The Point O’Woods Association, Incorporated
Download
Report
Transcript The Point O’Woods Association, Incorporated
Water and Sewer Systems:
WPCA Benefit Assessment and
Pre-Construction Public Hearing
WPCA BENEFIT ASSESSMENT, PRE CONSTRUCTION HEARING
AGENDA
2008 Sewer and Water Update
Overview of Construction Project
Review of Proposed Benefit
Assessment Method
Estimated Costs
Q&A with Panel
Rob Prybylo – RFP Engineering, LLC
Norbert Church, Esq. – Counsel
Chris Kerin – Appraiser, Kerin and Kerin
WPCA Members:
Kathy Aldridge
Marty Guyer
Jack Harney
Kathy Mckeough
Mark Stankiewicz
Bill Lacourciere
Rob Prybylo
Bill Lacourciere
FY 2008 in Review
Engineering Design Completed
DEP, DPH, CWC, VE reviews completed
Construction bids received
Benefit assessment method proposed
Project approved and funded by the CT Bond
Commission
FY 2008 in Review
Intermunicipal Agreement Completed
One agreement – East Lyme
Established interconnection fee of $1,026,000
User fee same as East Lyme customer: $5 per 1,000 GPD
Fee for using State loaned capacity if and when
necessary - $5 per 1,000 GPD
Pay for actual flow used instead of flat rate
FY 2008 in Review
Improved Communications
4 Benefit Assessment workshops
11 WPCA meetings
Annual Meeting
Public Hearing
Joint BOG/WPCA meetings
Monthly newsletters
Monthly FAQs
WPCA website
FY 2008 in Review
Construction Permits Approved:
Old Lyme Inland Wetlands and Watercourses
Commission
East Lyme Conservation (wetlands) Commission
DOT approval for Route 156
Amtrak for construction beneath railroad trestle
Old Lyme Zoning Commission (pending)
Construction Schedule
Paganelli Construction Co. has 2 years to complete the
project
No work will begin within Point O’Woods until after
Labor Day, 2008
We anticipate that Paganelli will try to complete as
much work as possible during “off seasons”
Sewer System
Work will start with mains in streets and pump
stations
Installation of individual grinder pumps and lateral
sewers to individual properties will be installed only
after mains have been installed in the streets
Curb-to-Curb overlay pavement will be installed
towards the end of the project after pipelines have
been installed
Sewer System
Working hours will be from 7:30 AM until 4:00 PM
Detours will be necessary to divert traffic around
construction crews
We will post and update construction schedules on the
WPCA’s website (www.point-o-woodswpca.com)
Water System
Paganelli Construction Co. will install the water mains
in the street in the same trench as the sanitary sewers.
All new water mains will be installed at frost-proof
depths
Paganelli will install new services from the mains to
each current customer’s property and install a new
meter pit at a frost-proof depth for each existing
customer
Water System
Paganelli will then connect from the meter pit to the
existing water service at a point near the street
Paganelli WILL NOT replace the existing pipe from
the meter pit to the house
Temporary water services will be maintained during
construction to enable existing system to be taken out
of service
Water System
Only brief outages are anticipated as houses are
connected from existing mains to temporary system
and from temporary system to new mains
Most/all of this work should be completed during offseason periods when most properties are not occupied
Grinder Pumps
The Association will own, install, and maintain grinder
pumps and pressure sewer from the pump to the main
in the street
Property owners will be responsible for connecting
from the house to the grinder pump and to bring
electricity to the electrical panel
Some properties may need to upgrade their electric
panel to accommodate grinder pumps
Notification letters have been sent to property owners
that will receive grinder pumps asking them to contact
Doug Hill at RFP Engineering
Grinder Pumps
• We will meet with property owners at their house to
discuss best location for pump and pipes
• Property owners will need to execute an agreement
with the Association giving the Association the right
to go onto property to install and maintain the pumps
and pipes
The WPCA will be contacting property owners with
grinder pumps soon to begin this process
Blasting
Unfortunately, much of the project will require
blasting to remove ledge rock
Paganelli Construction Co. is required to hire a
qualified, licensed blaster to oversee and perform all
blasting
Paganelli’s blaster will be required to perform a PreBlast survey of each building that is within 250 feet of
where blasting will be conducted.
Blasting
Blasting will only be allowed between the hours of 9
AM and 3 PM
All blasting work will be under the purview of the local
fire marshal's office
Easements
We need to obtain easements from the owners of 5
properties along Champion & Hillcrest Roads
Water and sewer services will be installed behind the
existing sea wall
Sewer service will be by gravity
The WPCA will be contacting these property owners
shortly to begin the process
Communications
Doug Hill, P.E. will serve as Resident Engineer during
construction and should be the first point of contact
for construction-related issues
He will have an office trailer in or near Point O’Woods
His contact information will be made available on the
POW WPCA website as soon as it is established
Communications
Please check www.point-o-woods.com often to receive
important bulletins and work schedule updates.
