Job Costs - Foremans Development Series

Download Report

Transcript Job Costs - Foremans Development Series

Objectives
In the 1st half of this Module we’re going to cover:
• The computerized estimating process.
• How a Contractor comes up with his Material
Costs and Labor Units.
The 2nd half of this module will look at how Labor
Units give us a way to check our Install Rates.
• Are we installing our materials in the time given
to us by the Job Estimate?
What’s the Point?
As we’ve seen in other Foreman Development modules, the Job Estimate
affects all other aspects of the Project:
Monthly Job Cost
Reports
Job
Estimate
Job
Budget
and Cost Codes
Project
Buy-Out
Man-Loaded
Schedule
Schedule of
Values
Pay Application
2 Week
Look-A- Head
Estimating Software??
Estimating Software Functions
Advantages of Estimating Software
Estimating Material Costs
• Big ticket items like Light Fixtures or
Switchgear are quoted as separate
packages in the Estimate.
• Getting quotes on Bulk buys will save $$$$
• Thousands of misc. electrical parts also
have to priced as part of the Estimate.
TRA-SER SX
Computerized Take Offs
Main Floor Take Off
Accubid Job Summary
Electrical Assemblies
Assm# Assm Name
Item# Item Name
60,034 DPLX 20/3 SS
14,486 DPLX 5-20r hd spec IV
14,349 1G SS DUPL RECP PLAT
14,669 4/S BOX 1-1/2 DEEP
14,674 4/S SG MUD RING 5/8"DP
3,891 BOX SUPPORTS - CLIP O
5,574 YELLOW 3M WIRE NUT
16,590 J-BOX ID TAG
16,591 DEVICE ID TAG
16,592 WIRE ID TAG
15,354 GROUND SCREW / #12 PI
60,040 DEVICE TEST
Material $'s
Labor Hours
Price
Bid lbr
$10.33
0.950
$499.80
$100.00
$60.00
$39.00
$42.46
$40.00
$0.25
$0.50
$0.25
$22.00
$0.00
C
C
C
C
C
C
E
E
E
C
X
30.00
6.25
10.00
6.25
7.50
0.03
0.04
0.04
0.04
7.50
0.07
Unit Price 1
qty
$22.18
C
C
C
C
C
E
E
E
E
C
E
1.0000
1.0000
1.0000
1.0000
1.0000
3.0000
1.0000
1.0000
3.0000
1.0000
1.0000
Estimating Labor
Labor Units
•
•
•
•
•
Labor Units are expressed in man-hours for the
installation of:
E = One or per each item
C = Per one hundred items
C = Per one hundred linear feet of the item
M = Per one thousand linear feet of the item
LF = Per linear foot
Labor Units vary by Jobsite conditions:
• Normal
• Difficult
• Very Difficult
What's in a Labor Unit?
Non-productive
Breaks
Studying
Plans
3%
6%
Receiving and
Storing Materials
3%
3%
Gathering
Materials
5%
Mobilization
3%
5%
Clean Up
Site Movement
(People)
8%
Measuring
& Layout
64%
Actual Installation Time
64% Efficiency
– RS Means
Typical Labor Units
•
•
•
•
•
•
•
Duplex Receptacle
Panelboard
¾” GRC
500 MCM Feeders
30 amp Disconnect
Surface mounted Shop Light
2’ x 4’ T-grid Light Fixture
What are your Labor Units?
• Your company had specific Labor Units
that they used when they bid your job
• Did your crew make the Estimate when
they installed that big rack of 4” EMT
conduits?
• If you are not making your install rates you
are in trouble!
Figure your Install Rate
A 2 person crew was told to install 2,000 feet of 4” EMT.
The NECA Labor Units for this material under normal
conditions is 16 Labor Units per 100’ of conduit.
1. How many feet of conduit should one person install in an hour?
6.25 feet per man hour
2. How long should this entire task take?
320 hours
3. How much conduit should be installed by your 2 man crew at the end of
5 days?
500 feet per hour
4. One day I had 4 people running conduit. How many feet of conduit
should they have put in?
200 feet
What’s Included?
What is and isn’t included in the Labor
Unit?
• Scope
• Work Operations NOT included
• Application Instructions
An Install Rate Example
• A 500’ long
conduit rack with
(4) 4” EMT
conduits.
• Supports every
8’= 63 racks
Calculators
Tracking Labor Estimates by Area
• Some contractors will break their Estimate
into small areas or phases
– So their take- offs will show the total labor and
materials quantities used in each of these
small areas.
• This method gives the Foreman in the field
a simpler way to track their labor in small,
