Transcript Fletton Parkway
Fletton Parkway Widening A1139 J17 – J2
Andy Tatt Peterborough City Council Transport and Engineering Group Manager John Holland Associate URS Infrastructure and Environment UK Ltd Scheme Project Manager
• History • Proposed Scheme • Funding • Procurement • Programme
• Scope – Widening of the section between Junctions 1 and 2; – Complete reconstruction of the eastbound carriageway between Junctions 1 and 2; – – – – – – – – Introduction of a ‘type C’ merge where the A1(M) link road joins Fletton Parkway; Link capacity improvements between junctions 17 and 2; Replacement Street Lighting between junctions 17 and 2 Resurfacing of road as necessary between junctions 17 and 2 Replacement of signage and lining as required; Installation of Average Speed Cameras to enforce a (60mph) speed limit in between J17 of the A1(M) (including the eastbound slip) and junction J3 of the Fletton Parkway.
Installation of Closed Circuit Television Cameras (CCTV); Installation of maintenance bays as required.