Transcript Slide 1
2014 Transmission & Distribution Benchmarking Insights Conference Substation August 20-22, 2014 Vail, CO 1.Primary power lines 2.Ground wire 3.Overhead lines 4.PotentialTransformer 5.Disconnect switch 6.Circuit breaker 7.Current transformer 8.Lightning arrester 9.Main transformer 10.Control building 11.Security fence 12.Secondary power lines 1 10.Control building 11.Security fence 12.Secondary power lines Agenda ◼ Key issues ◼ Statistics and System Activity ◼ Financial ◼ Practices and Initiatives 2 Key Benchmarking issues in substations Industry Issues ◼ ◼ ◼ ◼ Methodology Regulation ◼ NERC reporting (TADS) NERC compliance FERC Technology ◼ Substation Automation Age and obsolescence of components Problematic equipment Smart Grid requirements ◼ Planning to Build Process Planning Process Estimating tools Lead times for major equipment Lead times for environmental/permitting issues Competing goals of T&D organizations ◼ Planning/Engineering/Design coordination Workforce issues Contract Management Aging workforce ◼ Availability and quality of internal and contract resources Degree of specialization 2014 • Physical Security • Storm Threat • Spending Up ◼ T&D Costs are separated by FERC, but the "substation" account is not. Costs need to be allocated FERC allows some latitude in the distinction between distribution and transmission substations. For substations that have T&D facilities, the cost split is not always consistent In most organizations T&D Substations are typically managed in the same department, usually transmission. But there are T-only or D-only companies that are interested in separating T-subs vs. D-subs. Different voltage levels, purposes, levels of transformation, rollover schemes, loadings and designs make benchmarking comparisons problematic There is no consensus on normalizing variables: customers, installed MVA, average of peak load, assets, and book values. There is a lag in when capital additions are reported which is reflected in changes in CWIP accounts, 3 2014 T&D: Capital Projects CAPITAL SPENDING FORECAST: T&D SUBSTATIONS [ACTIVITYBASED] Mean Quartile Mean 0.91 Quartile 1 0.46 Quartile 2: 0.85 Quartile 3: 1.01 Comment s Calculation used ( ( CP125.1B + CP125.2B + CP125.3B ) / 3 ) / ( (TF50_ABC Trans Subs Cap v14) + (DF55_Dist Subs Cap ABC v.14) ) Page4 Transmission Substation Trends We see an increase in spending for 2013 . . . 5 Statistics and System Activity 6 Distribution Substations Demographic Profile Min Mean Max # of Bars $33.24 8.46 $38.21 16.10 $41.97 32.94 12 11 0.64 2.16 3.86 7 5kV class = >1kV, <=9kV 0.0% 23.4% 76.2% 14 15kV class = >9kV, <=15kV 16.9% 64.1% 99.1% 14 25kV class = >15kV to <=26kV 0.0% 6.5% 60.4% 14 35kV class = >26kV to <=36kV 0.0% 5.5% 27.3% 14 44kV class = >36kV to <=44kV 0.0% 0.5% 6.5% 14 10.06 28% 0% 18.02 52% 11% 63.24 91% 62% 11 10 11 $7,902 $34,744 $60,146 11 Organizational Demographics Wage Rate: Substation Journey Level Electrician Substation Staffing: FTEs per $100M Substation Assets Demographics: Distribution Distribution Substations per 100 Distribution structure mile Distribution Substations Transformer Banks by Voltage Level Installed MVA Capacity per 1000 Customers: Distribution Average Substation Transformer Loading: Distribution Percent of Switches outside the substation remotely operated Financial - Demographics Distribution Substation Assets per MVA Transmission Substations Demographic Profile Min Mean Max # of Bars 0.50 2.74 12.36 10 <69kV class [Subs] 0.0% 0.1% 1.6% 13 69kV class [Subs] 0.0% 30.5% 78.2% 13 100kV class [Subs] 9.2% 48.0% 100.0% 13 200kV Class [Subs] 0.0% 7.9% 27.0% 13 300kV Class [Subs] 0.0% 2.3% 29.4% 13 400kV Class [Subs] 0.0% 11.2% 63.9% 13 Installed MVA Capacity per 1000 Customers: Transmission 7.93 17.66 31.68 10 Average Substation Transformer Loading: Transmission 29% 59% 78% 8 $17,027 $48,193 $131,477 11 Demographics: Transmission Transmission Substations per 100 Transmission structure miles Transmission Substation Transformer Banks by Voltage Financial - Demographics Transmission Substation Assets per MVA Substation Definitions FERC provides definitions on what constitutes a Transmission vs. Distribution substation based upon use. ◼ For multipurpose substations, FERC allows either segregating costs, or assigning based upon predominant use. For purposes of this survey, we generally will recommend a low side definition based upon a 45kV or below as a distribution substation. ◼ We understand that a typical Canadian practice would be to define a substation based upon high side voltage (e.g. 115kv to 12kv stations are defined as transmission). Based upon predominant use, these still can be classified as transmission substations. ◼ It is unrealistic to ask utilities to redefine their cost or reliability reporting on the basis of these definitions. We will rely on each utility’s self-assigned definitions. However, a utility that has very different definitions may want to restate these statistics to better compare their performance. Transmission Voltage Classes: <69kV 69kV class (>=69kV <100kV) 100kV class (>=100kV <200kV) 200kV Class (>=200kV <300kV) 300kV Class (>=300kV <400kV) 400kV and above Distribution Voltage Classes: 5kV (>1kV, <=9kV) 15kV (>9kV, <=15kV) 25kV (>15kV, <=26kV) 35kV (>26kV, <=36kV) 44kV )>36kV, <=48kV) Note: We will have transmission-only and distribution-only entities participating in this survey. Undoubtedly their voltage levels will not necessarily line-up with the above definitions. 9 2014 T&D: Statistics DISTRIBUTION SUBSTATION TRANSFORMER BANKS BY VOLTAGE LEVEL Comment s Calculation used ST80.2 / (Dist Transformer Banks) * 100 , ST80.1 / (Dist Transformer Banks) * 100 , ST80.3 / (Dist Transformer Banks) * 100 , ST80.4 / (Dist Transformer Banks) * 100 , ST80.5 / (Dist Transformer Banks) * 100 Page10 2014 T&D: Statistics TRANSMISSION SUBSTATION TRANSFORMER BANKS BY VOLTAGE Comment s Calculation used ST85.3 / (Trans Transformer Banks) * 100 , Transformer Banks) * 100 , ST85.4 / (Trans Banks) * 100 , ST85.5 / (Trans Transformer ST85.6 / (Trans Transformer Banks) * 100 , Transformer Banks) * 100 Page11 ST85.2 / (Trans Transformer Banks) * 100 , ST85.1 / (Trans 2014 T&D: Statistics INSTALLED MVA CAPACITY: DISTRIBUTION Mean Quartile Mean 18.02 Quartile 1 12.70 Quartile 2: 13.58 Quartile 3: 14.77 Comment s Calculation used ST100.1 / ( (ST5_T&D Dist End Use Customers) / 1000 ) Page12 2014 T&D: Statistics INSTALLED MVA CAPACITY: TRANSMISSION Mean Quartile Mean 17.66 Quartile 1 11.75 Quartile 2: 16.85 Quartile 3: 22.18 Comment s Calculation used ST105.1 / ( (ST5_T&D Dist End Use Customers) / 1000 ) Page13 2014 T&D: Statistics AVERAGE SUBSTATION TRANSFORMER LOADING AT PEAK: DISTRIBUTION Mean Quartile Mean 52 % Quartile 1 49 % Quartile 2: 51 % Quartile 3: 56 % Comment s Calculation used ST100.5 Page14 2014 T&D: Statistics AVERAGE SUBSTATION TRANSFORMER LOADING AT PEAK: TRANSMISSION Mean Quartile Mean 59 % Quartile 1 46 % Quartile 2: 62 % Quartile 3: 74 % Comment s Calculation used ST105.5 Page15 2014 T&D: Statistics ANALYSIS: T&D PLANT IN SERVICE PER DISTRIBUTION ENDUSE CUSTOMER [FERC] Mean Quartile Mean $4,648 Quartile 1 $4,057 Quartile 2: $4,769 Quartile 3: $4,927 Comments This graph does not represent a performance measure, but instead is used for data validation and analysis. #24, 34 did not include Transmission expenses and will not be shown on subsequent slides. Calculation used ( DF70.1 ) / (ST5_T&D Dist End Use Customers) , ( DF70.2 + TF65.2 ) / (ST5_T&D Dist End Use Customers) , TF65.1 / (ST5_T&D Dist End Use Customers) Page16 2014 T&D: Statistics ANALYSIS: T&D SUBSTATION PLANT IN SERVICE PER INSTALLED MVA Mean Quartile Mean $39,936 Quartile 1 $28,810 Quartile 2: $34,778 Quartile 3: $49,300 Comment s Calculation used DF70.2 / ( ST100.1 + ST105.1 ) , TF65.2 / ( ST100.1 + ST105.1 ) Page17 2014 T&D: Statistics ANALYSIS: DISTRIBUTION SUBSTATION PLANT IN SERVICE PER INSTALLED MVA Mean Quartile Mean $34,744 Quartile 1 $44,242 Quartile 2: $32,630 Quartile 3: $27,128 Comments This graph does not represent a performance measure. It is used for analysis. Calculation used DF70.2 / ST100.1 Page18 2014 T&D: Statistics PERCENT OF DISTRIBUTION CIRCUITS REMOTELY OPERATED Comment s Calculation used ST110.1 Page19 2014 T&D: Statistics PERCENT OF SWITCHES OUTSIDE THE SUBSTATION REMOTELY OPERATED Comment s Calculation used ST110.2 Page20 We ask for several measures of System Activity 21 2014 T&D: System Activity SUBSTATION MVA ADDED Distribution Transmission Calculation used SA40.4A / ST100.1 * 100 , SA40.6A / ST100.1 * 100 , SA45.4A / ST100.1 * 100 , SA45.6A / ST100.1 * 100 Page22 Financial – Overview of the Cost Model Working with an adjusted FERC model 23 T&D Substation Cost Profile 2013YE 2012YE Mean Q1 Q2 Q3 # of Bars Mean Q1 Q2 Q3 # of Bars Substation O&M per Customer Distribution Substation O&M per Customer Substation O&M per Installed MVA Transmission Substations O&M per MVA Distribution Substations O&M per MVA $13.47 $7.94 $13.47 $14.64 15 $16.56 $8.42 $11.75 $15.05 17 $8.40 $3.78 $5.99 $13.75 14 $7.07 $3.39 $6.19 $11.00 17 $492 $267 $353 $483 12 $544 $308 $543 $802 14 $442 $205 $326 $614 11 $489 $217 $436 $681 12 $516 $235 $345 $501 10 $1,419 $274 $502 $703 14 Substation O&M per Total Assets 1.23% 0.87% 1.18% 1.47% 16 1.23% 0.94% 1.17% 1.40% 17 Transmission Substations per Asset 0.91% 0.57% 0.95% 1.08% 13 1.13% 0.76% 1.07% 1.16% 15 Distribution Substations per Asset 1.45% 0.74% 1.29% 2.24% 14 1.36% 0.76% 1.13% 1.83% 17 7.24% 10.45% 5.59% 3.82% 13 5.44% 6.41% 4.25% 2.63% 15 5.07% 5.19% 3.24% 11 3.93% 5.13% 3.38% 2.19% 14 8.23% 13.04% 5.27% 4.13% 12 6.38% 7.17% 5.26% 3.19% 14 O&M Cost Investment Rate Substation Capital Spending less New Subs per Asset [Activity Based] Distribution Substations Replacement Rate Transmission Substations Replacement Rate 5.55% 24 Financial – Overview of the Cost Model Working with an adjusted FERC model and the Activity-Based Cost Model 25 Activity-Based Cost Model 2014 Guidelines The activity-based cost model breaks the expenditures into capital and O&M, and then splits them into the activities shown on the process model introduced above. The following 3 pages provide more details of the individual activities for Transmission, Substations, and Distribution. Activity-Based Costs Transmission Lines Transmission Subs Distribution Subs Transmission Line Capital • Serve New • Expand • Sustain • Other • CIAC T&D Substation Capital • Serve New • Expand • Sustain • Other • CIAC Transmission Line O&M • Sustain the Network • Operate the Network T&D Substation O&M • Sustain the Network • Operate the Network • Other Distribution Lines Distribution Line Capital • Serve New • Expand • Sustain • Other • CIAC Distribution Line O&M • Sustain • Other 26 Activity Based Costs - Substations 2014 Guidelines While capital expenditures are split among several different processes from the overall process model, O&M expenses are almost entirely associated with sustaining the network. T&D Substation Capital • Serve New: New Substations and new substation capacity to serve specific new customer requests • Expand: Capacity Additions to meet generic load growth • Sustain: Repair/replace-in-kind • Sustain: system improvement (reliability/efficiency, system hardening, physical security) • Sustain: Service Restoration • Sustain: Mobile/Spare Transformer Purchases • Other • CIAC T&D Substation O&M • Inspection & Maintenance • Service Restoration • Distribution Operations Center • Engineering/Design O&M (Planning studies, standards, mapping) • Other 27 2014 T&D: T&D Substation Financials T&D SUBSTATION CAPITAL SPENDING PER ASSET [FERC] Mean Quartile Mean 10.0 % Quartile 1 7.5 % Quartile 2: 4.9 % Quartile 3: 4.7 % #28 reported all costs as transmission – total is correct but components will be excluded from TSub slides. Calculation used DF10.5 / ( DF70.2 + TF65.2 ) * 100 , TF10.5 / ( DF70.2 + TF65.2 ) * 100 Page 2 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION O&M & CAPITAL SPENDING PER ASSET [FERC] Mean Quartile Mean 5.9 % Quartile 1 3.7 % Quartile 2: 4.7 % Quartile 3: 7.4 % Comments Some companies are distribution only or transmission only, only a few are T&D combined. #24 reported very little O&M expense Calculation used DF30.5 / DF70.2 * 100 , DF10.5 / DF70.2 * 100 Page29 Distribution Substation Financial – Overview of the Cost Model Working with an adjusted FERC model 30 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION CAPITAL SPENDING PER ASSET [ACTIVITY- BASED] [V.14] Mean Quartile Mean 6.28 % Quartile 1 7.84 % Quartile 2: 5.56 % Quartile 3: 4.92 % Comment s Calculation used DF55.1 / DF70.2 * 100 , DF55.2 / DF70.2 * 100 , DF55.3 / DF70.2 * 100 , DF55.4 / DF70.2 * 100 , DF55.5 / DF70.2 * 100 , DF55.6 / DF70.2 * 100 , DF55.7 / DF70.2 * 100 Page31 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION CAPITAL SPENDING EX SERVE NEW, EXPAND PER ASSET [ACTIVITY-BASED] [V.14] Mean Quartile Mean 3.40 % Quartile 1 4.51 % Quartile 2: 2.88 % Quartile 3: 2.24 % Comment s Calculation used 1 / ( DF55.1 - DF55.1 ) , 1 / ( DF55.2 - DF55.2 ) , DF55.3 / DF70.2 * 100 , DF55.4 / DF70.2 * 100 , DF55.5 / DF70.2 * 100 , DF55.6 / DF70.2 * 100 , DF55.7 / DF70.2 * 100 Page32 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION CAPITAL SPENDING PER CUSTOMER [ACTIVITY-BASED] [V.14] Mean Quartile Mean $32.75 Quartile 1 $38.89 Quartile 2: $33.47 Quartile 3: $26.37 Comment s Calculation used DF55.1 / (ST5_T&D Dist End Use Customers) , DF55.2 / (ST5_T&D Dist End Use Customers) , DF55.3 / (ST5_T&D Dist End Use Customers) , DF55.4 / (ST5_T&D Dist End Use Customers) , DF55.5 / (ST5_T&D Dist End Use Customers) , DF55.6 / (ST5_T&D Dist End Use Customers) , DF55.7 / (ST5_T&D Dist End Use Customers) Page33 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION CAPITAL SPENDING EX SERVE NEW PER DEPRECIATION EXPENSE [ACTIVITY- BASED] [V.14] Mean Quartile 0% 200% 400% 600% Mean $248.71 Quartile 1 $331.12 Quartile 2: $190.57 Quartile 3: $161.50 Comment s Calculation used 1 / ( DF55.1 - DF55.1 ) , DF55.2 / DF80.2 * 100 , DF55.3 / DF80.2 * 100 , DF55.4 / DF80.2 * 100 , DF55.5 / DF80.2 * 100 , DF55.6 / DF80.2 * 100 , DF55.7 / DF80.2 * 100 Page34 2014 T&D: Dist Substation Financials OTHER ACTIVITY BASED COSTS: DISTRIBUTION SUBSTATION CAPITAL SPENDING Calculation used DF56.1 ID 31 33 23 38 24 21 30 27 32 Response Capital Tools, R&D, Premise Equipment, Facilities not applicable NA Environmental/Legislative/Regulatory Environmental/Legislative/Regulatory Not applicable Customer Orders, General Plant, Normal Ops, and Meters/Xfmrs N/A Environmental Not applicable Page35 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION O&M EXPENSE PER ASSETS [ACTIVITY-BASED] [V.14] Mean Quartile Mean 1.42 % Quartile 1 0.74 % Quartile 2: 1.11 % Quartile 3: 2.13 % Comment s #34 reported high service restoration costs #34, 40 high other Calculation used DF65.1 / DF70.2 * 100 , DF65.2 / DF70.2 * 100 , DF65.3 / DF70.2 * 100 , DF65.4 / DF70.2 * 100 , DF65.5 / DF70.2 * 100 Page36 2014 T&D: Dist Substation Financials DISTRIBUTION SUBSTATION O&M EXPENSE PER CUSTOMER [ACTIVITY- BASED] [V.14] Mean Quartile Mean $8.02 Quartile 1 $3.77 Quartile 2: $5.05 Quartile 3: $12.06 Comment s Calculation used DF65.1 / (ST5_T&D Dist End Use Customers) , DF65.2 / (ST5_T&D Dist End Use Customers) , DF65.3 / (ST5_T&D Dist End Use Customers) , DF65.4 / (ST5_T&D Dist End Use Customers) , DF65.5 / (ST5_T&D Dist End Use Customers) Page37 2014 T&D: Dist Substation Financials OTHER ACTIVITY BASED COSTS: DISTRIBUTION SUBSTATION O&M Calculation used DF66.1 ID 31 33 23 38 24 21 30 27 34 32 Response Training and R&D not applicable VM including mowing and landscape. na Not applicable O&M associated with New Customers and Construction N/A Administration, Landscape Maint, Order Material, Inspections, Rodent Proofing Substation training & staff Not applicable Page38 2014 T&D: Dist Substation Financials CWIP AS A % OF CAPITAL EXPENDITURES - DISTRIBUTION SUBSTATION Mean Quartile Mean 118.9 % Quartile 1 31.9 % Quartile 2: 55.7 % Quartile 3: 135.8 % Comment s Calculation used DF85.2 / DF10.5 * 100 Page39 2014 T&D: Dist Substation Financials FERC VS ACTIVITY SPENDING: DISTRIBUTION SUBSTATION O&M PER ASSET [V.14] Comment s #22, 24,25 did not report activity cost Calculation used DF30.5 / DF70.2 * 100 , (DF65_ABC Dist Sub O&M v.14) / DF70.2 * 100 Page40 2014 T&D: Dist Substation Financials FERC VS ACTIVITY SPENDING: DISTRIBUTION SUBSTATION CAPITAL PER ASSET [V.14] Comment s Calculation used DF10.5 / DF70.2 * 100 , (DF55_Dist Subs Cap ABC v.14) / DF70.2 * 100 Page41 2014 T&D: Dist Substation Financials DEPRECIATION EXPENSE AS A PERCENT OF ASSETS: DISTRIBUTION SUBSTATIONS Mean Quartile Mean Quartile 1 Quartile 2: Quartile 3: Comment s Calculation used DF80.2 / DF70.2 * 100 Page 4 2.20 % 1.81 % 2.25 % 2.55 % Distribution Substation: Capital Spending 2013 saw an increased spending level… 2010YE Q2 5.5% 2011YE Q2 4.5% 2012YE Q2 4.24% 2013YE Q2 5.56% Less Serve New: Subtotal: Sustain & Cap Adds Less Capacity Adds 1.9% 0.8% 2.07% 0.37% 3.6% 3.7% 2.17% 5.19% 1.4% 1.6% 0.08% 2.31% Subtotal: Sustain 2.2% 2.1% 2.09% 2.88% Total Capital 43 43 Panels exclude D-only companies Transmission sub Financial – Overview of the Cost Model 44 2014 T&D: Trans Substation Financials TRANSMISSION SUBSTATION O&M & CAPITAL SPENDING PER ASSET [FERC] Mean Quartile Mean 7.0 % Quartile 1 5.8 % Quartile 2: 6.6 % Quartile 3: 8.7 % Comments Some companies are distribution only or transmission only, only a few are T&D combined. Calculation used TF30.5 / TF65.2 * 100 , TF10.5 / TF65.2 * 100 Page45 2014 T&D: Trans Substation Financials TRANSMISSION SUBSTATION CAPITAL SPENDING PER ASSET [ACTIVITY-BASED] [V.14] Mean Quartile Mean 7.41 % Quartile 1 11.50 % Quartile 2: 5.60 % Quartile 3: 3.83 % Comment s Calculation used TF50.1 / TF65.2 * 100 , TF50.2 / TF65.2 * 100 , TF50.3 / TF65.2 * 100 , TF50.1 / TF65.2 * 100 , TF50.5 / TF65.2 * 100 , TF50.4 / TF65.2 * 100 , TF50.6 / TF65.2 * 100 Page46 2014 T&D: Trans Substation Financials TRANSMISSION SUBSTATION CAPITAL SPENDING EX SERVE NEW, EXPAND