Transcript POM+ Project
POM+ Project
Squeezing the Juice Out of the Beverage Market
POM+ Project
• • • •
Introduction Priority Matrix Work Breakdown Structure Critical Path
POM+ Project
• • • •
Resource Allocations Earned Value Cost Indicators Earned Value Schedule Indicators Conclusion
Introduction
• • • • •
Big Kola Company soda sales Losing profits Emerging Specialty Juice Market Market Research POM+ Project
POM+ Priority Matrix
Time Scope
Constrain Enhance Accept X X
Cost
X
Work Breakdown Structure
• • • • • •
Research & Development Secure Fruit Suppliers Initial Production Distribution Legal Prepare Product Launch
Critical Path
• • • • •
Need survey Set product specs Shelf life report Secure fruit suppliers Equipment rehab
Critical Path, continued
• • • • •
Production trials Quality trials Quality metrics Quality training Prepare product launch
Critical Path, continued
• • • • •
Production trials Quality trials Quality metrics Quality training Prepare product launch
Gantt Chart- Critical Path
Resource Allocations
Resource
Marketing R&D Engineering Purchasing Quality Designers Legal Staff Production 2 3 3 3 20
Available
5 5 10
Hourly Rate
$80/hr $80/hr $100/hr $60/hr $80/hr $60/hr $120/hr $60/hr
EARNED VALUE MANAGEMENT
Earned Value Cost Indicator
• • • • •
CPI- .70
EAC- $2.4 million BAC- $1.7 million VAC- $710,000 TCPI- $1.15
Earned Value Schedule Indicator
• • •
SPI- .69
SV%- .31
SV- $184,000 Earned Value Management crucial to project success.
Conclusion
• • •
Business savvy Priority Matrix EVM
REFERENCES
Cohen, M. W., & Palmer, G. R. (2004). Project Risk Identification and Management.
AACE International Transactions
, 1.
Business Source Premier
, EBSCO
host
Davies, J. R. (1995, November 6). Using work breakdown structure in project planning.
Plant Engineering
,
49
(14), 54+. Retrieved from http://go.galegroup.com/ps/i.do?id=GALE%7CA1798558 4&v=2.1&u=klnbsouthwest&it=r&p=AONE&sw=w Larson, E. W., & Gray, C. F. (2011).
Project management, the managerial process
(5th ed.). New York, NY: McGraw Hill Irwin.
REFERENCES
Poletti, B., & Marcoux, R. (2008). Performance indicators for project management.
CMA Management
,
82
(6), 24-28.
Business Source Premier
, EBSCO
host.
Slack, N. (1994). The importance-performance matrix as a determinant of improvement priority.
International Journal of Operations & Production Management, 14
(5), 59-59. Retrieved from http://ezproxy.sckans.edu/login?url=http://search.proques
t.com/docview/232337910?acco untid=13979