Seams PresentationOPSI Annual MeetingRaleigh, NCOctober 7

Download Report

Transcript Seams PresentationOPSI Annual MeetingRaleigh, NCOctober 7

Seams Presentation
OPSI Annual Meeting
Raleigh, NC
October 7, 2013
Stan Williams
Director, Compliance & Settlements
PJM Interconnection
www.pjm.com
PJM©2013
PJM-MISO JCM Work Plan
www.pjm.com
2
PJM©2013
RTO Load, LMP and Interchange on July 18th, 2013
180,000
RTO Total LMP
RTO Hourly MW Load (Preliminary)
RTO Load w/ Economic & Emergency DR
RTO Net Actual Interchange
160,000
160,285 MW with Estimated
Demand Response
Emergency DR
158,156 MW
RTO Peak
$465
140,000
$400
120,000
$298
60,000
96,033 MW
RTO Valley
$77
$250
$266
$200
$173
$130
$95
$28
40,000
$232
4,686 MW
PJM neighbors experience capacity
shortage and requested PJM assistance
$300
7,692 MW
100,000
80,000
$500
$74
$78
$101
$52
$100
Average Interchange Increases
64% from HE14 to HE15
$0
20,000
14:40 - Emergency Load Management Implemented
PECO, PPL, ATSI Zones
Cancelled 18:00
1
2
3
4
5
6
7
8
9
10
11
15:00 - Emergency Load Management Implemented
AEP Canton Subzone
Cancelled 18:00
12 13 14
Hour Ending
3
15
16
17
18
19
20
21
PJM capacity
assistance to
neighbors no
longer needed.
Sharp
interchange
increase into
PJM
-$100
22
23
24
PJM©2013
NYISO-PJM Interchange Optimization
The objective of Coordinated
Transaction Scheduling (CTS) is
to improve interchange
scheduling efficiency
$ NYISO
• Increase alignment of energy
scheduling with interface prices
$ $ PJM
33%
• Adds the option for Market
Participants to schedule energy
transactions across the
NYISO/PJM interface using an
interface bid
www.pjm.com
4
PJM©2013
Proposed CTS Implementation Timeline
Final Joint
Stakeholder
Meeting
Benefit
Assessment
TeleConference
NYISO and
PJM FERC
Filing
PJM Stakeholder
Process
NYISO
Stakeholder
Process
www.pjm.com
Independent
NYISO Bidding
Platform MP
Sandbox Testing
Ramp Solution
Implementation
MRC Forward
Price Projection
Performance
Evaluation
FERC
approval
PJM Led Stakeholder Effort
to Establish Price
Performance Expectations
5
Implementation
Independent
PJM Sandbox
Testing
MRC Endorsement Vote
for CTS Implementation
PJM©2013
Future Interchange Optimization Opportunities
• Develop an Interchange Optimization solution for the
MISO/PJM Seam
– Part of the current filed JCM Work Plan
• JCM effort underway with completion targeted for May 2014
• Individual stakeholder process expected to continue until November 2014
• Extend Interchange Optimization to non-market Seams
– How could this be accomplished?
– What time frame should be considered?
www.pjm.com
6
PJM©2013