IDGCC technology outline development status exploration

Download Report

Transcript IDGCC technology outline development status exploration

Gasification Technology for Brown Coal
Power Generation
Terry Johnson
HRL Developments Pty Ltd
APP Brown Coal Best Practice Workshop
Melbourne, June 2008
1
Issues for Brown Coal Power
• Brown coal in Latrobe Valley:
–
–
–
–
Large resource (>100,000 Mt)
Low level of impurities (ash <4%, sulphur <0.5%)
Low cost (<$0.60 per GJ)
Low emissions of pollutants (NOx, SOx, trace elements)
• BUT
– High moisture content (60+%), leads to
– Low efficiency, down by ~20% c.f. black coal
– High CO2 emissions, up by ~20% c.f. black coal
• Hence need for new lower CO2 emissions
technologies such as gasification combined
cycle
2
Current Latrobe Valley Steam Cycle Technology
Energy used to evaporate coal moisture is
lost as steam in the flue gas  chimney.
3
Efficiency Improvement - Drying
Efficient coal pre-drying - reduced moisture gives
higher efficiency and lower CO2
1.4
1.2
1
0.8
Efficiency
CO2 kg/kWh
0.6
0.4
0.2
0
5
20
35
50
Coal Moisture Content, % wb
65
4
Types of Coal Gasifiers
•
Fluidised bed: suitable for high reactivity coals - operates at low
temperature (800-900 degC), dry ash removal, can be air blown
•
Entrained flow: suitable for lower reactivity coals - operates at high
temperature, molten ash removal, usually O2 blown
5
IDGCC – Future for Brown Coal
• IDGCC is a technology that supports the future of
brown coal in a carbon-constrained world:
– Increased efficiency and 30% lower CO2 emissions than
current best Latrobe Valley
– Lower cost of electricity production
– Lower water consumption, 50% of steam cycle plant
– Potential for v. low CO2 emissions using CCS, at lower cost
than other technologies
6
IDGCC Technology
Integrated Drying Gasification Combined Cycle (IDGCC)
• Coal is dried using direct contact with hot gas
• Dried coal is converted to hot combustible gas in a
fluidised bed gasifier
• Hot gas is cooled by the coal drying step
• Gas is cleaned, burned in a gas turbine producing power
• Hot exhaust gas from gas turbine used in boiler to produce
steam
• Steam used in a steam turbine to produce extra power
• Gas turbine plus steam turbine - combined cycle
7
IDGCC Process
COOLED GAS
AND GAS COOLING
CYCLONE
NITROGEN
COMBUSTOR
DUST
FILTER
COAL
PRESSURISATION
LOCKHOPPER
STEAM
STEAM
TURBINE
ALTERNATOR
TURBINE
AIR
DRIED
ASH/ CHAR
COAL
COMPRESSOR
AIR
BUFFER / WEIGHING
HOPPER
TO STACK
CLEANED
GAS
BOILER
COAL DRYING
CONDENSER
WATER PUMP
EXHAUST GASES
AIR
STEAM
TURBINE
CO2
ASH/ CHAR
HEAT
HOT GAS
GAS
TURBINE
DRYER
GASIFIER
RECOVERY
CLEANING
8
Development of IDGCC Technology
TGA (1990)
CGDU (1992)
Reactivity tests
Dry coal gasification,
gas flared
CGDF (1996)
Wet coal gasification and
power generation
9
IDGCC Proven at
10-MW Scale
• Wet coal drying,
gasification and
power generation
• Power sent to grid
• 10-MW scale
10
Advantages of IDGCC Technology
• Particularly suited to reactive, wet coals
• Cost reductions of around 30% on boiler technology, wet
coals
• Efficiency at around 40% HHV (from gas turbine/steam
turbine) compared with 33% for supercritical boiler plant
• Significant reduction in CO2 emissions around 30%
compared with current best Latrobe Valley boiler plant
• Savings on water - IDGCC uses only 50% of usual cooling
water levels of boiler plant
• Suitable for pre-combustion CO2 capture for lower CO2
emissions in future
11
CO2 Emissions
1.60
1.40
CO2 Emissions, t/MWh sent out
1.20
1.00
0.80
0.60
0.40
0.20
0.00
Hazelwood
Yallourn
Loy Yang A
Brown Coal
Supercritical
Black Coal
Supercritical
Proposed
IDGCC
IDGCC w. CO2
Capture
12
Water Consumption
Cooling Water Consumption Rates of Latrobe Valley Power Stations
Cooling Water Consumption Rate, t/MWh sent out
3.00
2.50
2.00
1.50
1.00
0.50
0.00
Hazelwood
Yallourn
Loy Yang A
Proposed IDGCC
Proposed IDGCC
with Dry Cooling
13
Costs including CO2 Capture
Indicative Cost of Electricity for Different Technologies
140.00
Range for Nuclear Cost
Extra cost due to CO2 Capture
120.00
LRMC
Electricity cost, $/MWh
100.00
80.00
60.00
40.00
20.00
0.00
IDGCC
Brown Coal SC
Black Coal SC
IGCC
Natural Gas
Nuclear
14
IDGCC Next Steps
500 MW IDGCC Demonstration Project
2 gasifiers supplying Gas Turbine Combined Cycle
Proposed location Latrobe Valley
Gasifier
COAL
Gasifier
500
MW
GTCC
NATURAL GAS
Start- up & supplementary fuel
15
500 MW IDGCC Demonstration Project Structure
•
Funding will be a mix of equity, debt and government
support
•
State Government grant ($50M) announced November
2006
•
Federal Government grant ($100M) announced March
2007
•
HRL and Harbin Group in Joint Venture
– Harbin to be EPC Contractor
– Will engage local constructor for site erection
•
Planned start of operation early 2012
16
500 MW Project Outcomes
• Provide 500 MW combined cycle power into Grid
• Demonstrate 500 MW IDGCC power at Greenhouse Intensity
of about 0.8 tCO2/MWh
• Confirm low fuel use, low water consumption compared to
current LV power plant
• Prove scale up for commercial operation of IDGCC
• Provide the platform for commercial deployment of low
greenhouse power at cost of about $39/MWh
17
CO2 Capture
• IDGCC is suitable for pre-combustion CO2 capture with
systems already used commercially in other industries
• Additional cost is high ~45% increase in capex
• Penalty on power output ~10%
• Cost of CO2 capture lower for IDGCC than other power
technologies
• Working with CO2CRC to evaluate improved solvent
systems more suited to IDGCC, with support from Victorian
ETIS program
• HRL’s aim is to move towards near-zero CO2 from IDGCC in
future with CCS (believe we can get CO2 emissions down
close to 0.2 t/MWh)
18