PER ASSET [ACTIVITY- BASED] [V.14] Mean Quartile Mean 2.80 % Quartile 1 4.12 % Quartile 2: 2.37 % Quartile 3: 1.19 % Comment s Calculation used 1 / ( TF50.1 - TF50.1 ) , 1 / ( TF50.2 - TF50.2 ) , TF50.3 / TF65.2 * 100 , TF50.1 / TF65.2 * 100 , TF50.5 / TF65.2 * 100 , TF50.4 / TF65.2 * 100 , TF50.6 / TF65.2 * 100 Page47 2014 T&D: Trans Substation Financials OTHER ACTIVITY BASED COSTS: TRANSMISSION SUBSTATIONS CAPITAL SPENDING Calculation used TF51.1 ID 31 33 23 38 24 21 30 27 32 Response Capital Tools, R&D, Premise Equipment, Facilities not applicable NA Environmental/Legislative/Regulatory not applicable n/a N/A Substation security Not applicable Page48 2014 T&D: Trans Substation Financials TRANSMISSION SUBSTATION O&M EXPENSE PER ASSETS [ACTIVITY-BASED] [V.14] Mean Quartile Mean 0.90 % Quartile 1 0.57 % Quartile 2: 0.96 % Quartile 3: 1.06 % Comment s #40 has high sub operations expense Calculation used TF60.1 / TF65.2 * 100 , TF60.2 / TF65.2 * 100 , TF60.1 / TF65.2 * 100 , TF60.1 / TF65.2 * 100 , TF60.3 / TF65.2 * 100 Page49 2014 T&D: Trans Substation Financials CWIP AS A % OF CAPITAL EXPENDITURES - TRANSMISSION SUBSTATION Mean Quartile Mean 80.1 % Quartile 1 25.2 % Quartile 2: 48.5 % Quartile 3: 115.4 % Comment s Calculation used TF80.2 / TF10.5 * 100 Page50 2014 T&D: Trans Substation Financials FERC VS ACTIVITY SPENDING: TRANSMISSION SUBSTATION O&M PER ASSET [V.14] Comment s #25,359,37 Did not report T-Sub Activity O&M #21 Activity >>FERC Calculation used TF30.5 / TF65.2 * 100 , (TF60_ABC Trans Sub O&M v.14) / TF65.2 * 100 Page51 2014 T&D: Trans Substation Financials FERC VS ACTIVITY SPENDING: TRANSMISSION SUBSTATION CAPITAL PER ASSET [V.14] Comment s #25,37 did not report activity Calculation used TF10.5 / TF65.2 * 100 , (TF50_ABC Trans Subs Cap v14) / TF65.2 * 100 2014 T&D: Trans Substation Financials DEPRECIATION EXPENSE AS A PERCENT OF ASSETS: TRANSMISSION SUBSTATION Mean Quartile Mean 2.01 % Quartile 1 1.90 % Quartile 2: 2.06 % Quartile 3: 2.21 % Comment s Calculation used TF75.2 / TF65.2 * 100 Page53 Transmission Substations: Capital Spending 2013 saw a slightly reduced level of transmission substation overall spending, but an increase in sustain activity. 2010YE Q2 2011YE Q2 2012YE Q2 2013YE Q2 Total Capital 7.0% 7.9% 6.16% 5.74% Less Serve New Subtotal: Sustain & Cap Adds Less Capacity Adds 1.6% 0.7% 1.12% 0.47% 5.4% 7.2% 5.04% 5.27% 2.9% 3.8% 3.14% 2.16% Subtotal: Sustain 2.5% 3.4% 1.90% 3.11% 54 54 Substation Practices and Initiatives 55 AGING ASSETS A PROBLEM FOR ASSET MANAGERS Aug 11, 2014 T&D World magazine conducted the expansive research, collecting data from June 5-9, 2014, and 685 respondents representing T&D managers and engineers working in construction, maintenance, operations and engineering. The report looks at all the of the main issues professionals are facing including aging assets, equipment and technology investments, upgrading capacity vs. lessening susceptibility, power delivery system redesign plans. Some interesting statistics: •The majority are investing in diagnostic equipment (66%), while 52% are installing outage management systems. Far fewer are looking at self-healing circuits (21%). •A third of respondents (34%) report their utilities are planning to redesign their power delivery systems within the next two years to accommodate distributed generation, including 16% who plan to do so within the next year. •Respondent attitudes are divided with regard to whether or not it would make sense for their utilities to support the development of hybrid microgrids in order to take congestion off the utility grid while meeting local interests in being more independent: 28% believe this would make sense for their utilities, 35% believe it may, and 37% are doubtful. •Just under a third of respondents (29%) expressed a healthy interest in learning more about compliance with FERC Order 1000, which enables companies to compete against incumbent utilities and bid to deliver turnkey transmission to meet ISO requested transmission. Another 31% are moderately interested. 56 Potential for Terrorist Attack The U.S. could suffer a coast-to-coast blackout if saboteurs knocked out just nine of the country's 55,000 electrictransmission substations on a scorching summer day, according to a previously unreported federal analysis. Gunmen attacked transformers at PG&E's Metcalf substation near San Jose, Calif., last year, putting it out of service for almost a month. Talia Herman for The Wall Street Journal 57 A Process Model for Managing the Network Add New Customers Expand Network Respond to Emergencies Operate Network Sustain Network Project/Portfolio Management Develop and Approve Asset Plans Develop Network Strategy 58 Substation Practices/initiatives section 2013 Sections 2014 Proposed by Process ◼ Asset Management – RCM and Life cycle ◼ Asset Management costing approaches; replacement programs, ◼ Strategy and problematic equipment Substation automation ◼ Planning/Engineering/Design –Changes to Mobile spares standards ◼ Sustain Substations ◼ Substation Automation – Technology and Maintenance planning initiatives underway Field maintenance ◼ Job Estimating – Software tools and role of Including NERC standards construction Replacement/upgrades ◼ Mobiles/Spares – Deployment of mobiles and ◼ Expand Substations spare, and optimization techniques Planning/Engineering/Design ◼ Field Maintenance Activities – Initiatives Job estimating underway, degree of crew specialization, and Field Construction work management systems ◼ NERC Maintenance Standards – Impact of NERC standards on substation maintenance ◼ Maintenance – Inspections, impact of deferred maintenance, initiatives to reduce outages 59 Substation practice Questions 2014 Proposed by Process ◼ Asset Management ◼ Strategy Substation automation Mobile spares ◼ Sustain Substations Maintenance planning Field maintenance Including NERC standards Replacement/upgrades ◼ Expand Substations Planning/Engineering/ Design Job estimating Field Construction Asset Management (AM) • Role of the Asset Management organization in decision making • Key responsibilities of the Substation AM organization • What keeps you up at night worrying about your system • Analytic approaches used to predict replacement needs • Use of concepts embodied in RCM in Subs • Use of the concepts embodied in 'Life Cycle Costing' • Use predictive reliability analysis tools on component failure rates • Replacement Programs Underway: Power Transformers; Switch Gear; Circuit Breakers; Relays; Instrument Transformers; Secondary/Communications • Classes of equipment that are becoming problematic • Other Classes of equipment that are becoming problematic • Use of dedicated software tools to support substation AM 60 1QC Industry Perspective: Substations Situation • Technology changes are moving faster in substations than elsewhere in T&D • Regulation changes have impacted substation operations • Workforce aging and knowledge transfer are significant issues • Plan to Build Process Complication Question • NERC maintenance standards are imposing additional • What are substation organizations doing requirements to meet the • Equipment challenges? obsolescence is an issue with new digital equipment replacing older components • Protracted permitting can create project delays • Reliability requirements continue to increase Answer •Asset Management to optimize life cycle costs and reliability •Strategic Planning Improving the design and construction process • More sophisticated maintenance programs, driven by analytics around economics as well as equipment failure analysis. 61 Key Success Factors: Manage assets Identify risk factors; aging equipment and reduced maintenance budgets are concerns. Use Reliability Centered Maintenance (RCM) concepts Set replacement cycles using condition and failurebased approaches Strengthen Asset Management Role; can include strategy, policy, analytics, prioritization, and management Use predictive analysis tools focusing on component failures and customer reliability metrics. 62 2014 T&D: Substations WHAT KEEPS YOU UP AT NIGHT WORRYING ABOUT YOUR SYSTEM ID 31 28 33 37 38 40 24 Response Knowledge Transfer and the development of field personnel continues to be a major problem as the tenured work force leaves. Safety, theft, our ability to manage the reliability of all the software/firmware/settings associated with microprocessor control equipment. Trans bank failures, relay misoperations Aging infrastructure coupled with limited resources to address Maintaining a good maintenance program AND meeting O&M targets. Older equipment (Reliability) and lack of spare parts or vendor support. Electromechanical relays. 