Transcript Larry Hoy
RTD Procurement and Construction Management Oversight for FasTracks
Larry Hoy RTD Board Member, District J
1
3
Overview of FasTracks Project
•
What is FasTracks?
The Regional Transportation District is engaged in completing a
$7.9+ billion
voter- approved capital expansion project across the 8-county region that when complete will provide:
122
miles of new rail service
18
miles of bus rapid transit
57
new stations
31
new Park-n-Rides
21,000
new parking spaces
Redevelopment
of Denver Union Station 4
2008 PPP Industry Forum
6
FasTracks Progress Progress Update
• 81 miles of rail and bus transit in construction or soon to begin construction • Current construction includes: – West line just completed – three more under construction. – Segment of a fifth line I-225 – Bus Rapid Transit (BRT) project Denver to Boulder – Denver Union Station
BOARD’S Role During Procurement and Construction Process (continued)
• • • • • • • • •
Use Committee Structure to Approve Contracts and Review of Procurement/construction Milestones
Board Approval of initial application for Public-Private Partnership Pilot project (Penta-P) Board Approval of Final PPP Application to FTA Board’s Approval to hire Outside legal counsel with expertise in this area Board’s approval of the P3 goals and Milestones Board’s Review/Approval of the RFP Process proposal Board Approvals of Key Intergovernmental Agreements (IGAs) Board’s approval of the Selection of the Eagle P3 Concessionaire Team Board’s approval of Purchase and Sale of Railroad Right of Way (ROW) 9
Denver Union Station Panoramic View
10