Site Location
• Located 1.3 miles
south of downtown
Collinsville
• 60 acres
• Bounded by:
– Garnett/RR to east
– Strip mine pit to
south
– Acreage to west
– Faith Assembly
Church to north
Site History
1914-1925: Active Zinc
Smelter and Lead Roaster
1999: Listed on the National
Priority List (NPL)
2008: Record of Decision
(ROD) issued
February 2, 2015: Proposed
Plan announced
Areas that Require Cleanup
• Pink - areas that
require cleanup
• Green - areas that
do not require
cleanup
• COCs include
arsenic, cadmium,
and lead
Proposed Plan for Cleanup
• Consolidation and capping of soil,
sediment, and waste materials on-site
• Remedy will not include:
1. Five-foot vertical separation between waste
and groundwater
2. Stabilization of waste
• Proposed Plan remedy offers equivalent
protection
Cleanup Goals
Site-Specific PRGs by Medium
COC
Site-Specific PRG
Soil, Residential (mg/kg) or (ppm)
Arsenic
37
Cadmium
75
Lead
500
Soil, Nonresidential (mg/kg) or (ppm)
Arsenic
200
Cadmium
560
Lead
1,000
Surface Water (μg/L) or (ppb)
Cadmium
238
Sediment (mg/kg) or (ppm)
Arsenic
181
Cadmium
813
Lead
500
• Protect human health
and the environment
• Impacts above cleanup
goals and visual smelter
waste will be addressed
Site Design
Site Design
Stormwater Management
Tentative Schedule
• Procurement of a Contractor – 30 to 60
days
• Pre-Construction Tasks – 45 days
• From Mobilization to Substantial
Completion of On-site Activities – 10
months
Activities during that 10 month
period
• Site Mobilization
• Clear and Grub
• Soil and Sediment Erosion Control
• Decontamination Area
• Dewatering the Ponds
• Waste, Soil, and Sediment Consolidation
• Confirmation Sampling
• Remove Existing Wells/Install O&M Wells
• Site Grading and Seeding
• Demobilization
Protective Elements
• Health & Safety Plan
• Transportation Plan
• Decontamination Plan
• Dust Suppression Plan
• Site Management Plan
• Stormwater Management Plan
Site at Completion
Perimeter Sign
Operation and Maintenance
Locations to review site
documents:
• Collinsville Public Library
• Oklahoma Department of Environmental
Quality
• Central Records Division
• http://www.deq.state.ok.us/lpdnew/SF/Tuls
aFuels.htm
• United States Environmental Protection
Agency
Your input on the Proposed
Plan is important to us
Ways to Comment on the Proposed Plan:
• Orally at tonight’s meeting
• By Letter to: ODEQ, Rachel Hanigan, 707 N.
Robinson, P.O. Box 1677, Oklahoma City, OK
73101-1677
• By Email to: [email protected] or
[email protected]
Comments must be postmarked or emailed by
Monday, March 2, 2015.
Questions or Comments?