27 The increasing age, deteriorating condition, and decreasing reliability of several classes of equipment in the system - despite continuing efforts at cost effective Condition Based Maintenance (CBM). Aging equipment Substations without internal T- line protection, aging infrastructure, incomplete and inaccurate asset history and maintenance data Aging equipment, EHV transformer failure, large customers with single source transformer 359 32 Aging assets and unexpected failures. Loss of AY autobank or RR autobank 1 until new RR autobank 2 is in service 21 30 Calculation used SP10.1 Page 6 2014 T&D: Substations ANALYTIC APPROACHES USED TO PREDICT REPLACEMENT NEEDS ID 22 31 28 33 23 37 38 40 21 30 27 359 32 Calculation used SP15.1 Response Condition health assesment in Cascade Condition/operational monitoring, equipment history, environment issues MTBF (mean time between failures) is a key metric . Our Sustain Investment Model looks at groups of assets, anticipated lifetimes, historical performance to determine an evergreen investment program over multiple decades. Using cascade we've identified replacement criteria by asset category. We use manufacture recommendations and industry standards Failure history, performance, maintenance requirements and grid criticality. Past failure trending, industry benchmarking and trending, trending of test data Proprietary models by equipment class to determine replacement order. Costs, trips per line, age of equipment, availability of spare parts and support. Infrared, test results. Data from worst performing circuits, track failure rates by equipment types and cause. We are developing a risk based maintenance strategy to drive replacement needs that will take into consideration probability of failure (health), consequence of failure (criticality) and life cycle costing considerations. Transformer criticality spreadsheet that factors in customer base, average loading, emergency ties, and transformer DGA test results. We take historical hazard/survival rates for each particular asset classification into consideration when determining overall operational risk to the organization Power factor testing, DGA, and trends of like equipment. For long range planning, look at population models and how the age is varying with time. For individual components, use health index and criticality of the asset. Mean time between failures, life expectancy, fleet analysis, previous inspection findings (eg wood pole test/treat reject rates). TRANS - 1) DGA 2) Doble test, megger test, etc. 4) Difficulty in buying replacement parts 5) Maintenance history Page 6 2014 T&D: Substations ANALYTIC APPROACHES USED TO PREDICT REPLACEMENT NEEDS PSEG 24 Our Computerized Maintenance Management System (CMMS) provides the means for optimizing the maintenance of our assets through the use of condition - based tools. • It is a decision support system that assists in making repair/replace/maintain decisions. •The CBM implementation strategy through CMMS requires the comprehensive integration of data from multiple systems. These systems include but are not limited to OMSto gather weekly inspection data, delivery work management (DWMS) to gather diagnostic data collection from field personnel, system and equipment operational data, equipment test data, and on - line equipment monitoring data. • This system utilizes available information on equipment health by incorporating it into the maintenance decision process. Algorithms have been set up to provide ranking systems for all major equipment. The algorithm factors are based on the data available for each particular asset, and the factor weightings vary between voltage classes. •The Action Algorithms provide a score for each asset, with those most in need of review and/or action scoring the highest. Replacement Algorithms are used to help identify equipment advancing towards completion of useful life. The algorithms are periodically reviewed and adjusted to keep them on track in identifying equipment maintenance needs. 2014 T&D: Substations USE OF CONCEPTS EMBODIED IN 'RELIABILITY CENTERED MAINTENANCE' IN SUBSTATIONS ID 22 31 28 Response Maintenance tempaltes use failure modes to determine appropriate PM taslks Set frequencies of maintenance, required test performed We use function, criticality, and condition monitoring to establish our maintenance programs. 33 we look at equip category failure history by manufacture, age, duty cycle to help predict future replacement criteria. 23 Targeting worse performers, reviewing failure modes and customer impacts and the risk to grid on run to failure scenarios. 37 Gone to condition base versus time based maintenance on some assets. Adjusted maintenance intervals and tasks based on performance. Prioritized spending on maintenance 38 Monitor critical parameters and replace the worst first. Use equipment condition wherever possible. 40 Specific reads on inspection triggers 21 Used to determine the proper maintenance strategy for assets. In addition, used to drive some equipment upgrades and/or reliability improvement projects. We are not heavily involved in RCM currently. 27 Criticality, impact, failure modes, cost of assets used to determine maintenance cycles 359 For replacement strategy, look at multiple inputs to make decisions, not just one, such as age Page 6 USE OF CONCEPTS EMBODIED IN 'RELIABILITY CENTERED MAINTENANCE' IN SUBSTATIONS PSEG 24 32 Reliability Centered Maintenance (RCM), or Condition - Based Maintenance (CBM), is a proactive equipment maintenance capability that uses system health indications to identify and predict functional failure in advance of the event and provide the ability to take appropriate preventive action. This approach to maintenance uses data drawn during operations and/or maintenance intervals to forecast the need for additional or future maintenance. It extends the concepts of predictive maintenance by using data from maintenance tests. Ideally condition - based maintenance will allow maintenance personnel to locate and resolve asset functionality issues before they escalate, minimizing corrective maintenance costs and system downtime. TRANS - All major eqipment is routinely maintained on a time based system. Maintenance intervals are based on a combination of generally accepted industry practice, performance history, age of equipment, and to some degree the criticality of the equipment. Nonroutine maintenance is performed as required. 2014 T&D: Substations USE PREDICTIVE RELIABILITY ANALYSIS Calculation used SP30.1 ID 31 28 33 23 38 40 24 Response TORT - Transmission operational data Yes, Asset Health Index (AHI) and Strategic Asset Management (SAM) tools part of the EPS - M UtiliCase. no We track SAIDI, SAIFI, CAIDI as they relate to transmission line,station and feeder performance. We analyze each incident that we encounter and search for the problem as a part of our equipment failure reporting in an attempt to identify and share failure modes and equipment issues that need to be addressed on other infrastructure of the same type. Key metrics are used to verify effectiveness of improvement projects. We use SAIFI and SAIDI that helps us to predict and determine reliability issues on our transmission lines and helps to determine replacement priorities. Component failure rate information (as available) is used to recommend budgetary needs for equipment replacements required to maintain system reliability. Specific candidates for equipment replacement are determed by condition assessment review. Substation design philosophy includes redundancy and reliability considerations to minimize impact of 21 Substation equipment failures on customer reliability metrics such as SAIFI and CAIDI. Not sure what you are looking for with this question. Page 6 2014 T&D: Substations USE OF DEDICATED SOFTWARE TOOLS TO SUPPORT SUBSTATION ASSET MANAGEMENT Calculation used SP45.1 ID 22 31 33 23 37 38 40 21 30 27 Response Cascade Davies AIS tool for investment prioritization. SAP/BI for asset life cycle analytics. digital inspections, cascade, 4 years, full inventory, and complete maintenance functionality. Maximo 7.5 since May 2013. Asset warehouse & maintenance system. Maximo - last updated in 2009 provides asset tracking and cost analysis '1) TOA(Transformer Oil Analysis) Delta X Research 16 years CASCADE - Tracks maintenance tasks results and history of equipment. Cascade 2 - 1/2 years, Powerbase 6 months EMPAC (Indus) 1994 We have used Maximo by IBM for 2 years. It holds are maintenance records & is work manangement 359 Digital Inspections - CASCADE 3.31, Substation and LTN Inventory and Preventative Maintenance Management. 32 TRANS - MAXIMO used for creating and storing job plans, test data. Automatically generates work orders for all time based maintenance activities. Any unscheduled maintenance is planned through MAXIMO and records kept. Page69 USE OF DEDICATED SOFTWARE TOOLS TO SUPPORT SUBSTATION ASSET MANAGEMENT 28 1) NERC Audit & Report, in - house, 4 years, Management of work orders, schedule, compliance. 2) EPS - M (Utili - Case), 5 years, Asset Analytics, Asset Information, Asset Performance, Algorithms used to provide the 30 years System Investment Management profile, and Reporting. 3) Asset Health Index (AHI), 10 years, Report provides full of results data on the condition and estimated remaining life of assets in the BC Hydro transmission and distribution system (T&D), including substation assets (Stations). 