Despite Order No. 1000
Planning Gaps for (Certain) Merchants
OPSI Annual Meeting 2013
National Grid is a key investor in Clean Line Energy
Partners
National Grid brings extensive experience in building, owning,
and operating large transmission projects in the United States
and overseas
National Grid owns and operates more than 8,600 miles of
transmission in the United States
National Grid joins Clean Line’s existing investors that include
private equity firm ZBI Ventures
2
Clean Line’s projects connect the best wind resources
to demand centers
Clean Line
projects
3
Rock Island will connect western Iowa with PJM 765 kV
system
STATUS
Interconnection
• PJM Merchant Queue positions under study since 2007 -- Collins
Regulatory
• Received FERC negotiated rate approval
• Filed with the Illinois Commerce Commission in Oct 2012
• Iowa Utilities Board Informational Meetings (precursor to filing) Q3-Q4 2013
Converter Stations
• Converter station land options acquired in Illinois and Iowa
• Development agreement with Siemens for HVDC converter stations
Outreach
• Invited 40,000+ residents to 33 open house meetings
Agreements & Partnerships
• MOU with Kiewit for EPC development support
• Siemens as HVDC technology provider
• Preferred supplier agreement with Southwire (IL)
4
Grain Belt Express has reached key milestones
KEY MILESTONES
STATUS
Interconnection
• PJM: System Impact Study underway for 3,500 MW near Sullivan 765 kV
• MISO: Studying 500 MW interconnection near Maywood 345kV [old Palmyra Tap]
• SPP: Completed Criteria 3.5 Studies(No Harm)
Regulatory
• Kansas Corporation Commission granted public utility status in Dec 2011
• Indiana Utility Regulatory Commission granted public utility status in May 2013
Routing
• Proposed Route filed in Kansas in July 2013 – Order expected Nov. 2013
• Developing potential routes in MO and IL and will file for approval and utility
status in 2014
Outreach
• Obtained routing feedback from 2,300 Kansans at public open house meetings
• Granted Franchise Approvals from 16 Missouri counties in study area
• Obtained routing feedback from 1,250 people at public open houses in Missouri
5
Grain Belt Express will deliver wind energy from Kansas
to PJM 765 kV and MISO 345 kV systems
MISO
PJM
SPP
750-mile overhead, direct current (DC) transmission line
$2 billion transmission project that will enable $7 billion of new wind energy investments
1.4 million homes powered per year
6
Order No. 1000
What does Order No. 1000 say about merchants?
Order No. 1000 requires a transmission developer
proposing a merchant transmission project to “provide
adequate information and data to allow public utility
transmission providers in the transmission planning
region to assess the potential reliability and
operational impacts of the merchant transmission
developer’s proposed transmission facilities on other
systems in the region.”
Order No. 1000, FERC Stats. & Regs. ¶ 31,323 at P 164.
8
The Order also says…
As the Commission noted in Order No. 1000, “nothing
in this Final Rule prevents a merchant transmission
developer from voluntarily participating in the regional
transmission planning process (beyond providing the
information and data required above) even if it is not
seeking regional cost allocation for its proposed
transmission project…we encourage them to do so.”
Order No. 1000, FERC Stats. & Regs. ¶ 31,323 at P 165.
9
Compliance Findings…
Unfortunately, the Commission rejected Clean Line’s
requests that jurisdictional transmission providers be
directed to allow transmission developers to submit
merchant transmission projects for full evaluation in
the regional transmission planning process – even if
not seeking cost allocation.
10
To What Effect?
PJM, MISO, and SPP all filed compliance plans which
failed to include a portal in the regional transmission
planning process for merchant developer projects to
be submitted for consideration in the regional
planning process “not for purposes of cost allocation.”
11
Participant-funded Merchant Projects are Still Outside Looking
In…
12
And then, we have another whole area to discuss…
• Merchant transmission development, benefits, multidriver approach and partial cost allocation of
network upgrades…and, maybe merchant projects
themselves.
Any Good Ideas