quantifiable work areas.
Extended Costs
Extended Material and Labor Costs
Description / Size
Quantity
Unit
Material Units cost
Material Result
Labor Units
Man hours)
(in Labor Result
Man hours)
(in
EMT 1/2"
4330
ft.
0.2362
$1,022.75
0.045
194.85
EMT 3/4"
4715
ft.
1.0614
$5,004.50
0.05
235.75
EMT 1 1/2"
155
ft.
3.6288
$562.46
0.07
10.85
EMT 4"
350
ft.
12.8759
$4,506.57
0.16
56
EMT-90 1 1/2"
5
ea.
7.8269
$39.13
0.4
2
EMT-90 4"
3
ea.
54.3683
$163.10
1
3
80
ft.
0.1863
$14.90
0.045
3.6
120
ft.
0.2718
$32.62
0.0525
6.3
PVC 1 1/2"
60
ft.
0.4551
$27.31
0.07
4.2
GRC-90 1/2"
32
ea.
3.26
$104.32
0.35
11.2
GRC-90 1"
44
ea.
5.25
$231.00
0.5
22
8
ea.
8.84
$70.72
0.75
6
PVC 3/4"
PVC 1"
GRC-90 1 1/2"
Total
$11,779.38
0.2362 unit cost
Material Prices per TRA-SER, 3/25/12, NECA Normal - 2010
.05 man hours
555.75
Job Take-Off Activity
• Use the Extended Material and Labor Costs
Handout
• Answer the following questions;
01 / Mobilization – Job site set up & removal: trailers, office, gang boxes, materials, etc.
02 / Demolition – Removals and demolition
03 / Site work – Underground, pole lights, temporary power, etc.
04 / Branch – conduit, boxes and wire; up to 1”.
05 / Feeders – conduit, boxes and wire; 1 ¼” and above.
06 / Gear – Switchgear, transformers, starters, disconnects, contactors, etc.
07 / Fixtures – receiving and installing any and all fixtures
08 / Special Systems – Security, fire alarm, PA, etc., including all conduit and wire
- does not include sub contractor’s work.
09 / Devices – plugs and switches, trim plates, etc.
10 / Warranty Work
Job Budget
• The money from the Estimate is juggled
around into various job categories and line
items.
• Each of the Budget line items will include
all costs involved; labor and materials,
equipment, overhead and profit, etc.
• All of the line items will add up to the
contract amount
Job Budget
Code
Labor
Hours
Labor$$ ($30/
hour)
1
Jobsite set up
20
$600
2
Demolition
107
$3,210
3
Site work
132
$3,960
4
Branch Circuits
500
5
Feeders
6
Material $$
Equip.
Subs
Misc.
$500
OH & Profit Contract
Total Cost
(15%)
Amount
$1,100
$165
$1,265
$3,210
$482
$3,692
$1,107
$5,067
$760
$5,827
$15,000
$2,805
$17,805
$2,671
$20,476
182
$5,460
$7,668
$13,128
$1,969
$15,097
Gear
66
$1,980
$3,000
$4,980
$747
$5,727
7
Fixtures
495
$14,850
$98,941
$113,791
$17,069
$130,860
8
Special Systems
221
$6,630
$3,481
$17,611
$2,642
$20,253
9
Devices
102
$3,060
$683
$3,743
$561
$4,304
10
Warranty Work
$0
$0
$0
11
General
$4,000
$4,000
$600
$4,600
$4,000
$184,435
$27,665
$212,100
Totals
$7,500
$0
1825
$54,750
$118,185
$0
$7,500
A Job Cost Report
Labor
Hours
Code
1
Jobsite set up
20
2
Demolition
3
Labor
Costs
%
Labor
Spent
Material $$
Material $$ % Material
Spent
Spent
$500.00
83%
$500.00
$700.00
107
$3,210.00 $2,000.00
62%
$0.00
Site work
132
$3,960.00 $4,000.00 101%
4
Branch Circuits
500
$15,000.00 $7,000.00
5
Feeders
182
6
Gear
66
7
Fixtures
8
Contract
Amount
%Total
Spent
140%
$1,265.00
95%
$0.00
0%
$3,691.50
54%
$1,107.00
$1,000.00
90%
$5,827.05
86%
47%
$2,805.00
$2,000.00
71%
$20,475.75
44%
$5,460.00 $3,000.00
55%
$7,668.00
$4,000.00
52%
$15,097.20
46%
$1,980.00
$100.00
5%
$3,000.00
$3,000.00
100%
$5,727.00
54%
495
$14,850.00 $12,000.00
81%
$98,941.00 $80,000.00
81%
$130,859.65
70%
Special Systems
221
$6,630.00 $2,000.00
30%
$3,481.00
$3,000.00
86%
$20,252.65
25%
9
Devices
102
$3,060.00 $2,000.00
65%
$683.00
$600.00
88%
$4,304.45
60%
10
Warranty Work
0%
$0.00
0%
11
General
$4,600.00
0%
$212,100.25
60%
Totals
$600.00
Labor
Spent
$0.00
1825
$0.00
$54,750.00 $32,600.00
0%
60%
$118,185.00 $94,300.00
80%
Production?
Are you making your Labor
rates??
Summary
Anyone want to be an Estimator?
• Well, maybe not, but at least we have a
better understanding of how they do their
work
• We need to be more competitive!
– In order to do that we need to be more
productive.
– System Productivity and checking our Labor
Install Rates are tools we can use to help us
do that.