LRL Standardized Slide Packet

Download Report

Transcript LRL Standardized Slide Packet

The Louisville Engineer District
Military Program Overview
Louisville District
Rick Lotz
Chief, Fort Campbell Support Section
July 31, 2009
BUILDING STRONG
®
The Louisville Engineer District
SALAMONIE
McAlpine Locks
J. EDWARD ROUSH
MISSISSINEWA
CECIL M.
HARDEN
IN
OH
BROOKVILLE
CAGLES
MILL
IL
MONROE
MARKLAND L&D
CLARENCE
J. BROWN
CAESAR CREEK
WEST FORK
MILL CREEK
WILLIAM H. HARSHA
PATOKA
€
T
T
T
CANNELTON McALPINE L&D
KY
NEWBURGH L&D
JOHN T. MYERS
CAVE RUN
TAYLORSVILLE
L&D
Louisville
1
L&D 52
T
2 ROUGH
NOLIN
L&D 53 T
RIVER
BUCKHORN CARR
GREEN
SMITHLAND L&D
CREEK
RIVER
OLMSTED L&D
BARREN RIVER
TENN
Olmsted Locks
2
BUILDING STRONG
®
The Louisville Engineer District
Military Boundaries
Military Program
7 Army
5 Air Force
6 BRAC
3 DOD
3
BUILDING STRONG
®
The Louisville Engineer District
FY09 MILCON Program Projected Execution PY09 &
Prior
Air Force Reserve
2 Project
$15.4M (2.9%)
Army Reserve
22 Projects (Includes 2 MMCR Project)
$247.8M (46.5%)
DOD
8 Projects
$83.2M (15.6%)
Air Force
1 Projects
$14M (2.6%)
Original Program: $507.6M, 37 Projects
Current Program: $533.1M, 46 Projects
Actual FY09 Award: $304.5M, 23 Projects
Army
13 Projects (Includes 2 MMCA Projects
$172.7M (32.4%)
4
BUILDING STRONG
®
The Louisville Engineer District
MP-01 FY09 BRAC Program Projected Execution
PY09 & Prior
Army Reserve
26 Projects
$716.6M (76.9%)
Air Force Reserve
3 Projects
$33.5M (3.6%)
Army
4 Projects
$129.8M (13.9%)
Original Program: $949.6M, 36 Projects
Current Program: $932.5M, 35 Projects
Actual FY09 Award: $324.1M,14 Projects
Air Force
2 Projects
$52.6M (5.6%)
5
BUILDING STRONG
®
The Louisville Engineer District
MP-01 FY09 ARRA Program Projected Execution PY09
Army O&M
19 Projects
$35.5M (25.0%)
Army Reserve FFR
5 Projects
$49.7M (36.4%)
Army F H
1 Project
$0.9M (0.6%)
Army
1 Project
$43.0M (31.5%)
MILCON: Original Program: $51.8M, 5 Projects
MILCON: Current Program: $52.8M, 6 Projects
Actual FY09 Award: $0, 0 Projects
O&M Program: $83.8, 23 Projects
Total Military ARRA Program: $136.6M, 29 Projects
BUILDING STRONG
®
DOD
4 Projects
$8.9M (6.5%)
6
The Louisville Engineer District
ARMY MILCON
Fort Knox
Project
HRCoE
EACI (Wilson Road)
Army Reserve Ctr. (84th ARRTC)
School Age Child Development Center
Aircraft Directional Signage
Child Development Center Connector
100th Div AR Center/Unheated Stor
Family Asst Ctr, Warriors-in-Transition
PA
$206M
$ 6.7M
$ 9.5M
$ 7.4M
$ 1.3M
$ 1.1M
$ 2.4M
$ 65.0M
Award
Oct 08 A
Sep 08 A
Mar 09 A
Jul 09
Sep 09
Sep 09
Apr 10
Mar 10
7
BUILDING STRONG
®
The Louisville Engineer District
Military Work
Bluegrass Army Depot, KY
Project
Energy Optimization Phase 2
PA
Award
3.0 M
Jun 09 A
