Modernisation of EHV Transmission System
Download
Report
Transcript Modernisation of EHV Transmission System
RESTRUCTURED APDRP-II IN XI PLAN
Scope of Part - B :
Strengthening of Distribution System.
Fund Allocation of Part - B:
Proposed fund allocation Rs 40,000 Cr.
1
Steps for Preparation of DPR
Collection of data
Physical,
Loading,
Losses,
Voltages
Computerise Data
Validate Data
Benchmark Performance Parameters
Prioritise feeders/DTs
Group feeders for Optimisation
Contd…
2
Steps for Preparation of DPR
Evaluate options
R&M,
Augmentation,
New Work
Cost benefit analysis
Prioritise & Shortlist
Finalisation of DPR & submission to nodal
agencies
3
Contents of DPR
1. Executive Summary
Introduction
Objective
Scope & Cost Estimate
Benefits
Implementation Schedule
Payback Period
4
Contents of DPR
2. Town/circle profile & organization setup
Consumers profile
Existing distribution system with sources of supply
Details of sub stations, feeders, DTs with electrical
and physical boundaries etc.
History of Load growth & Consumer growth
Power and energy flow details
Metering details at all voltage levels
HT/LT Ratio
Organisation Setup
5
Contents of DPR
3. Commercial performance
Billing details
Input Energy
Billed Energy
Revenue Billed
Revenue Realised
T&D and AT&C losses
Feeder outage and reliability index
Power & Distribution transformer failure rate
6
Contents of DPR
4. Constraints & Difficulties in the existing system
Adequacy of EHV transformation capacity for
supply of power
Adequacy of Sub Transmission capacity at 66kV
or 33 kV level sub stations
Overloading of 66kV or 33 kV, 11 kV and 440
volts feeder
Overloading of distribution transformers
7
Contents of DPR
5. Scope of R&M works for
Existing Sub station
Feeders (including reconductoring, Bifurcation,
Segregation, Conversion to under ground cable,
Conversion to Arial Bunch Cable (ABC) etc.
Distribution Transformers
Service connection
8
Contents of DPR
6. Scope of New Works for
New Sub station
New Feeders
High Voltage Distribution System (HVDS)
New DTs
Capacitor bank - HT & LT
New Service connection
9
Contents of DPR
7. Project Implementation schedule
Schedule for NIT,OBD & LOA.
Schedule for Project Execution
10
Contents of DPR
COST BENEFIT ANALYSIS
Estimated cost of the scheme
Increase in annual revenue due to
o Increased energy consumption (Load growth)
o Reduction in technical losses
o Reduction of commercial losses
Total annual benefit
Payback period
11
Contents of DPR
Bench marks of performance (Yearly)
Sl
Benchmark Parameter
a)
Metering efficiency (Input Vs.
metered energy)
b)
Collection efficiency (amount
collected to amount billed)
c)
Transmission & Distribution losses
d)
DT Failure rate
e)
Number of feeder outages
f)
Period of feeder outages
g)
Reliability Index
h)
Number of consumer complaints
i)
Consumer complaint disposal time
k)
AT&C Loss
Present
Level
Level to be
achieved
Date by which parameter
would be achieved