Transcript Slide 1

City of Bainbridge Island
Eagle Harbor Beach Mains
Replacement 30% Design
Wing Point Country Club
CarolloTemplateWaterWave.pptx
July 15, 2013
Agenda
• Introductions
• Project History
• Project Overview
• Project Schedule
• Project Costs
CarolloTemplateWaterWave.pptx
• Questions and Answers
2
Introductions
• City Staff
– Larry Ward – Project Manager
– Chris Hammer – Engineering Manager
• Carollo Engineers
– Lara Kammereck – Project Manager
– Anh Quach – Project Engineer
• Roth Hill
CarolloTemplateWaterWave.pptx
– Erik Waligorski – Design Manager
• ESA
– Pete Lawson - Permitting
3
CarolloTemplateWaterWave.pptx
PROJECT HISTORY
4
CarolloTemplateWaterWave.pptx
The City of Bainbridge Island has two sewer
service areas serving portions of the island
5
CarolloTemplateWaterWave.pptx
The Winslow sewer service area is
served by the City’s WWTP
Source: 2004 City of Bainbridge Island Comprehensive Plan
6
CarolloTemplateWaterWave.pptx
The South Island service area is served by
Kitsap County Sewer District 7
Kitsap Co. Sewer
District 7 WWTP
Source: 2004 City of Bainbridge Island Comprehensive Plan
7
CarolloTemplateWaterWave.pptx
Wastewater in Winslow conveyed to
WWTP via Hwy 305 and Wing Point PS
8
CarolloTemplateWaterWave.pptx
Treated effluent from the Winslow WWTP
discharges to Puget Sound via a 16-in
diameter force main
9
Force mains have failed several times due to
corrosion triggering replacement
Hwy 305 PS failed spilling
400K gallons sewage into
Puget Sound
Commenced
30% Design
BHC performed
study
Wing Point PS failed 3 times
CarolloTemplateWaterWave.pptx
2003
2009
2011
2012
10
CarolloTemplateWaterWave.pptx
Several alternative routes were evaluated
for the Hwy 305 PS force main
11
CarolloTemplateWaterWave.pptx
Several alternative routes were evaluated
for the Hwy 305 PS force main
12
CarolloTemplateWaterWave.pptx
Several alternative routes were evaluated
for the Wing Point PS force main
13
City recommended alignment along the
beach
• Utilize current Easements
• Repair and Replacement Focus
• Less ROW Improvements
CarolloTemplateWaterWave.pptx
• Less neighbor/traffic disturbance
14
CarolloTemplateWaterWave.pptx
PROJECT OVERVIEW
15
The design project consisted of several
components
• Topographical Survey
• Environmental Permitting
• Biological Assessment
• Critical Areas and Cultural Resources Evaluation
• Geotechnical Exploration
• Trenchless Technologies Analysis
CarolloTemplateWaterWave.pptx
• Easements and Construction Permitting
• 30% Design
16
CarolloTemplateWaterWave.pptx
Design engineers have completed the
30% level design
17
Design Summary
• Hwy 305 FM replaced with ~ 3,370 LF 12-inch HDPE
pipe
• Wing Point FM replaced with ~ 3,860 LF 6-inch
HDPE pipe
CarolloTemplateWaterWave.pptx
• Effluent FM replaced with ~ 3,730 LF 16-inch HDPE
pipe
18
Geotechnical explorations revealed
various constructability issues
• High Water Table (Tidal Influence)
• Need for Buoyancy Calculations
• Dewatering
• Trench Stabilization
CarolloTemplateWaterWave.pptx
• Flowing Sand
19
Several trenchless construction methods
were evaluated in order to minimize
disturbances
Trenchless Method
Pipe Bursting
Considerations
• Ground surface heaving possible due to
expansion of pipe during bursting.
• Additional excavation pits required where pipe
trenchless
construction methods
bends.
• Bypass
system required
aboveground
deemed
feasible,
and the
projectthrough
wetlands.
Ultimately,
were NOT
will be constructed using an open cut
Sliplining
• Additional pull and insertion pits required
construction method.
where pipe bends.
CarolloTemplateWaterWave.pptx
• Bypass system required aboveground through
wetlands.
Horizontal Directional Drilling • Potential for drilling fluid released to wetlands
and Puget Sound.
• Alternate alignment required due to minimum
bending radius of HDD tool.