No other work is currently planned or directed at BGAD for Louisville
District execution at this time.
8
BUILDING STRONG
®
The Louisville Engineer District
ARMY MILCON
Fort Campbell
FY09
Project
Child Development Center (Ages 6-10) *
Unit Operations Fac (Maint) (3 RFPs)*
Unit Operations Fac (Engineer BN) (3 RFPs)*
Training Support Center
Child Development Center (6-10) (Add) *
Elementary School
Troop Medical/Dental Clinic
Warriors-in-Transition Complex (2 RFPs)* +
SOF Equipment Maintenance Fac
Award
May 09 A
Jun 09 A
Mar 09 A
Mar 09 A
Sep 09
Feb 09 A
May 09 A
Aug 09
Mar 09 A
9
* = CoS MATOC / D-B RFP
+ = Economic Stimulus package funded
PA
$ 8.6 M
$47.0 M
$37.0 M
$15.5 M
$10.0M
$21.4 M
$24.0 M
$43.0 M
$15.0 M
BUILDING STRONG
®
The Louisville Engineer District
ARMY MILCON
Fort Campbell
FY10
Project
Med/Dent Clinic Addition
EOD Group HQ/COF * (2 RFP’s)
Armed Forces Reserve Center
PA
Award
$ 8.8 M
$14.8 M
$ 5.9 M
Mar 11
Oct 09
Nov 09
10
BUILDING STRONG
®
The Louisville Engineer District
ARMY MILCON
Fort Campbell
FY11-14
 FY11 – 5 projects @ $148.5 M
 FY12 – 7 projects @ $222.4 M
 FY13 – 7 projects @ $237.5 M
 FY14 – 1 projects @ $109.0 M
Total Fort Campbell, FY 09 - 14 MILCON = $968 M (over $1B
with ARRA Stimulus)
BUILDING STRONG
®
11
The Louisville Engineer District
AIR FORCE MILCON
Wright-Patterson AFB, OH
Scott AFB, IL
FY09-10
Project
FY09
Joint Intelligence Operations Fac, Scott
Pipeline Dorm, WPAFB
Add/Alter Sensors Lab, WPAFB
Security Forces Operations Fac, WPAFB
$14.0 M
$12.6 M
$40.0 M
$14.0 M
Nov 08 A
Dec 08 A
Apr 09 A
Jun 09 A
FY10
Conversion Advance Power Lab, WPAFB
Info Tech Complex, Phase 1, WPAFB
$21.0M
$27.0M
Mar 10
Mar 10
Award
12
* = CoS MATOC / D-B RFP
+ = Economic Stimulus package funded
PA
BUILDING STRONG
®
The Louisville Engineer District
• Upcoming Projects
Russ Boyd (Military) 502.315.6801
Rick Lotz (Fort Campbell) 502.315.6818
Contracts &
Contacts
Contract Opportunities….
• FEDBIZOPS
• S.A.M.E. activities
• Military Installation pr/public events
• Congressional documents
• Presolicitation/advance notice
• Corps-wide Small Business Fairs
• Local Business Fairs
Mike Ryan (Fort Knox) 502.315.6887
Dewey Rissler (Air Force) 502.315.6807
• General Contracting
Mark Yates, 502.315.6172
• Small Business Office
Linda Hunt-Smith, 502.315.6111
• Environmental Contracts
Chris Karem, 502.315.6300
• A/E Contract Process
Sharon Raque 502.315.6247
Gerard Edelen, 502.315.6310
13
BUILDING STRONG
®
The Louisville Engineer District
Contracts
www.fedbizopps.gov
www.fedteds.gov
Search on W912QR%
14
BUILDING STRONG
®
The Louisville Engineer District
Questions???
15
BUILDING STRONG
®
The Louisville Engineer District
Serving our military and the nation
www.lrl.usace.army.mil
16
BUILDING STRONG
®