4) Asset Needs and Risk Register (in -house), 2 years, integrated planning and risk register tool for both long term (20 -30 years) and short - term (2- 10 years) assets/system needs. 24 The CMMS system discussed in SP15 is an internally developed software platform that is used to integrate data from multiple sources and apply internally generated condition assessmemnt algorithms to rank all assets in terms of need for maintenance and/or replacement. The sources include characterisitic and cost information from SAP, loading and other system condition data maintained in a PI historical data warehouse, weekly inspection data input from hand - held mobile devices, on- line monitoring devices (such as gas - in - oil monitors for transformers), and laboratory diagnostic field test databases maintained by our Test Laboratory. 2014 T&D: Substations SUBSTATION STANDARDS CHANGED RECENTLY AND WHY ID Response 31 Meet with user groups to identify required standards needs 28 Planning, Design, and Commissioning standards have changed recently to provide consistency with third party service providers and alignment with Safety - by - Design principles. 33 Complete standards revision began in 2013 for update our maintenance practices. 37 Application of substation safety signs to comply with latest version of ANSI/NESC. Relay standards updated Capacitor Protection guide, Alarm guide, Cyber security guide. Breaker standard updated to include magnetic actuators (new technology for us) and battery standard updated per periodic review 40 Relay Maint. and Const. for updated supplements to PRC - 005 of 001b, 002, and 003. Updated transformer and breaker specifications; Protection System Maintenance Plan 21 Transformers, SF6 Breakers 30 None Page71 SUBSTATION STANDARDS CHANGED RECENTLY AND WHY 27 We require our 13.8kV switchgear to be arc resistant type 2B rated for increased crew safety while racking the breakers in and out. We added card readers to PDC buildings and added building access, building temperature and fire alarms to our SCADA system to better monitor and control building access and decrease response time in the event of a fire. We automated the drive - through gate with card reader control at new substations with the open and closed positions reported to SCADA to monitor and control access to the substation. We also install a manual locked man gate to be used if the automated gate does not operate. We revised our transformer specifications to inlcude transformer monitioring equipment from Dynamics Ratings 359 We are in the process of 'overhauling' all of our Standards for Transmission and Substations. Currently we revised the 230/69 kV entire substation standard and created a manual. The manual consist of Standard design intent, design criteria, relay design intent, relay and control acceptable devices and protection requirements, Construction work and bid template and testing and commissioning requirements. This manual will be a model to be used when doing the 500 and 69/12 kV substations, which we intend to have done by the end of the year. We are also updating our entire grounding standards for all substations. We have also updated our equipment specifications to include more industry proven devices that will help move us from time based maintenance to a condition based maintenance approach. For instance we now require on - line DGA devices to eliminate employees from taking samples every 6 months on our transformers. We are also using bushing monitoring devices for our transformers to move away from Doble testing. 2014 T&D: Substations IDENTIFY ANY SOFTWARE PRODUCTS USED OR BEING EVALUATED FOR SUBSTATION JOB ESTIMATING Calculation used SP60.1 ID Response 22 None 31 Internally developed excel spreadsheets 28 We are currently using Excel for estimating and @Risk for Monte- Carlos analysis. We are also evaluating ???U.S Cost?? and HeavyBid estimating software for future use. 33 in house estimating program 23 Spreadsheets and in house software tool. 37 Maximo and Business Objects 38 none 40 Maximo & Excel 21 Cascade 30 Excel 27 Microsoft Excel 359 Excel; Bulk Power Estimator (internally developed tool) 32 No Software Page73 Key Success Factors: Maintenance programs Understand and comply with NERC requirements Conduct regular inspections, and analyze the results to drive maintenance activity Review inspection program and maintenance cycles, using advanced analytic tools Coordinate maintenance activity with the asset management function, to get the most from both maintenance and capital replacement . Use mobile spares to reduce outage durations 74 2014 T&D: Substations Power Transformers Switch Gear Circuit Breakers Relays Instrument Transformers SecondaryCommunications Other 87% 67% 93% 80% 60% 60% 40% Calculation used SP35.1 , SP35.2 , SP35.3 , SP35.4 , SP35.5 , SP35.6 , SP35.7 Legends Power Transformers ♦ Switch Gear ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ Relays ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ Instrument Transformers SecondaryCommunication s Other ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ Circuit Breakers ♦ ♦ ♦ ♦ ♦ ♦ ♦ Page 7 ♦ Partial Table SUBSTATION REPLACEMENT SUBSTATION REPLACEMENT PROGRAMS POWER TRANSFORMERS ID# I nstrument Transformers Secondary Communications Switch Gear Circuit Breakers Relays Life Cycle Replacement 24 Program based on condition Life Cycle Replacement Program based on condition Life Cycle Replacement Program based on condition As needed of As needed enhance functionality As needed Replace transformers based 27 upon transformer index rating Replacing switch gear with PDC or free standing breaker. (several a year) Replace 5 - 10 OCB's each year Electromechanical relays are being replaced. upon failure Microwave radios are being replaced. Replacing airblast breakers and associated compressor systems. Dual pressure SF6 and bulk oil breakers are also being replaced. Electromechanical relays are being replaced with microprocessor based relays. Proactive replacement program. 1. Batteries and chargers, 2. Tone and test panels. 3. Microwave links are being converted from analog to digital and MPLS. Poor performing models proactive Automation/installatio n of electronic relays FBS breakers replacement continues and micro - processor upgrades Continue SCADA RTU replacements OCB, Airblast, high SF6 leak rate Electro - mechanical None At fialure;not supported by vendor;or as required to meet project specs Driven by capacity needs and failures Driven by capacity needs and failures Replaced when End - of - life 28 loading exceeds replacements. capacity or on failure. 30 Split winding 50MVA units proactive 31 Yes 32 Replace on loading or testing 37 Driven by capacity needs and failures Yes - nearly completed None 76 Substation Practices and Initiatives 77 AGING ASSETS A PROBLEM FOR ASSET MANAGERS Aug 11, 2014 T&D World magazine conducted the expansive research, collecting data from June 5-9, 2014, and 685 respondents representing T&D managers and engineers working in construction, maintenance, operations and engineering. A majority of T&D professionals reported that their companies are addressing aging assets (65%), followed by the use of smart meters feeding outage management systems (42%), according to a new survey sponsored by Burns & McDonnell. (http://tdworld.com/sitefiles/tdworld.com/files/uploads/2014/08/BurnsMcDonnellSurvey.pdf) T&D World magazine conducted the expansive research, collecting data from June 5-9, 2014, and 685 respondents representing T&D managers and engineers working in construction, maintenance, operations and engineering. The report looks at all the of the main issues professionals are facing including aging assets, equipment and technology investments, upgrading capacity vs. lessening susceptibility, power delivery system redesign plans. Some interesting statistics: •The majority are investing in diagnostic equipment (66%), while 52% are installing outage management systems. Far fewer are looking at self-healing circuits (21%). •A third of respondents (34%) report their utilities are planning to redesign their power delivery systems within the next two years to accommodated distributed generation, including 16% who plan to do so within the next year. •Respondent attitudes are divided with regard to whether or not it would make sense for their utilities to support the development of hybrid microgrids in order to take congestion off the utility grid while meeting local interests in being more independent: 28% believe this would make sense for their utilities, 35% believe it may, and 37% are doubtful. •Just under a third of respondents (29%) expressed a healthy interest in learning more about compliance with FERC Order 1000, which enables companies to compete against incumbent utilities and bid to deliver turnkey transmission to meet ISO requested transmission. Another 31% are moderately interested. 