Transcript Slide 1
Green Datacenters solution March 17, 2009 By: Sanjay Sharma
•
Energy Facts
Of all the potential electricity available in an energy source, only 30 percent reaches consumers
•
An estimated 170 billion kilowatts are wasted by consumers each year due to insufficient power usage information
•
US Datacenters and servers consumed about 670 billion kWh in 2008 with an estimated total electricity cost of $ 5.0 Billion Generation & Distribution Cooling DATA CENTER Power Supplies, UPS 100% 30% 16%
2 2
Mission Critical Apps .003% Silicon 1% Servers
IT Equipment = 30% Energy Equipments = 25% Cooling = 45%
Where Does Power Go?
3 3
Total number of servers installed increased by factor 100 in one decade
Number of server/processors per rack increased by factor 10 in ten years
Power and thermal waste per server increased by factor 5 in ten years
Source: APC View
I.T damage to the environment
Billions of KW/hrs Millions of Tons of CO 2
• I.T Does as much damage to environment as Airline Industry • 2% of CO 2 Emitted comes from I.T Industry • For every 1 spent powering systems 0.5 to 1 spent on cooling 4 4 I.T is the focus of GREEN lobby!
Source: EPA Report
5 5
Green Buildings
Enhancing existing buildings to be more energy efficient typically reduces total energy consumption by 20-50%...
…
while new “green” buildings have the potential to reduce energy consumption by 80% or more.
Benefits
Average achievable energy savings greater
Asset utilization rates increasing 2x-4x;
Average payback of <2 years in Data Center Energy Efficiency assessments; Deferral of massive capital investments in new datacenter builds
$1 energy savings drives another $6-8 operational savings on average
Source: IBM Client Survey
6 6
Case Study
Energy Management Solutions for Bharti’s Telecom Towers
Conventional solutions & associated problems
Problems with Conventional systems Conventional systems 15/25 KVA DG
• • •
Unhealthy Grid
High DG running costs Higher capacity DG’s 7 7
IT, Servo, AMF, Alarm box ACDB etc GI:GI Shelter 1.5x2
2.0x2
Tr AC’s
• • • • • •
Operational problems
Low efficiency in Power utilization (85%) – Leading to Heat losses Slow Voltage regulation time leading to – SMPS Failure – High maintenance Large foot print Excessive cabling Frequent breakdowns with no monitoring of passive infrastructure elements • • • •
Shelter
High solar gain Non modular Rusting problem • • • •
Air Conditioning
Oversized AC’s Very High Inrush Current No Free Cooling
Challenges
Addressing Challenges
Contributor/Reasons Innovative ‘s Solutions Site Operation Cost
• • • • • Various AC/DC Conversion Cost Backup Cost Environment Conditioning Cost D.G. running cost due to unhealthy grid Over-design Infrastructure for Peak Load (like 15KVA DG for 3KW load) • • • • • Less/low AC/DC Conversion
Low backup cost
Low Air-Conditioning Cost Wide range PIU to maximize low cost grid usage Low back up power cost with DC power house of 5kw
Site Downtime Main Reasons
• Battery • • Generator Air-Conditioner • • • NextGen thin Plate Technology Aviation grade very high MTBF DC Generator Compressor less N + 2 redundancy 8 8
Project Operation and Maintenance Cost ,
• • • Installation Time Expandability IT Interface for critical and operational need monitoring • • • • Installation time (24-48 hours) Expandability modular Energy metering for each operator and their individual load Detailed NMS
9 9
Use of technology for reducing energy costs
•
Air Conditioning
–
Next Generation Cooling solutions (for Indoor BTS)
–
Battery Cooler (for Outdoor BTS)
•
Battery back-up power
–
High efficiency and cycle life batteries
–
Float Mode operation for extended life
•
DG based power
– – –
Cost of DG running to be reduced Move site to DC Power architecture which creates future proof site Explore Alternative technologies like wind/ solar or fuel cells
•
Energy losses in SMPS & PIU
– –
New products offering high efficiency Wide operating range to reduce DG running
•
Integrated NMS
–
Integrate Tower Management (Through SMS and GPS) with overall NOC
Conventional Telecom Approach
IT and Datacenters are in similar position like telecom was few years back
AC 1.4 kW
3.4 kW
Mains DG
3.15 kW
PIU 250 W 3% SMPS 250 W 10% BTS
1.5 kW
Battery 300 AH 50 W Leakage
Note: Per hour energy usage / energy losses
Every IT Companies were focusing at this point
11 11
Our Green Solution for Telecom
2
AC 0.45 kW PCM Technology
2.4 kW
Mains
1
PIU 150 W 3% SMPS 250 W 10% BTS
1.5 kW 3
Battery 15 W Leakage
4
DC Power House
Note: Per hour energy usage / energy losses
1 MW Loss 3% Transformer
Current IT Datacenter set up
Switch Yard Loss 5% Regulator Loss 0.5% AMF Panel 915 kW Distribution Panel Generator 1 Generator 2 Generator 3 Synchronization Panel 366 kW AC Air Lighting Misc. Load Mains 366 kW Distribution 1 Distribution 2 Loss 10% UPS 1 UPS 2 15% (no Load) UPS UPS Precision AC1 Precision Cooling for Server AC2
ACME’s Green Datacenter Solution
1 MW Mains Line Conditioner + Isolation Transfer + Lightning Protection 970 kW (rarely used) Mains Distribution 970 kW Electronic Distribution N+1 350 kW N + 1 Servers & Electronics Mirror Server & Electronics Mains Synchronized Micro turbine (500 kW) in n+2 configuration Hot air VAM Electrical Chiller (Redundancy) 470 kW (used in emergency) Precision AC Distribution N+1 75 kW N + 1 Precision AC Redundant Precision AC Fuel Tank 1 Fuel Tank 2 Normal Cooling Multi Fuel 75 kW Lighting
Macro level Savings
• On site power generation 24x 7 • No separate expenditure on Air Conditioners • Elimination of various AC-DC conversion losses • Energy generation at low cost in cogeneration mode • Carbon credit benefit • No operation and maintenance expenditure of DG
Making green solution profitable
• ACME can built clean energy infrastructure for new IT Datacenter set up and reduce – 20% Capex (approx.) – 15% Opex – 30% Carbon Emission • ACME can take up existing infrastructure and reduce – 10% Opex – 20% Carbon emission
Thank You !!
Partnership Contact: Email: [email protected]
Mobile:+919810159777