Service Presentation title
Download
Report
Transcript Service Presentation title
eDEP Contractual aspects
Mohamed ELLEJMI
June 2008
European
Organisation for the Safety of Air Navigation
1
Contents
2
Previous Contract
Current contract
2008 developments
Budget
Processes
Previous Contract
eDEP Core contract (2006 – 2007)
Maintenance service (EEC/RIF funded : 89K/2007 and 62k/2006)
RIF/EEC sponsored developments (EEC/RIF funded : 248K/2007 and
114k/2006)
APT sponsored developments (paid for by APT : 215K/2007 and 62K/2006)
AVT sponsored developments (paid for by AVT : 22K in 2007 and 5k in 2006)
STORIA included in this contract
“MTV” separate Contract TRS A14-2005 (197K in 2006/2007)
Private treaty for the ITWP connection to TwoSim 3D simulator (94K
in 2007)
3
2006/2007 : investment of 1 million for three projects
EEC/RIF Contract
Maintenance Service
1st Level support service
Ad-hoc tasks
Setting up demos, experiments
Investigating issues on-site
2nd Level
4
Bug fixing in previously released software
delivery service
support service
Actually only 3 deliveries per year
Fixed price
Merging of all development lines, non-regression testing, correction of
found bugs (due to the developments)
Delivery on-site into CM Synergy
Maintenance Report (delivery contents, test results)
Perfective maintenance
Current Contract
EEC/RIF
CNS
5
Integrated Tower Position (Stephane Dubisson)
FASTI
AVT project (Leo Van der Hoorn)
APT
ESCAPE: AEG/TCT/STORIA
Perfective Maintenance
Support
TCT and FASTI Demonstrator (Chris Brain, Bogdan Petricel,
Christopher Costelloe)
EHQ/DAS
CIMACT (Alain Fowler, Jan Scholz)
What’s New in 2008
Maintenance Improvement:
Perfective Maintenance
6
Simplification of test documentation and alignment with eDEP SRD
Automated test
TCT in ESCAPE
New eDEP Launching interface
Map editor
PWP development
Budget 2008/2009
For 2008:
Maintenance: 108k
ERS : 146K
CIMACT: 136 K
AVT: 11k
APT: 150k
FASTI: 120k
RST ?
Total 671K+ ? for 2008
7
For 2009: need to raise a new contract
Development Process
All developments have a Work Plan. The work plan defines
8
The requirement
The proposed architecture changes
The test strategy
Detailed design issues if needed
Proposed documentation updates
Developments fit in with the client need and client timescales
(need to be flexible and client oriented)
merges parallel development lines as needed during the
delivery to EEC
Configuration Management
Master database (in Graffica premises at Malvern
Backup database in EEC/RIF Configuration Management (CM
Synergy)
9
CVS based
Bretigny developers use this Malvern database (via remote link)
Perfectly integrated into Eclipse
Re-synchronised every 4 months as part of delivery process
One exception : AEG (ACE eDEP Gateway) – which is developed under
Configuration Management CM Synergy
Contract Concepts
EEC/RIF contracts are based upon the “Phased Tasking”
model
Tasks are broken down into 3 categories
10
Initial Tasks
Optional Tasks
Future Tasks
Contract Concepts
Initial Tasks
Optional tasks
11
EUROCONTROL provides a detailed task specification
Bidders provide a fixed, non-reversible price
Task is implicitly ordered at contract signature
EUROCONTROL provides a detailed task specification
Bidders provide a fixed, non-reversible price
Task is not implicitly ordered at contract signature.
EUROCONTROL at some point during the contract may raise this task
(no change to specification, no change to price)
Contract Concepts
Future Tasks
EUROCONTROL provides a rough outline of the task
EUROCONTROL provides guidance and/or historical data
Bidder provides
12
A Cost envelope for the future task
A Costing Model for the future task
Task is not implicitly ordered at contract signature.
During the contract, EUROCONTROL may raise the task, providing at
that moment a detailed task specification
The supplier analyses the detailed specification, and calculates a fixed
non-reversible price, using the previously agreed costing model
Contract Concepts
Future Tasks : Cost Envelope
13
Bidders estimate a cost envelope (with some margin) to cover this task
Given the EUROCONTROL task definition is “rough” then obviously the
bidder cost envelope is “rough”
Estimating a large cost envelope is not necessarily bad
(the costing model is more important)
For a bid, all the future task cost envelopes are added-up to give a total
contract envelope. This is considered as the “potential to spend”
2008/2009 Envelope: 989 K€
Contract Concepts
Future Tasks : Costing Model
The Costing Model explains how the supplier shall compute the real
cost of a future task, once EUROCONTROL provides a real and
detailed specification
Costing models vary from simple to complex.
Typically, a complex costing model defines
14
Effort profiles : e.g. a typical s/w development would be
12% Design+TestPlan, 30% development, 10% test, 20% support to
Integration,…
Overheads : e.g. 10% project management overhead, 4% Quality
Staff Profiles /Costs:
Project Manager (620€/day), Senior Engineer(560€/d), Junior
Engineer(520€/d)
Effort/Staff relationship:
e.g. 80% of Design/Test is done by Senior Engineer
Contract Execution
The contract is signed for a
Committed amount
Total of Initial Tasks (ordered implicitly at contract start)
Maximum Contract value which is
Total of initial tasks
Total of optional tasks
Total of future tasks
Initial Task 1
Optional Task 2
Future Task 3
Future Task 4
Future Task 5
15
Contract Execution
During the contract, Optional tasks may be activated
No change to specification
No change to price.
Committed contract value increases, remaining within the overall
maximum amount.
Initial Task 1
Optional Task 2
Future Task 3
Future Task 4
Future Task 5
16
Contract Execution
During the contract, Future tasks may be activated
EUROCONTROL provides a detailed specification
Supplier provides a technical response
Once approved, supplier provides a financial response (using the Costing Model)
The real cost may vary from the original “guess” given in the CFT response (this is
natural)
However, the new committed contract value must remain within the overall contract
maximum value.
Initial Task 1
Optional Task 2
Future Task 3
Future Task 4
Future Task 5
17
18
Core code sharing
19
AVT
ITWP
CIMACT
LARA
FASTI
Core
90% core
30% core
80% core
30% core
90% core
100% core