Transcript Slide 1

Connecting small
renewable energy
generators to the grid in
Thailand:
case studies & technical
requirements
Renewable Energy Forum
Thursday, 28 October 2004
BITEC Bangna, Bangkok
Chris Greacen
Palang Thai
www.palangthai.org
Outline
• Very Small Power Producer (VSPP)
examples
– Solar
– Wind
– Biogas
• Technical requirements for interconnection
VSPP
Grid interconnection of small
scale renewable energy
Reduces air and water pollution
Biogas from
Pig Farms
Produces fertilizer
Produces electricity
Biogas from Pig
Farms
As of Jan 2004: 4 farms legally
connected
Potential for hundreds of farms
Grid
interconnection
at pig farm
100 kW Wind turbine
• Part of environmental
training center
• ReCycle Engineering, Chonburi
ReCycle Engineering
Community
micro-hydro
• Mae Kam Pong village,
Chiang Mai
• 40 kW
• Community cooperative
• Expected gross
revenues: 30,000
baht/month
40 kW micro-hydro generator at
Mae Kam Pong
Korat Waste to Energy - biogas
• Uses waste water from cassava
• Removes 99% of COD
• Produces gas for all factory heat + 5 MW
of electricity
Korat Waste to Energy - biogas
• 3 x 1 MW Jenbacher gas generators
Technical requirements – why?
• Utility is responsible for ensuring reliable,
safe electricity for customers. Safety for
workers.
• System designed for one-way flow of
electricity.
• …but should also not impose
unreasonable costs or other barriers to
interconnection
Technical requirements – what?
• Must not island
• Voltage (PEA):
19.8kV – 24.2kV (nominal = 22 kV)
• Frequency:
50 Hz +/- 0.5. Disconnect within 0.1 sec
• Power factor:
>0.85
(This list not complete.)
Technical requirements – relays
•
•
•
•
•
•
59/27
50/51, 50N/51N
59N
67/67N
81
25
Overvoltage and undervoltage
Phase & ground overcurrent
Zero sequence overvoltage
Directional & gnd overcurrent
Over/under frequency
Synchronizing check
Integrated digital relay
BE1-GPS100
BASLER ELECTRIC
www.basler.com
BECKWITH ELECTRIC
www.beckwithelectric.com
Typical interconnection with
integrated relay
Resources for VSPP
www.netmeter.org
• VSPP regulations (Thai)
http://www.netmeter.org/th/regs/docs/VSPP_regulation.pdf
• Interconnection application form
http://www.netmeter.org/th/regs/docs/connection_form.pdf
• Sample tariff calculations
http://www.palangthai.org/en/docs/SampleTariffCalculation-new.xls
For more information
Contact:
Tel. 02-674-2533
[email protected]
www.palangthai.org
Aggregate Net Metering
M
meter
Utility’s responsibility
Village’s responsibility
• Village is metered as a single customer
• Collection of tariffs from individual households and
maintenance of local lines is the responsibility of the
REE.
Objectives of Power Purchase from
VSPPs
• To promote efficient use of domestic natural
resources and reduce dependency on the use of
commercial fuels
• To open up an opportunity for remote areas to
participate in electricity generation
• To alleviate the government’s budgetary burden
to invest in electricity generation and distribution
systems
Applications received
(as of 20 Jan 2004)
MEA
PEA
# of projects
kW
# of projects
kW
Solar PV
25
71.1
5
15.4
Biogas
1
1048
6
>750
Biomass
0
0
4
5000
Total
26
1119.1
15
>5765
Contracts signed
(as of 20 Jan 2004)
MEA
PEA
# of projects
kW
# of projects
kW
Solar PV
0
0
1
3.1
Biogas
0
0
4
?
Biomass
0
0
3
4000
Total
0
0
8
>4000
Sticking points…
• Expensive interconnection requirements
• VAT tax issue unresolved
• Concession by Department of Energy
Business, Ministry of Energy
• Lack of awareness among potential
customer generators
Today's
Central Utility
Central Generation
Tomorrow's
Distributed Utility?
Central Generation
Wind
Remote
Loads
Genset
Fuel Cell
Customers
Customer
Efficiency
© Distributed Utility Associates, Used with Permission
Battery
PV
28