Transcript Slide 1

Notice and Opportunity for Public Comment
Amendments to PFC Applications 2 and 3
Maryland Aviation Administration
Baltimore/Washington International Thurgood Marshall Airport
May 8, 2007
Terminology and Amendment Overview
• In this amendment, the Maryland Aviation Administration (MAA)
proposes to:
– Amend down Application 2 (94-02-C-01-BWI) by $51,466,477 (-18.1%)
to reflect MAA early defeasance of the Series 1994 bonds, which
minimized interest costs
– Amend up Application 3 (95-03-U-00-BWI) by $674,840 (+29.8%)
• PFC costs of the Terminal Roadway Improvement and Expansion of
BWI Fire/Rescue Facility projects increased by more than 25%
– When PFC project costs increase by more than 25%, Federal Aviation
Administration regulations require an opportunity for public comment
• MAA’s amended PFC application is summarized as follows:
– PFC Level: $4.50 per eligible enplaned passenger
– Estimated charge expiration date for Application 6 after amendments:
December 31, 2015
Amendments to PFC Applications 2 and 3
Public Consultation Materials
May 8, 2007
1
Maryland Aviation Administration
Baltimore/Washington International Thurgood Marshall Airport
Summary of Proposed Amendments
Project
Previously
approved use
authority
Proposed
change
Proposed
amendment
% chg
PFC APPLICATION 94-02-C-01-BWI
New International Terminal
$198,863,739
($45,335,821)
$153,527,918
(22.8%)
14,872,897
(1,486,507)
13,386,390
(10.0%)
9,828,817
4,798,318
14,627,135
48.8%
Pier C Extension
39,659,611
(2,972,322)
36,687,289
(7.5%)
Aircraft Deicing Facilities
20,571,319
(6,470,145)
14,101,174
(31.5%)
$283,796,383
($51,466,477)
$232,329,906
(18.1%)
$2,261,000
$674,840
$2,935,840
29.8%
$2,261,000
$674,840
$2,935,840
29.8%
Runway 10/28 Extension
Terminal Roadway Improvements
TOTAL
PFC APPLICATION 95-03-U-00-BWI
Expansion of BWI Fire/Rescue Facility
TOTAL
Note: Projects requiring consultation are noted in italics, as the proposed change is 25% or more of the
previously approved use authority.
Amendments to PFC Applications 2 and 3
Public Consultation Materials
May 8, 2007
2
Maryland Aviation Administration
Baltimore/Washington International Thurgood Marshall Airport
Projects with Opportunity for Public Comment
TERMINAL ROADWAY IMPROVEMENTS
Project description:
This project consisted of the design and construction of
improvements to the terminal access roadways at the Airport
including the widening of Elm Road, reconstruction of the existing
terminal mall loop roadway, and the widening of the lower-level
outer roadway.
Reason for amendment: This project is being amended to account for final capital costs,
which increased principally due to unanticipated utility relocation
expenses and updated requirements for manholes and ductbanks.
EXPANSION OF BWI FIRE/RESCUE FACILITY
Project description:
This project consisted of the design and construction of a new
Aircraft Fire/Rescue facility at the Airport.
Reason for amendment: This project is being amended to account for final capital costs.
The final project incorporated communication systems
enhancements to interface with other MAA systems. Additionally,
project costs increased due to unanticipated expenses for utility
relocations.
Amendments to PFC Applications 2 and 3
Public Consultation Materials
May 8, 2007
3
Maryland Aviation Administration
Baltimore/Washington International Thurgood Marshall Airport
Public Comment Period
• In accordance with Federal Aviation Administration
regulations, the public is given an opportunity for
comment on the proposed amendments through
June 7, 2007
• Comments should be sent to:
Mr. Jeffrey B. Williams
Senior Financial Analyst
Phone: (410) 859-7010
Fax: (410) 684-3050
Maryland Aviation Administration
901 Elkridge Landing Road
Linthicum, Maryland 21090
E-mail: [email protected]
• This notice can be downloaded at
http://www.bwiairport.com
Amendments to PFC Applications 2 and 3
Public Consultation Materials
May 8, 2007
4
Maryland Aviation Administration
Baltimore/Washington International Thurgood Marshall Airport