78 Potential for Terrorist Attack The U.S. could suffer a coast-to-coast blackout if saboteurs knocked out just nine of the country's 55,000 electrictransmission substations on a scorching summer day, according to a previously unreported federal analysis. Gunmen attacked transformers at PG&E's Metcalf substation near San Jose, Calif., last year, putting it out of service for almost a month. Talia Herman for The Wall Street Journal 79 A Process Model for Managing the Network Add New Customers Expand Network Respond to Emergencies Operate Network Sustain Network Project/Portfolio Management Develop and Approve Asset Plans Develop Network Strategy 80 Substation Practices/initiatives section 2013 Sections 2014 Proposed by Process ◼ Asset Management – RCM and Life cycle ◼ Asset Management costing approaches; replacement programs, ◼ Strategy and problematic equipment Substation automation ◼ Planning/Engineering/Design –Changes to Mobile spares standards ◼ Sustain Substations ◼ Substation Automation – Technology and Maintenance planning initiatives underway Field maintenance ◼ Job Estimating – Software tools and role of Including NERC standards construction Replacement/upgrades ◼ Mobiles/Spares – Deployment of mobiles and ◼ Expand Substations spare, and optimization techniques Planning/Engineering/Design ◼ Field Maintenance Activities – Initiatives Job estimating underway, degree of crew specialization, and Field Construction work management systems ◼ NERC Maintenance Standards – Impact of NERC standards on substation maintenance ◼ Maintenance – Inspections, impact of deferred maintenance, initiatives to reduce outages 81 Substation practice Questions 2014 Proposed by Process ◼ Asset Management ◼ Strategy Substation automation Mobile spares ◼ Sustain Substations Maintenance planning Field maintenance Including NERC standards Replacement/upgrades ◼ Expand Substations Planning/Engineering/ Design Job estimating Field Construction Asset Management (AM) • Role of the Asset Management organization in decision making • Key responsibilities of the Substation AM organization • What keeps you up at night worrying about your system • Analytic approaches used to predict replacement needs • Use of concepts embodied in RCM in Subs • Use of the concepts embodied in 'Life Cycle Costing' • Use predictive reliability analysis tools on component failure rates • Replacement Programs Underway: Power Transformers; Switch Gear; Circuit Breakers; Relays; Instrument Transformers; Secondary/Communications • Classes of equipment that are becoming problematic • Other Classes of equipment that are becoming problematic • Use of dedicated software tools to support substation AM 82 1QC Industry Perspective: Substations Situation • Technology changes are moving faster in substations than elsewhere in T&D • Regulation changes have impacted substation operations • Workforce aging and knowledge transfer are significant issues • Plan to Build Process Complication Question • NERC maintenance standards are imposing additional • What are substation organizations doing requirements to meet the • Equipment challenges? obsolescence is an issue with new digital equipment replacing older components • Protracted permitting can create project delays • Reliability requirements continue to increase Answer •Asset Management to optimize life cycle costs and reliability •Strategic Planning Improving the design and construction process • More sophisticated maintenance programs, driven by analytics around economics as well as equipment failure analysis. 83 Key Success Factors: Manage assets Identify risk factors; aging equipment and reduced maintenance budgets are concerns. Use Reliability Centered Maintenance (RCM) concepts Set replacement cycles using condition and failurebased approaches Strengthen Asset Management Role; can include strategy, policy, analytics, prioritization, and management Use predictive analysis tools focusing on component failures and customer reliability metrics. 84 2014 T&D: Substations Substa tion WHAT KEEPS YOU UP AT NIGHT WORRYING ABOUT YOUR SYSTEM ID 31 28 33 37 38 40 24 Response Knowledge Transfer and the development of field personnel continues to be a major problem as the tenured work force leaves. Safety, theft, our ability to manage the reliability of all the software/firmware/settings associated with microprocessor control equipment. Trans bank failures, relay misoperations Aging infrastructure coupled with limited resources to address Maintaining a good maintenance program AND meeting O&M targets. Older equipment (Reliability) and lack of spare parts or vendor support. Electromechanical relays. 27 The increasing age, deteriorating condition, and decreasing reliability of several classes of equipment in the system - despite continuing efforts at cost effective Condition Based Maintenance (CBM). Aging equipment Substations without internal T- line protection, aging infrastructure, incomplete and inaccurate asset history and maintenance data Aging equipment, EHV transformer failure, large customers with single source transformer 359 32 Aging assets and unexpected failures. Loss of AY autobank or RR autobank 1 until new RR autobank 2 is in service 21 30 Calculation used SP10.1 Page 8 2014 T&D: Substations ANALYTIC APPROACHES USED TO PREDICT REPLACEMENT NEEDS ID 22 31 28 33 23 37 38 40 21 30 27 359 32 Response Condition health assesment in Cascade Condition/operational monitoring, equipment history, environment issues MTBF (mean time between failures) is a key metric . Our Sustain Investment Model looks at groups of assets, anticipated lifetimes, historical performance to determine an evergreen investment program over multiple decades. Using cascade we've identified replacement criteria by asset category. We use manufacture recommendations and industry standards Failure history, performance, maintenance requirements and grid criticality. Past failure trending, industry benchmarking and trending, trending of test data Proprietary models by equipment class to determine replacement order. Costs, trips per line, age of equipment, availability of spare parts and support. Infrared, test results. Data from worst performing circuits, track failure rates by equipment types and cause. We are developing a risk based maintenance strategy to drive replacement needs that will take into consideration probability of failure (health), consequence of failure (criticality) and life cycle costing considerations. Transformer criticality spreadsheet that factors in customer base, average loading, emergency ties, and transformer DGA test results. We take historical hazard/survival rates for each particular asset classification into consideration when determining overall operational risk to the organization Power factor testing, DGA, and trends of like equipment. For long range planning, look at population models and how the age is varying with time. For individual components, use health index and criticality of the asset. Mean time between failures, life expectancy, fleet analysis, previous inspection findings (eg wood pole test/treat reject rates). TRANS - 1) DGA 2) Doble test, megger test, etc. 4) Difficulty in buying replacement parts 5) Maintenance history Calculation used SP15.1 Page 8 2014 T&D: Substations ANALYTIC APPROACHES USED TO PREDICT REPLACEMENT NEEDS PSEG 24 Our Computerized Maintenance Management System (CMMS) provides the means for optimizing the maintenance of our assets through the use of condition - based tools. • It is a decision support system that assists in making repair/replace/maintain decisions. •The CBM implementation strategy through CMMS requires the comprehensive integration of data from multiple systems. These systems include but are not limited to OMSto gather weekly inspection data, delivery work management (DWMS) to gather diagnostic data collection from field personnel, system and equipment operational data, equipment test data, and on - line equipment monitoring data. • This system utilizes available information on equipment health by incorporating it into the maintenance decision process. Algorithms have been set up to provide ranking systems for all major equipment. The algorithm factors are based on the data available for each particular asset, and the factor weightings vary between voltage classes. •The Action Algorithms provide a score for each asset, with those most in need of review and/or action scoring the highest. Replacement Algorithms are used to help identify equipment advancing towards completion of useful life. The algorithms are periodically reviewed and adjusted to keep them on track in identifying equipment maintenance needs. 2014 T&D: Substations USE OF CONCEPTS EMBODIED IN 'RELIABILITY CENTERED MAINTENANCE' IN SUBSTATIONS ID 22 31 28 Response Maintenance tempaltes use failure modes to determine appropriate PM taslks Set frequencies of maintenance, required test performed We use function, criticality, and condition monitoring to establish our maintenance programs. 