relative
bunch length
monitors
BC1
E
X-band
RF
April 20, 2006
Injector/BC1 Commissioning
E
slice gey
6
gex,y
stopper
Paul Emma
[email protected]
Many Measurement Simulations Done
L1-Linac RF Phasing
Slice Emittance Measurement
20-mm res. BC1 BPM
= meas. sim.
= calc.
= y distribution
= actual
DL1 slice-emit on WS02
L1 RF phase
Linac-1 RF phase scan
(X-band off, BC1 bends at 295 MeV)
rf
gun
set phase to -25˚0.5˚
Linac-1
21-1b
21-1d
X
April 20, 2006
Injector/BC1 Commissioning
7
Paul Emma
[email protected]
LCLS Drive-Laser Commissioning
8-Hour Cycle (5 days/week, 8/1/06 to 12/1/06, 16 total weeks)
DAY SHIFT (8:00-16:00)
W. White, J. Castro,
D. Dowell, S. Gilevich,
H. Loos, S. Peng (as needed)
Also available:
P. Emma,
P. Krejcik,
C. Limborg,
J. Schmerge,
et al.
SWING SHIFT (16:00-24:00)
(none)
OWL SHIFT (0:00-8:00)
(none)
(see W. White)
April 20, 2006
Injector/BC1 Commissioning
8
Paul Emma
[email protected]
LCLS Injector/BC1 Commissioning
24-Hour Cycle (7 days/week, 12/1/06 to 8/1/07, 32 total weeks)
DAY SHIFT (8:00-16:00)
1 lead physicist, 1 physicist,
1 controls eng., 1 sys. engineer,
1 LCLS operator, 1 laser operator
SWING SHIFT (16:00-24:00)
1 lead physicist, 1 physicist,
1 LCLS operator, 1 laser operator
OWL SHIFT (0:00-8:00)
1 LCLS operator, 1 operator,
1 laser operator
April 20, 2006
Injector/BC1 Commissioning
9
Paul Emma
[email protected]
Personnel Available for LCLS Injector/BC1 Commissioning
Shift Leaders (initially)
(1 per D/S shift)
1. Dave Dowell
2. Paul Emma
3. Patrick Krejcik
4. Cecile Limborg
5. Bill White
LCLS Physicists
(1 per D/S shift)
1. Sasha Gilevich
2. Henrik Loos
3. Heinz-Dieter Nuhn
4. John Schmerge
5. Dave Schultz
6. Jim Welch
7. Juhao Wu
Laser Operators
Controls eng.
(1 per DAY shift)
1. Stephanie Allison
2. Mike Zelazney
3. Debbie Rogind
4. Diane Fairley
5. Stephen Norem
6. Arturo Alarcon
7. Doug Murray
8. Sergei Chevtsov
9. Karen Kotturi
10. Kristi Luchini
11. Sheng Peng
12. Stephen Schuh
13. Till Straumann
Operations
(1 per DAY & SWING
shift and 2 per OWL)
Visitors ?
April 20, 2006
Injector/BC1 Commissioning
10
Sys. Engineers
(1 per DAY shift)
1. Eric Bong
2. Carl Rago
3. Leif Eriksson
4. Richard F. Boyce
5. Jose Chan
6. Tim Montagne
7. Paul Bellomo
8. Antonio de Lira
9. Dave MacNair
Accelerator, ILC, SSRL
1. Franz-Josef Decker
2. Jim Turner
3. Rick Iverson
4. Doug McCormick
5. Joe Frisch
6. Marc Ross
7. Jeff Corbett
8. James Safranek
Paul Emma
[email protected]
Man-Power Requirements (12/1/06 – 8/1/07)
32 weeks total (12/1/06 to 8/1/07, minus 2 weeks)
80% coverage (downtime)
14 lead-physicist shifts/week
14 physicist shifts/week
7 controls eng. shifts/week
7 sys. engineer shifts/week
21 laser operator shifts/week
(28 operator shifts/week)
Average of 2.8 shifts/week for each lead physicist
Average of 2.0 shifts/week for each physicist
Average of 0.5 shifts/week for each controls eng.
Average of 0.8 shifts/week for each sys. engineer
Average of 4-5 shifts/week for each laser operator
(32 weeks)(214 + 27 + 21)(80%)  1600 man-shifts =
12900 man-hours  6.5 man-years (+ 2.9 from op’s)
April 20, 2006
Injector/BC1 Commissioning
11
Paul Emma
[email protected]
LCLS Commissioning Parameters
Parameter
Value
Comments
RF rate
30 Hz
30 Hz in linac (possible short-term 120 Hz linac rate
in L0-BC1 for feedback tests, etc) - 120 Hz in gun for
short time to verify full rate
Beam rate
≤30 Hz
30 Hz e- beam as baseline – possible 120-Hz tests in
L0-BC1 for short term verification of feedback, etc
Drive-laser rate
120 Hz
120-Hz all the times – pulse-picker provides e- rate
as required above
200-500 pC
200-500 pC, depending on QE and diagnostics short spans at 10 pC – later in ’07 we explore 1-nC
Drive-laser pulse length 10 ps fwhm
10 ps fwhm startup with possibility of 6-ps at 0.2 nC
later – early laser tests may provide path to more
convenient pulse-length changes
Gun gradient
120 MV/m, although 110 MV/m is adequate in ‘07
Bunch charge
April 20, 2006
Injector/BC1 Commissioning
120 MV/m
12
Paul Emma
[email protected]
Issues
Controls will be mixed (SLC & epics) and
capabilities may be limited initially
Most High-Level Applications (emittance,
bunch length, feedback) must done through
MATLAB as a temporary solution
Most LCLS physicists not yet experienced in
SLAC control room with SLC controls
Help from operations group will be needed
April 20, 2006
Injector/BC1 Commissioning
13
Paul Emma
[email protected]