Benefit Assessment Method
Goal: Determine the most equitable benefit
assessment method for our community which is most
defensible in court
Benefit Assessment Method
Process:
Four public workshops
Nine WPCA meetings
Surveyed various communities with similar conditions
Consultants
Real Estate Experts
Appraisers
Legal Experts
BOG survey of the community
Considered several benefit assessment methods
Benefit Assessment Method
Methods Considered:
Flat rate (evenly divided amongst all of us)
Property value
Front footage, acreage
Usage
Number of bedrooms
Combinations of the above
Benefit Assessment Method
All but flat rate and property value methods were
ruled out because:
Uniquely, POW properties are all single-family homes
No commercial properties
No industrial properties
No farms
No municipal buildings
No method of measuring usage at this time
Benefit Assessment Method
Two methods best met our objectives:
Flat Rate
Property Assessment
Property Assessment:
Preferred by majority of respondents to BOG survey
Least defensible legally – there would be cases where the
benefit assessment would exceed the value of the
benefit derived from the project
Benefit Assessment Method
Property Assessment (continued):
Most disproportionate – some properties would pay over
$50,000 and others less than $15,000 and at times the
derived value would be reversed
Moving target – a presently unimproved property could
be greatly improved following construction but pay a
disproportionately small assessment.
Benefit Assessment Method
Flat Rate:
Met expectations of most property owners of $24,000
per property
Method used alone or in some comination by most
communities
Most defensible in court – highly unlikely that a
property would be assessed higher than the value
derived from the project
Whether communities we spoke with used it solely or
not, most strongly recommended it because it is simple,
fair, and defensible
Benefit Assessment Method
Flat Rate (continued):
Recommended by counsels Norbert Church and James
Mattern and our appraiser, Chris Kerin
Method most easily managed by a small, volunteer
community
Benefit Assessment Method
Appraisal Report:
Average value derived from the sewer and year-round
water project is
$70,000
Benefit derived could be inverse from benefit assessed
Virtually guarantees that that a flat rate method could
not be legally defeated in court
Benefit Assessment Method
Legal Opinion:
It is reasonably probable that a seasonal property would
be converted to year round occupancy with year round
sewer and water available
Flat rate was most legally defensible method
Benefit Assessment Method
Grinder Pumps:
Use of grinder pumps saves us all millions of dollars
Their proper function is critical to the overall efficacy of
the system; therefore, they should be owned, installed
and maintained by the POW Association
They are an inconvenience to the property owner
Have to pay for electricity to operate
Have to provide POW an easement for access
Compensation:
POW pays for grinder pump and its installation
POW maintains the grinder pump
POW pays for cost of any connection that exceeds $8,000
Benefit Assessment Method
PROPOSAL:
The WPCA proposes that the benefit assessment
method be flat rate for all
That each single-family dwelling be classified as a unit
That the benefit assessment be assessed on each unit
That all property owners pay for their own connections
That the maximum cost a property owner will pay for the
connection of a grinder pump to the street is $8,000
Annual User Fees (Entire System)
Annualized Avg.
Daily Use @ a
Cost of $5/1,000
GPD
Daily
Cost
Annual
Cost
Cost per
Unit
25,000 GPD
$125
$45,625
$106
30,000 GPD
$150
$54,750
$128
40,000 GPD
$200
$73,000
$171
100,000 GPD
$500
$182,500
$426
Other Costs
Expense
Range
Average Per Unit
One Time
Connection Costs
$1,000 - $8,000
$2,500
Association’s
Annual
Maintenance
Expense
$10,000 - $20,000
$23 - $47/year
Description
Construction
Including
Technical
Services,
Design Costs
Cost
State Grants
& Other
Funds
Net Cost to
Association
$2,922,000
$7,423,00
Cost per
Unit
Cost/Unit/
Year @ 2%,
20 Years
$9, 290,000
Legal,
Admin. &
Other
$345,000
Contingency
$530,000
Interest
$180,000
Subtotal
$10,345,000
$17,343
$20,811
$1,041/yr
Cost To Homeowners for Water,
Sewers and “New” Roads:
$17,343
Next Steps
Gravity Sewer Connections:
The WPCA is working on a plan to enable homeowners
to use a pre-selected/pre-qualified contractor at a preestablished price
Policies:
In the coming months, the WPCA will be establishing
several new policies:
Connection Policy (who, how, and when)
Sewer Use Charge Policy
Next Steps
Meetings with Property Owners:
Grinder Pump Properties
Decide on best location for grinder pump and pipe
Execute agreement
Gravity Sewer Properties
Decide on best location for lateral sewer
Blast Area Properties
Schedule time for pre-blast survey
Summary
Design is Complete
Bids are in and they are low
State monies have been set aside
Grant and Loan applications are pending
East Lyme agreement is completed
Permits are complete except one: Old Lyme Zoning
Benefit Assessment method has been proposed
THANK YOU!!