33 we look at equip category failure history by manufacture, age, duty cycle to help predict future replacement criteria. 23 Targeting worse performers, reviewing failure modes and customer impacts and the risk to grid on run to failure scenarios. 37 Gone to condition base versus time based maintenance on some assets. Adjusted maintenance intervals and tasks based on performance. Prioritized spending on maintenance 38 Monitor critical parameters and replace the worst first. Use equipment condition wherever possible. 40 Specific reads on inspection triggers 21 Used to determine the proper maintenance strategy for assets. In addition, used to drive some equipment upgrades and/or reliability improvement projects. We are not heavily involved in RCM currently. 27 Criticality, impact, failure modes, cost of assets used to determine maintenance cycles 359 For replacement strategy, look at multiple inputs to make decisions, not just one, such as age Page 8 USE OF CONCEPTS EMBODIED IN 'RELIABILITY CENTERED MAINTENANCE' IN SUBSTATIONS PSEG 24 32 Reliability Centered Maintenance (RCM), or Condition - Based Maintenance (CBM), is a proactive equipment maintenance capability that uses system health indications to identify and predict functional failure in advance of the event and provide the ability to take appropriate preventive action. This approach to maintenance uses data drawn during operations and/or maintenance intervals to forecast the need for additional or future maintenance. It extends the concepts of predictive maintenance by using data from maintenance tests. Ideally condition - based maintenance will allow maintenance personnel to locate and resolve asset functionality issues before they escalate, minimizing corrective maintenance costs and system downtime. TRANS - All major eqipment is routinely maintained on a time based system. Maintenance intervals are based on a combination of generally accepted industry practice, performance history, age of equipment, and to some degree the criticality of the equipment. Nonroutine maintenance is performed as required. 2014 T&D: Substations USE PREDICTIVE RELIABILITY ANALYSIS Calculation used SP30.1 ID 31 28 33 23 38 40 24 Response TORT - Transmission operational data Yes, Asset Health Index (AHI) and Strategic Asset Management (SAM) tools part of the EPS - M UtiliCase. no We track SAIDI, SAIFI, CAIDI as they relate to transmission line,station and feeder performance. We analyze each incident that we encounter and search for the problem as a part of our equipment failure reporting in an attempt to identify and share failure modes and equipment issues that need to be addressed on other infrastructure of the same type. Key metrics are used to verify effectiveness of improvement projects. We use SAIFI and SAIDI that helps us to predict and determine reliability issues on our transmission lines and helps to determine replacement priorities. Component failure rate information (as available) is used to recommend budgetary needs for equipment replacements required to maintain system reliability. Specific candidates for equipment replacement are determed by condition assessment review. Substation design philosophy includes redundancy and reliability considerations to minimize impact of 21 Substation equipment failures on customer reliability metrics such as SAIFI and CAIDI. Not sure what you are looking for with this question. Page 9 2014 T&D: Substations Substa MOVE UP tion REPLACEMENT PROGRAMS UNDERWAY: SUBSTATIONS Comments Total Respondents Power Transformers 15 86.67% Switch Gear 66.67% Circuit Breakers 93.33% Calculation used SP35.1 , SP35.2 , SP35.3 , SP35.4 , SP35.5 , SP35.6 , Relays SP35.7 Instrument Transformers Legends SecondaryCommunications Power Transformers Switch Gear Other Circuit Breakers ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ Relays ♦ ♦ ♦ ♦ ♦ Instrument Transformers SecondaryCommunication s Other ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ 80% 60% 60% ♦ ♦ 40% ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ Page 9 ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ 2014 T&D: Substations USE OF DEDICATED SOFTWARE TOOLS TO SUPPORT SUBSTATION ASSET MANAGEMENT Calculation used SP45.1 ID 22 31 33 23 37 38 40 21 30 27 Response Cascade Davies AIS tool for investment prioritization. SAP/BI for asset life cycle analytics. digital inspections, cascade, 4 years, full inventory, and complete maintenance functionality. Maximo 7.5 since May 2013. Asset warehouse & maintenance system. Maximo - last updated in 2009 provides asset tracking and cost analysis '1) TOA(Transformer Oil Analysis) Delta X Research 16 years CASCADE - Tracks maintenance tasks results and history of equipment. Cascade 2 - 1/2 years, Powerbase 6 months EMPAC (Indus) 1994 We have used Maximo by IBM for 2 years. It holds are maintenance records & is work manangement 359 Digital Inspections - CASCADE 3.31, Substation and LTN Inventory and Preventative Maintenance Management. 32 TRANS - MAXIMO used for creating and storing job plans, test data. Automatically generates work orders for all time based maintenance activities. Any unscheduled maintenance is planned through MAXIMO and records kept. Page92 USE OF DEDICATED SOFTWARE TOOLS TO SUPPORT SUBSTATION ASSET MANAGEMENT 28 1) NERC Audit & Report, in - house, 4 years, Management of work orders, schedule, compliance. 2) EPS - M (Utili - Case), 5 years, Asset Analytics, Asset Information, Asset Performance, Algorithms used to provide the 30 years System Investment Management profile, and Reporting. 3) Asset Health Index (AHI), 10 years, Report provides full of results data on the condition and estimated remaining life of assets in the BC Hydro transmission and distribution system (T&D), including substation assets (Stations). 4) Asset Needs and Risk Register (in -house), 2 years, integrated planning and risk register tool for both long term (20 -30 years) and short - term (2- 10 years) assets/system needs. 24 The CMMS system discussed in SP15 is an internally developed software platform that is used to integrate data from multiple sources and apply internally generated condition assessmemnt algorithms to rank all assets in terms of need for maintenance and/or replacement. The sources include characterisitic and cost information from SAP, loading and other system condition data maintained in a PI historical data warehouse, weekly inspection data input from hand - held mobile devices, on- line monitoring devices (such as gas - in - oil monitors for transformers), and laboratory diagnostic field test databases maintained by our Test Laboratory. 2014 T&D: Substations SUBSTATION STANDARDS CHANGED RECENTLY AND WHY ID Response 31 Meet with user groups to identify required standards needs 28 Planning, Design, and Commissioning standards have changed recently to provide consistency with third party service providers and alignment with Safety - by - Design principles. 33 Complete standards revision began in 2013 for update our maintenance practices. 37 Application of substation safety signs to comply with latest version of ANSI/NESC. Relay standards updated Capacitor Protection guide, Alarm guide, Cyber security guide. Breaker standard updated to include magnetic actuators (new technology for us) and battery standard updated per periodic review 40 Relay Maint. and Const. for updated supplements to PRC - 005 of 001b, 002, and 003. Updated transformer and breaker specifications; Protection System Maintenance Plan 21 Transformers, SF6 Breakers 30 None Page94 SUBSTATION STANDARDS CHANGED RECENTLY AND WHY 27 We require our 13.8kV switchgear to be arc resistant type 2B rated for increased crew safety while racking the breakers in and out. We added card readers to PDC buildings and added building access, building temperature and fire alarms to our SCADA system to better monitor and control building access and decrease response time in the event of a fire. We automated the drive - through gate with card reader control at new substations with the open and closed positions reported to SCADA to monitor and control access to the substation. We also install a manual locked man gate to be used if the automated gate does not operate. We revised our transformer specifications to inlcude transformer monitioring equipment from Dynamics Ratings 359 We are in the process of 'overhauling' all of our Standards for Transmission and Substations. Currently we revised the 230/69 kV entire substation standard and created a manual. The manual consist of Standard design intent, design criteria, relay design intent, relay and control acceptable devices and protection requirements, Construction work and bid template and testing and commissioning requirements. This manual will be a model to be used when doing the 500 and 69/12 kV substations, which we intend to have done by the end of the year. We are also updating our entire grounding standards for all substations. We have also updated our equipment specifications to include more industry proven devices that will help move us from time based maintenance to a condition based maintenance approach. For instance we now require on - line DGA devices to eliminate employees from taking samples every 6 months on our transformers. We are also using bushing monitoring devices for our transformers to move away from Doble testing. 