20
Construction activities will impact a total
of 45 parcels
• The replacement force mains will be constructed
within the existing easement where possible
• ~ 5,500 SF of permanent easement must be
acquired (3 parcels)
CarolloTemplateWaterWave.pptx
• ~ 18,000 SF of temporary construction permit
required (42 parcels)
21
Construction along the beach will require
federal, state and local permits
Federal
CarolloTemplateWaterWave.pptx
Permit
Agency
Section 404/10 Nationwide Permit
US Army Corps of Engineers
Endangered Species Act Section 7
Consultation
US Fish and Wildlife Service/National
Marine Fisheries Service
National Historic Preservation Act
Section 106 Consultation
Washington Department of
Archaeology and Historic Preservation
22
Construction along the beach will require
federal, state and local permits
State
Permit
Agency
CarolloTemplateWaterWave.pptx
Section 401 Water Quality Certification Washington State Department of
Ecology
Coastal Zone Management (CZM)
Certification
Washington State Department of
Ecology
Aquatic Lands Lease and/or Rights of
Access Agreement
Washington Department of Natural
Resources
Hydraulic Project Approval (HPA)
Washington Department of Fish and
Wildlife
NPDES Permit for Construction
Activity
Washington State Department of
Ecology
WSDOT Utility Crossing Permit
Washington State Department of
Transportation
23
Construction along the beach will require
federal, state and local permits
Local
CarolloTemplateWaterWave.pptx
Permit
Agency
Shoreline Conditional Use/Substantial
Development Permit
City of Bainbridge Island
Critical Areas Review
City of Bainbridge Island
Clearing and Grading Permit
City of Bainbridge Island
24
The Biological Assessment revealed that
several animal species may be affected
Effect**
Common Name
Coastal-Puget Sound DPS Bull
Trout
ESA Status *
Critical
Habitat
Species/
Critical Habitat
Threatened
No
NLAA
Threatened
No
NLAA
Threatened
Yes
Yelloweye Rockfish
Threatened
No
NLAA
Canary Rockfish
Threatened
No
NLAA
Bocaccio Rockfish
Endangered
No
NLAA
Southern DPS Eulachon
Threatened
No
NLAA
Marbled Murrelet
Threatened
No
NLAA
Southern Resident Killer Whale
Endangered
Yes
Stellar Sea Lion
Threatened
No
NLAA
Humpback Whale
Endangered
No
NE
Puget Sound DPS Steelhead
CarolloTemplateWaterWave.pptx
Puget Sound ESU Chinook Salmon
NLAA/
NLAA
NE/
NLAA
25
CarolloTemplateWaterWave.pptx
The project area falls within several
regulated critical areas
Source: Kitsap County, 2007; USFWS, 2010; NWI, 2009; Roth Hill Engineering Partners
26
Cultural resources evaluation demonstrated
that no historic properties will be impacted
CarolloTemplateWaterWave.pptx
• ESA photo of sites?
27
Project Schedule critical path are
Easements, Permits and Fish Window
• Easement Acquisition in 2013 to meet 2014
construction window
• Permit Approval may take 6 – 9 months
• Fish window for beach work July 16 – Aug 31
CarolloTemplateWaterWave.pptx
• Easement and permit timelines may push
construction to 2015 fish window
28
CarolloTemplateWaterWave.pptx
Next Steps for 2014 Construction
• August – December 2013
Easement Acquisition
• September – February 2014
Final Design
• August 2013 – June 2014
Permit Approval
• June – October 2014
Construction
29
Project Schedule for 2015 Construction
Sep
2013
Oct Nov
Dec
Jan
Feb
Mar
Apr May
2014
Jun Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
2015
Apr May
Jun
Jul
Aug
Notice to Proceed
CarolloTemplateWaterWave.pptx
60% Design
City Review
90% Design
City Review
Final Design
Easement Acquistion
Temp Permit Acquisition
Permitting
Project Bidding
Contract Award
Construction
30
CarolloTemplateWaterWave.pptx
Project Costs
• ANH
31
CarolloTemplateWaterWave.pptx
QUESTIONS
32
CarolloTemplateWaterWave.pptx
PARKING LOT
33
CarolloTemplateWaterWave.pptx
Three permanent
easements must
be acquired
34
CarolloTemplateWaterWave.pptx
Three permanent
easements must
be acquired
35
Forty-two temporary construction
permits must be acquired
CarolloTemplateWaterWave.pptx
• ERIK – ENHANCE??
36