Transcript Slide 1

NIRANTHARA JYOTHI SCHEME
NIRANTHARA JYOTHI SCHEME:

Niranthara Jyothi Project is a prestigious scheme of Government of
Karnataka, to provide 24 hrs 3 phase power supply to non-agricultural
loads like domestic, commercial, water supply, street light, rural
industries, milk dairies etc., in rural areas by segregating the
agricultural loads, which is a boon to the rural economy.
Objectives :

This will enable BESCOM to give 24X7 supply to Non-Agricultural
loads in Rural areas

Reduction in transformer failure

Increase in metered sales

Reduction in technical losses

Improved load management
The plan of implementation and progress is shown separately.
1
STAGES OF IMPLEMENTATION
Phase I
•
–
–
–
25 Lots, 260 feeders, 19 taluks.
Project cost :Rs 355.85 cr.
Expected completion : June-2013.
Phase II
•
–
–
–
–
–
24 lots, 289 feeders, 22 taluks.
Project cost :Rs 385.71 cr.
Work Award issued for 6 Lots, 86 feeders , DWA issued in Nov
2011, Jan-2012 ,works under progress.
Work Award issued for 10 Lots ,96 feeders , DWA issued in
Oct, Nov 2012,Works under progress.
For the 93 feeders, LOI is issued and works under progress.
2
300
269
260
260*
250
240
No of feeders
200
150
100
50
0
03
06
feeders
dropped
feeders merged
0
Total feeders
(DWA)
Total feeders
(actuals)
completed
commissioned
work under
progress
Note:
* All works relating to 11KV Distribution network is completed in respect of 260 feeders and for the
balance feeders to be commissioned requires, segregation and realignment of LT lines.
3
STATUS OF NIRANTHARA JYOTHI PHASE-I IN BESCOM
4
STATUS OF NJ FEEDERS AS ON 24.06.13
Sl. NO
Name of the
Circle
Name of the
Division
Lot No
Total No of
NJ feeders
(Actual)
1
2
3
4
5
6
7
No. of feeders
work under
progress
8
Chikkaballapura
8 : Bagepalli
11
11
11
0
11
11
11
0
SUB TOTAL
1
KOLAR
9 : Shidlagatta
14
14
13
0
SUB TOTAL
SUB TOTAL
14
14
13
0
25
25
24
0
13 : Tumkur-1
16
16
15
0
14 : Tumkur-2
9
9
9
0
16 : Gubbi-1
11
11
11
0
17 : Kunigal-1
8
8
7
0
18 : Kunigal-2
8
8
7
0
52
52
49
0
11: Tiptur-1
6
6
6
0
12: Tiptur-2
6
12
11
6
12
11
6
12
10
0
0
0
25: Madhugiri-2 &
Sira-1
13
13
13
0
26: Sira-2
11
11
11
0
SUB TOTAL
35
35
34
0
TOTAL(B)
99
99
95
0
Tumkur
SUB TOTAL
TUMKUR
No. Feeders
Commissioned
Chintamani
TOTAL (A)
2
No. Feeders
Completed
Tiptur
SUB TOTAL
24: Madhugiri-1
Madhugiri
STATUS OF NIRANTHARA JYOTHI PHASE-I IN BESCOM
5
STATUS OF NJ FEEDERS AS ON 24.06.13
Sl. NO
Name of the
Circle
1
2
Name of the Division
Lot No
3
Chirtadurga
Sub Total
4
1: Hosadurga
7
8
8
15
9
8
0
0
0
0
27
27
24
0
4: Harapanahalli
10
10
10
0
5: Honnali
Sub Total
11
21
9
7
16
11
21
9
7
16
10
20
9
7
16
0
0
0
0
0
TOTAL(C)
77
77
68
0
7: Anekal
5
5
5
5
5
5
0
0
22: Kanakapura-1
9
9
7
0
23: Kanakapura-2
19: Hosakote-2
10
19
7
10
19
7
8
15
7
0
0
0
20(A) :Hosakote-1
11
11
11
0
10: Devanahalli
17
17
15
0
Sub Total
35
35
33
0
TOTAL(D)
59
59
53
0
260
260
240
0
2: Channagiri
3: Jagalur
Harihara
Sub Total
Hiriyur
Chandapura
Sub Total
Ramanagara
20: Hiriyur-1
21: Hiriyur-2
Sub Total
4
No. Feeders No. of feeders work
under progress
Commissioned
6
13
13
18
9
Sub Total
DAVANGERE
No. Feeders
Completed
5
13
13
18
9
Davangere
3
Total No of NJ
feeders (Actual)
BANGALORE
RURAL
Yelahanka
GRAND TOTAL (A+B+C+D)
STATUS OF NIRANTHARA JYOTHI PHASE-II IN BESCOM
Name Name of
Sl
of the
the
No
Circle Division
1
2
3
Total
Total No. of
No. of
Total No. of NJ feeders
Lot
NJ
NJ feeders Commissione
No./Taluk feeders
d
Completed
propose
d
4
1
Bangal
Nelamang 1:Doddaballa
ore
ala
pura
Rural
2
Tumku
Madhugiri 9:Koratagere
r
3
Tumku
r
4
5
6
Kolar
Tiptur
8:Chikkanaya
kanahalli
(part-2)
KGF
10:Bangarpet
/
KGF
Kolar
Chintama 13:Chintama
ni
ni
Kolar
Chiikaball 16:Gowribida
apura
nur
Total
5
17
11
8
16
15
6
5
3
WUP
WUP
5
Status
7
8
_
DWA issued on
10.11.11
work under progress.
_
DWA issued on
21.01.12
work under progress
_
DWA issued on
10.11.11
work under progress
_
DWA issued on
10.11.11
work under progress.
2
DWA issued on
10.11.11
work under progress.
19
2
_
86
15
2
DWA issued on
10.11.11
work under progress.
6