2014 T&D: Substations IDENTIFY ANY SOFTWARE PRODUCTS USED OR BEING EVALUATED FOR SUBSTATION JOB ESTIMATING Calculation used SP60.1 ID Response 22 None 31 Internally developed excel spreadsheets 28 We are currently using Excel for estimating and @Risk for Monte- Carlos analysis. We are also evaluating ???U.S Cost?? and HeavyBid estimating software for future use. 33 in house estimating program 23 Spreadsheets and in house software tool. 37 Maximo and Business Objects 38 none 40 Maximo & Excel 21 Cascade 30 Excel 27 Microsoft Excel 359 Excel; Bulk Power Estimator (internally developed tool) 32 No Software Page96 NEW Substation Automation Substation Automation Initiatives ID# RTU Replacement LTU position indicators Automation of station voltage regulators (to provide volt/var optimization) and feedback monitoring. Installing standard tap changer control systems compatible with volt/var optimization schemes. Replacing of the old 500kV stations fault recorders with new DFRs. Electromechanical relays are being replaced with microprocessor based relaying that provides enhanced functionalities. A multiyear plan is continuing to replace older units and 31 replace with units that will communicate with micro processor relays Smart Grid installations continue which incorporates transformer monitoring Process beginning on Auto LTC's to install transmitter module to inhibit LTC ranges on auto's near generation. We have a proactive plan to replace and/or install a specific number each year at key substations Relay protection upgrade projects continue to meet current ERCOT/NERC relay requirements 32 TRANS - None TRANS - Transformers are monitored. TRANS -Yes TRANS - In all switchyards TRANS - Replacement schedule is included in 20 year plan Multiyear SIRIUS Program to 37 replace Siemens 44550 RTU??s Pilot Breaker Monitoring program Integrated Digital Fault Recorders MICROPROCESSOR PROTECTIVE Facility Monitoring CONTROL Systems RELAYING Other SYSTEMS On-line monitoring Replacement of old RTUs with new 61850 compatible logic 28 control devices (between 10 20 devices per year). Video feeds and equipment monitoring cameras to provide N/A remote video monitoring system. TRANS - All control houses are monitored to varing degrees Implementation of Distributed Disturbance Monitoring System in accordance with PRC - 002 DME requirements. Also implementing Bitronics meters to replace aging Qualitrol (Hathaway) DFR??s 97 NEW Substation Replacement SUBSTATION REPLACEMENT PROGRAMS POWER TRANSFORMERS ID# I nstrument Transformers Secondary Communications Switch Gear Circuit Breakers Relays Life Cycle Replacement 24 Program based on condition Life Cycle Replacement Program based on condition Life Cycle Replacement Program based on condition As needed of As needed enhance functionality As needed Replace transformers based 27 upon transformer index rating Replacing switch gear with PDC or free standing breaker. (several a year) Replace 5 - 10 OCB's each year Electromechanical relays are being replaced. upon failure Microwave radios are being replaced. Replacing airblast breakers and associated compressor systems. Dual pressure SF6 and bulk oil breakers are also being replaced. Electromechanical relays are being replaced with microprocessor based relays. Proactive replacement program. 1. Batteries and chargers, 2. Tone and test panels. 3. Microwave links are being converted from analog to digital and MPLS. Poor performing models proactive Automation/installatio n of electronic relays FBS breakers replacement continues and micro - processor upgrades Continue SCADA RTU replacements OCB, Airblast, high SF6 leak rate Electro - mechanical None At fialure;not supported by vendor;or as required to meet project specs Driven by capacity needs and failures Driven by capacity needs and failures Replaced when End - of - life 28 loading exceeds replacements. capacity or on failure. 30 Split winding 50MVA units proactive 31 Yes 32 Replace on loading or testing 37 Driven by capacity needs and failures Yes - nearly completed None 98 Thank you for your Input and Participation! Your Presenters Dave Canon [email protected] 817-980-7909 Debi McLain Cook [email protected] 760-272-7277 Ken Buckstaff [email protected] 310-922-0783 Dave Carter [email protected] 414-881-8641 Tim. Szybalski [email protected] 301-535-0590 About 1QC First Quartile Consulting is a utility-focused consultancy providing a full range of consulting services including continuous process improvement, change management, benchmarking and more. You can count on a proven process that assesses and optimizes your resources, processes, leadership management and technology to align your business needs with your customer’s needs. Visit us at www.1stquartileconsulting.com | Follow our updates on LinkedIn Satellite Offices Corporate Offices California 400 Continental Blvd. Suite 600 El Segundo, CA 90245 (310) 426-2790 Maryland New York | Texas | Washington | Wisconsin 3 Bethesda Metro Center Suite 700 Bethesda, MD 20814 (301) 961-1505 99 Substation practice Questions 2014 Proposed by Process ◼ Asset Management ◼ Strategy Substation automation Mobile spares ◼ Sustain Substations Maintenance planning Field maintenance Including NERC standards Replacement/upgrades ◼ Expand Substations Planning/Engineering/ Design Job estimating Field Construction Strategy - Mobile Spares •Role of spares/mobiles in overall strategy •Decision support tools used for optimality of mobile/spares inventory Sustain Substations •Number of different facilities out of which field personnel work •Most important initiative underway to improve Sub maintenance practices •Changed maintenance cycle times for major pieces of equipment and why •Changes in the degree of specialization of field work force •WMS Vendor and year of implementation or last major upgrade: Substation •Regular inspections performed at Substations •Inspections added at Substations in the last year •Maintenance deferred or reduced that have NOT caused problems •Maintenance deferred or reduced that has caused problems •Actions undertaken to reduce the occurrence of outage causes: Failed Protection System Equipment; Failed AC Substation Equipment Expand Substations Planning/Engineering/Design •Substation standards changed recently and why •Substation automation initiatives: RTU replacement; On -line monitoring; LTC position indicators; Integrated digital fault recorder systems; Microprocessor protective control relaying systems; Equipment/facility monitoring systems; Other •Software products used /evaluated for substation job estimating •Involving construction in developing job estimates •Estimate Accuracy -- % of projects completed within +/ - noted % •Average "Actual as a % of Estimate” 100 Key Success Factors: strategic planning Develop Substation Automation Strategy; includes RTU replacement, on-line monitoring, microprocessor relaying system; digital fault locating Assure NERC Compliance; including substation maintenance documentation Update Standards; multiple standards, including mitigation of copper theft 101 Key Success Factors: Maintenance programs Understand and comply with NERC requirements Conduct regular inspections, and analyze the results to drive maintenance activity Review inspection program and maintenance cycles, using advanced analytic tools Coordinate maintenance activity with the asset management function, to get the most from both maintenance and capital replacement . Use mobile spares to reduce outage durations 102 Key Success Factors: design and construction Use multiple tools for estimating process Involve construction in job estimating Set and monitor estimating accuracy Use Work Management Systems for scheduling jobs (SAP and Maximo are most used) Review Specialization of Field Workforce 103 Thank you for your Input and Participation! Your Presenters Dave Canon [email protected] 817-980-7909 Debi McLain Cook [email protected] 760-272-7277 Ken Buckstaff [email protected] 310-922-0783 Dave Carter [email protected] 414-881-8641 Tim. Szybalski [email protected] 301-535-0590 About 1QC First Quartile Consulting is a utility-focused consultancy providing a full range of consulting services including continuous process improvement, change management, benchmarking and more. You can count on a proven process that assesses and optimizes your resources, processes, leadership management and technology to align your business needs with your customer’s needs. Visit us at www.1stquartileconsulting.com | Follow our updates on LinkedIn Satellite Offices Corporate Offices California 400 Continental Blvd. Suite 600 El Segundo, CA 90245 (310) 426-2790 Maryland New York | Texas | Washington | Wisconsin 3 Bethesda Metro Center Suite 700 Bethesda, MD 20814 (301) 961-1505 104